ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021

H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
0 IBS Campus, Infopark, Cochin (R4) dtd 02042018 1126 days4/26/2017 1/11/2021
1 1.)Project Kickoff Meeting with PMC 100 days 4/26/2017 8/23/2017
2 2.)Project Initiation 25 days 4/27/2017 5/26/2017
6 3.)Pre-Construction 604 days 5/4/2017 4/29/2019
22 4.)Construction Management 1093 days 4/26/2017 12/1/2020
23 4.1.)Piling and pile related works 526 days 5/4/2017 1/23/2019
38 4.2.)Main works 939 days 4/26/2017 5/30/2020
39 4.2.1.)Preliminary works 15 days 2/26/2018 3/14/2018
43 4.2.2.)Building Structure Works (Incl. Civil and Structural)
939 days 4/26/2017 5/30/2020
44 4.2.2.1)Below Basement 1(-)2.5m Lvl 319 days 3/14/2018 3/30/2019
46 4.2.2.2.)Above Basement 1 (-)2.5m Lvl upto GF (0.00m)
907 days
Lvl 4/26/2017 4/22/2020
47 Retaining wall 344 days 4/26/2017 6/12/2018
48 Roof Slab concreting 300 days 4/26/2019 4/22/2020
49 Basement Floor 50 days 4/26/2019 6/25/2019
50 Ground Floor 46 days 6/8/2019 7/31/2019 49FF+31 days
51 First Floor 50 days 6/19/2019 8/16/2019 50SS+9 days
52 Second Floor 44 days 7/12/2019 9/2/2019 51FF+14 days
53 Third Floor 44 days 7/29/2019 9/18/2019 52FF+14 days
54 Fourth Floor 43 days 8/13/2019 10/3/2019 53FF+12 days
55 Fifth Floor 34 days 9/11/2019 10/21/2019 54FF+15 days
56 Sixth Floor 33 days 9/27/2019 11/6/2019 55FF+13 days
57 Seventh Floor 32 days 10/16/2019 11/22/2019 56FF+14 days
58 Eighth Floor 32 days 11/1/2019 12/7/2019 57FF+13 days
59 Ninth Floor 31 days 11/18/2019 12/23/2019 58FF+13 days

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 1
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
60 Tenth Floor 32 days 12/2/2019 1/9/2020 59FF+13 days
61 Eleventh Floor 32 days 12/16/2019 1/24/2020 60FF+12 days
62 Twelfth Floor 31 days 1/3/2020 2/8/2020 61FF+13 days
63 13th Floor 30 days 2/5/2020 3/12/2020 62FF+26 days
64 Terrace Floor 27 days 2/26/2020 3/30/2020 63FF+14 days
65 Head room 17 days 4/3/2020 4/22/2020 64FF+20 days
66 Post tensioning works 277 days 5/22/2019 4/20/2020 64FF+18 days
67 4.2.2.3.)Civil Finishes 230 days 8/27/2019 5/30/2020
68 Substructure 36 days 8/27/2019 10/8/2019
69 Basement 1 36 days 8/27/2019 10/8/2019
70 Brickwork 34 days 8/27/2019 10/5/2019 53FS-20 days
71 Plastering 34 days 8/29/2019 10/8/2019 70SS+2 days
72 Super Structure 209 days 9/20/2019 5/30/2020
73 Ground floor 209 days 9/20/2019 5/30/2020
74 Brickwork 21 days 9/20/2019 10/15/2019 70FS-13 days,49
75 Plastering 21 days 9/26/2019 10/21/2019 74SS+5 days
76 Ist Floor 22 days 10/4/2019 10/30/2019
77 Brickwork 18 days 10/4/2019 10/24/2019 74FS-10 days,50
78 Plastering 18 days 10/9/2019 10/30/2019 77SS+4 days
79 2nd Floor 28 days 10/14/2019 11/15/2019
80 Brickwork 24 days 10/14/2019 11/11/2019 77FS-10 days,51
81 Plastering 26 days 10/16/2019 11/15/2019 80FF+4 days
82 3rd Floor 30 days 10/19/2019 11/23/2019
83 Brickwork 26 days 10/19/2019 11/19/2019 80FS-20 days,55FS-2 days

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 2
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
84 Plastering 26 days 10/24/2019 11/23/2019 83SS+4 days
85 4th Floor 31 days 11/5/2019 12/10/2019
86 Brickwork 26 days 11/5/2019 12/4/2019 83SS+13 days
87 Plastering 26 days 11/11/2019 12/10/2019 86SS+5 days
88 5th Floor 28 days 11/22/2019 12/24/2019
89 Brickwork 24 days 11/22/2019 12/19/2019 86SS+15 days
90 Plastering 24 days 11/27/2019 12/24/2019 89SS+4 days
91 6th Floor 27 days 12/9/2019 1/10/2020
92 Brickwork 23 days 12/9/2019 1/6/2020 89SS+14 days
93 Plastering 24 days 12/12/2019 1/10/2020 92SS+3 days
94 7th Floor 29 days 12/21/2019 1/27/2020
95 Brickwork 24 days 12/21/2019 1/21/2020 92SS+11 days
96 Plastering 24 days 12/28/2019 1/27/2020 95SS+5 days
97 8th Floor 29 days 1/8/2020 2/11/2020
98 Brickwork 25 days 1/8/2020 2/6/2020 95SS+13 days
99 Plastering 25 days 1/13/2020 2/11/2020 98SS+4 days
100 9th floor 30 days 1/24/2020 2/28/2020
101 Brickwork 25 days 1/24/2020 2/22/2020 98SS+13 days
102 Plastering 25 days 1/30/2020 2/28/2020 101SS+5 days
103 10th Floor 29 days 2/8/2020 3/14/2020
104 Brickwork 24 days 2/8/2020 3/7/2020 101SS+13 days
105 Plastering 25 days 2/13/2020 3/14/2020 104SS+4 days
106 11th Floor 28 days 2/25/2020 3/30/2020
107 Brickwork 24 days 2/25/2020 3/24/2020 104SS+13 days

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 3
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
108 Plastering 24 days 2/29/2020 3/30/2020 107SS+4 days
109 12th Floor 29 days 3/12/2020 4/15/2020
110 Brickwork 25 days 3/12/2020 4/10/2020 107SS+13 days
111 Plastering 24 days 3/18/2020 4/15/2020 110SS+5 days
112 13th Floor 29 days 3/28/2020 4/30/2020
113 Brickwork 25 days 3/28/2020 4/25/2020 110SS+13 days
114 Plastering 25 days 4/2/2020 4/30/2020 113SS+4 days
115 Attic Floor 29 days 4/15/2020 5/19/2020
116 Brickwork 25 days 4/15/2020 5/14/2020 113SS+15 days
117 Plastering 25 days 4/20/2020 5/19/2020 116SS+4 days
118 Terrace Floor 26 days 4/30/2020 5/30/2020
119 Brickwork 25 days 4/30/2020 5/29/2020 116SS+13 days
120 Plastering 21 days 5/7/2020 5/30/2020 119SS+5 days
121 Roof floor 22 days 4/23/2020 5/19/2020
122 Brickwork 16 days 4/23/2020 5/12/2020 116SS+7 days
123 Plastering 18 days 4/28/2020 5/19/2020 122SS+4 days
124 Common area finishes 192 days 11/11/2019 6/29/2020
125 External plastering 150 days 11/13/2019 5/13/2020 72FF-15 days
126 False ceiling 180 days 11/11/2019 6/15/2020 152SS+30 days
127 Flooring, wall cladding etc. 131 days 1/11/2020 6/17/2020 117FF+15 days,83,120FF+15 days,123FF+15 days
128 Internal painting 160 days 12/18/2019 6/29/2020 77,127FF+10 days
129 4.4.)External Finishes -(Painting/Cladding/ACP) 178 days 2/12/2020 9/12/2020
130 Cladding Works (ACP or Stone) 90 days 3/20/2020 7/4/2020 131SS+30 days
131 Façade Glazing Works 178 days 2/12/2020 9/12/2020 125SS+75 days

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 4
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
132 4.5.)External Development 491 days 4/20/2019 12/1/2020
133 Compound Wall 114 days 12/4/2019 4/21/2020
134 Substation 130 days 5/2/2019 10/3/2019 50SS-31 days
135 STP 139 days 6/1/2019 11/14/2019
136 Security Cabin 93 days 12/2/2019 3/24/2020 133SS-2 days
137 Service trench 116 days 12/4/2019 4/23/2020 133SS
138 Entrance Area 131 days 1/3/2020 6/9/2020 137SS+24 days
139 Landscape & Hardscape 200 days 3/26/2020 11/19/2020 136
140 4.3.)MEP Package 480 days 4/20/2019 11/18/2020
141 Initiation 32 days 4/30/2019 6/7/2019
142 Client-PM-Vendor Kickoff Meeting 1 day 4/30/2019 4/30/2019 21
143 Submission of OHSE Plan 6 days 5/2/2019 5/8/2019 142
144 Approval of OHSE Plan 13 days 5/9/2019 5/23/2019 143
145 Submission of QA/QC Plan & Method Statements6 days 5/24/2019 5/30/2019 144
146 Approval of QA/QC Plan & Method Statements 6 days 5/31/2019 6/7/2019 145
147 4.3.1.)Electrical 420 days 4/20/2019 9/7/2020
148 Low side works 420 days 4/20/2019 9/7/2020
149 Conduting 350 days 4/20/2019 6/15/2020 49SS-5 days
150 Light & Power wiring 280 days 8/6/2019 7/8/2020 149SS+90 days
151 Cable tray works 280 days 9/4/2019 8/5/2020 150SS+24 days
152 DB fixing 280 days 10/5/2019 9/7/2020 151SS+26 days
153 LT cable laying 280 days 9/21/2019 8/25/2020 151SS+15 days
154 Electrical final fix 60 days 6/18/2020 8/28/2020 128FF+50 days
155 High side 190 days 1/22/2020 9/5/2020

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 5
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
156 Installation of RMU and HT panel 170 days 1/22/2020 8/11/2020 134FS+90 days
157 HT cabling 15 days 8/12/2020 8/31/2020 156FF+15 days
158 Transformer installation 90 days 3/17/2020 7/1/2020 156SS+45 days
159 HT and LT panel installation 120 days 4/4/2020 8/25/2020 134FS+90 days,158FF+45 days
160 Busduct Installation 40 days 7/20/2020 9/5/2020 159FF+10 days
161 4.3.2.)HVAC 250 days 10/11/2019 8/6/2020
162 Low side works 220 days 10/11/2019 7/2/2020
163 Ducting and installation works 180 days 11/5/2019 6/9/2020 126SS-5 days
164 Chilled water line 220 days 10/11/2019 7/2/2020 163SS-20 days
165 Highside works 160 days 1/29/2020 8/6/2020
166 Chillers installation 60 days 4/11/2020 6/20/2020 64FS+10 days
167 Cooling Towers Installation 60 days 4/23/2020 7/2/2020 166FF+10 days
168 Chilled water line-external and raising lines 160 days 1/29/2020 8/6/2020 167FF+30 days
169 4.3.3.)PHE 315 days 10/24/2019 11/6/2020
170 External plumbing 75 days 7/4/2020 10/1/2020
171 Seewage line & Manholes 75 days 7/4/2020 10/1/2020 139FF-40 days
172 Water lines 75 days 7/4/2020 10/1/2020 171SS
173 Rain water lines 75 days 7/4/2020 10/1/2020 172SS
174 Internal Plumbing 315 days 10/24/2019 11/6/2020
175 Piping in shafts/walls - water/drainage/rain 220 days 10/24/2019 7/15/2020 116FF+10 days,119FF+10 days,122FF+55 days
176 Pumps installation 30 days 8/8/2020 9/14/2020 177FF+5 days
177 Piping & connections at Terrace 45 days 7/16/2020 9/8/2020 175
178 Sanitary ware & fixtures installation 60 days 8/28/2020 11/6/2020 176FF+45 days
179 4.3.4.)FPS 290 days 10/16/2019 9/29/2020

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 6
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
180 Fabrication and erection of header and branches 250 days 10/16/2019 8/11/2020 54FS+10 days
181 Postion welding 255 days 10/29/2019 8/31/2020 180SS+10 days
182 Hydraulic testing 255 days 11/9/2019 9/11/2020 181SS+10 days
183 Cabling for FAS 260 days 11/9/2019 9/17/2020 182SS
184 Fire pump room works 45 days 8/6/2020 9/29/2020 182FF+15 days
185 4.3.5.)Elevators 125 days 5/11/2020 10/6/2020
186 Electromechanical work 100 days 5/11/2020 9/5/2020 180FS-80 days
187 Slow speed commissioning 15 days 9/7/2020 9/23/2020 186
188 High speed commissioning 10 days 9/24/2020 10/6/2020 187
189 4.3.6.)STP 140 days 2/8/2020 7/24/2020
190 Mechanical works 90 days 2/8/2020 5/27/2020 135FS+70 days
191 Electrical and automachine works 30 days 5/28/2020 7/1/2020 190
192 Dry run testing 10 days 7/2/2020 7/13/2020 191
193 Wet run testing 10 days 7/14/2020 7/24/2020 192
194 4.3.7.)Security Systems 90 days 3/2/2020 6/17/2020
195 Access Control cabling 90 days 3/2/2020 6/17/2020 128FF-10 days
196 CCTV cabling 90 days 3/2/2020 6/17/2020 195SS
197 4.3.8.) DG works 135 days 6/10/2020 11/18/2020
198 DG installation and associated works 60 days 8/27/2020 11/5/2020 199FS+5 days
199 Exhaust stack 60 days 6/10/2020 8/19/2020
200 Associated electrical works 15 days 10/31/2020 11/18/2020 198FF+10 days
201 MEP final fixtures 60 days 8/24/2020 11/2/2020 128FS+45 days
202 Testing and commissioning 75 days 8/12/2020 11/10/2020 185FF+30 days
203 Authority approvals 61 days 9/19/2020 12/1/2020

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 7
ID Task Name Duration Start Finish Predecessors 2017 2018 2019 2020 2021
H2 H1 H2 H1 H2 H1 H2 H1 H2 H1 H2
204 CEIG inspection 30 days 9/19/2020 10/24/2020 147FS+10 days
205 Lift inspection 15 days 9/30/2020 10/17/2020 185FF+10 days
206 Fire inspection 15 days 10/27/2020 11/12/2020 205FS+7 days
207 Occupation certificate 15 days 11/14/2020 12/1/2020 206FF+15 days
208 5.)Post-Construction 81 days 10/6/2020 1/11/2021
209 Snagging and desnagging works 60 days 10/6/2020 12/15/2020 132FF+12 days,140FF+5 days
210 Package technical closure 40 days 11/5/2020 12/22/2020 202FF+35 days
211 Package commercial closure 40 days 11/18/2020 1/5/2021 210FF+10 days
212 Handing Over/Taking Over and Move in 15 days 12/23/2020 1/11/2021 210

Task Inactive Milestone Deadline


Split Inactive Summary Late
Milestone Manual Task Critical
Project: IBS Campus, Infopark, Co Summary Duration-only Critical Split
Date: 4/9/2019 Project Summary Manual Summary Rollup Progress
External Tasks Manual Summary Manual Progress
External Milestone Start-only Slippage
Inactive Task Finish-only

Page 8