Professional Documents
Culture Documents
#Project Management Summary Notes For PMP Exam - A Quick Refreshing Guide For PMP Exam Based On PMBOK 6th Edition
#Project Management Summary Notes For PMP Exam - A Quick Refreshing Guide For PMP Exam Based On PMBOK 6th Edition
1
Project Management Concepts
Ready Reckoner
By SN Panigrahi
Essepee Business Solutions
A Project may be a set of interrelated tasks to be executed over a fixed period and within
certain cost, time and other limitations.
Project Management
Set of knowledge, skills, best practices, tools and techniques that have significant impact
on project objectives and successful project outcome
Unique
Unique Product or Service or Result or Outcome
Outcome
New & Different from the Previous
Progressive Elaboration
Initially Plans are made on Broad basis, and Details are done
Don’t confuse it with changes. In progressive elaboration, there is no
as the project progressing change in requirement, its only requirement detailing.
Approved Budget
wh co
e
What can go Wrong
Co
er be d th
e
at st?
Required to do the
Resources
m
l
sh
s
?
Ti
ou
Ou n s
t
ed
li v ut
about it
Risk
ld
e
wh
Work
Quality
it
By
How Close the
Outcome meets
the Customer
Requirements?
Scope
If any one of these factors changes, What work to be
then at least one of the other factors done & Expected?
also will change.
SN Panigrahi, Essenpee Business Solutions, India 11
Corporate Top Level Strategies
Related Projects, Programs, Decision Making,
Prioritization,
Portfolio Or Sub-portfolios, and Review,
un-related Operations Realignment, and
Reprioritization of a firm’s projects.
Focuses on interdependencies
Program
Only Projects between projects to determine
optimal approach for managing them
Related - Managing groups of projects in a
coordinated way
Strategies with
Organizational
Organizational
Aligning Harmonizes its projects and program
Project Program components and controls interdependencies.
Management Management Focusses on Optimal Approach for Managing
(OPM)
them
The project manager must set the final goal for the project and
motivate his/her team to complete the project on time.
The project manager must assess and monitor risks to the project
and mitigate them.
Predictive When scope, time, and cost are defined within the early phases of the project. Any
changes must then be carefully managed through Change Control Mechanism. Also
Life Cycle known as waterfall life cycles
Iterative Scope is determined at an early point of the life cycle but time and cost estimates are revisited
as the understanding of the product develops. Iterations develop the product through a series
Life Cycle of repeated lifecycles, while increments successively add to the functionality
The deliverable is produced through a series of iterations that successively add functionality
Incremental within a predetermined time frame. The deliverable contains the necessary and sufficient
Life Cycle capability to be considered complete only after the final iteration
Adaptive Adaptive – either agile, incremental, or iterative in nature, the detailed scope is defined and
approved before the start of an iteration. This is also called agile or change-driven life cycles
Life Cycle
SN Panigrahi, Essenpee Business Solutions, India
Project and Development Life Cycles – Different types
Hybrid (Combination of Predictive (Waterfall) and Adaptive): Elements of the project that have fixed requirements
follow predictive approach, elements that are ‘Progressively Elaborated’ follow an adaptive (iterative) approach
21
Characteristics of Project Lifecycle
The generic life cycle structure
commonly exhibits the
following characteristics:
At the start, cost and staffing
levels are low and reach a
peak when the work is in
progress. It again starts to drop
rapidly as the project begins to
halt.
The typical cost and staffing
curve does not apply to all
projects. Considerable
expenses are required to
secure essential resources early SN Panigrahi, Essenpee Business Solutions, India 22
Characteristics of Project Lifecycle
Stakeholder influence, Risk and
uncertainty are at their peak at the
beginning of the project. These factors
drop over the lifecycle of the project as
decisions are reached, and deliverables
are accepted.
The ability to affect the final product of
the project without impacting the cost
drastically is highest at the start of the
project and decreases as the project
advances towards completion.
The cost of making new changes and
rectifying errors are initially low and
increases as the project approaches
completion. SN Panigrahi, Essenpee Business Solutions, India
23
SN Panigrahi, Essenpee Business Solutions, India 6th
24
Progressive Elaboration
Progressive elaboration allows a project management team to define work and manage it to a greater
level of detail as the project evolves. Plan keep on changing and we get better clarity as we build on the
various plans.
Planning is an iterative process. Often times, it’s difficult to do detailed planning of a project in the
beginning. As the project evolves, and more specific and accurate details are available, the planning
gets more detailed. With each successive iteration of the planning process, the project plan becomes
more elaborate and complete. This approach to planning is known as Progressive Elaboration.
Total
49
Processes
The Inputs, Tools, Techniques and Outputs (ITTOs) of each
Process is laid out
SN Panigrahi, Essenpee Business Solutions, India 27
5 Project Management Process Groups
As Per PMBOK –
6th Edition INITIATING Decide Why
Develop Project Charter this Project
with Defined Objectives
Get It Processes - 2 What & How
Track &
Check Do it as
MONITORING & Planned
EXECUTING
CONTROLLING
Directing and Managing
Measuring & Taking Corrective
Project Execution
Measures
Processes - 12 SN Panigrahi Processes - 10 28
Throughout the lifecycle of the
project, a set of processes such as
initiation, planning, execution and
closing and overall monitoring &
controlling and Closing have to be
followed.
Scope • Ensure the project includes all the work required, and only the work required, to complete the
6
Mgt project successfully
Quality • Incorporating the organization’s quality policy regarding planning, managing and controlling
3
Mgt project and product quality requirements in order to meet stakeholders’ expectations.
Resource • Identify, acquire, and manage the resources needed for the successfully completion of the
6
Mgt project.
Communications • Required to ensure the planning, creation, distribution, control and monitoring of project
3
Mgt information's
SN Panigrahi
Risk • Planning risk management, the identification, analysis, and monitoring of risks on a project,
7
Mgt and the implementation of risk responses.
Procurement • Necessary to purchase or acquire products, services, or results needed from outside the
3
Mgt project team.
• Required to identify stakeholders, to analyze their expectations and impact on the project,
Stakeholder and to develop management strategies for effectively engaging stakeholders in decisions that 4
Mgt affect the project.
Total
SN Panigrahi, No. Business
Essenpee of Processes
Solutions, India 49 30
Project Management Process Group and Knowledge Area Mapping
Knowledge Areas Initiating Process Planning Process Group Executing Process Group Monitoring & Controlling Closing Process Group
Group Process Group
3.Direct and Manage 5.Monitor and Control
4. Project Integration 4.1 Develop Project 4.2 Develop Project Project Work 4.7 Close Project or
Project Work
Management Charter Management Plan 6.Perform Integrated Phase
4.Manage Project
Knowledge Change Control
1. Plan Scope Management
5. Project Scope Management 2. Collect Requirements 5. Validate Scope
3. Define Scope 6. Control Scope
4. Create WBS
1. Plan Schedule Management
6. Project Schedule 2. Define Activities
3. Sequence Activities 6.6 Control Schedule
Management
4. Estimate Activity Durations
5. Develop Schedule
7. Project Cost Management 1. Plan Cost Management
2. Estimate Costs 7.4 Control Costs
3. Determine Budget
8. Project Quality Management 8.1 Plan Quality Management 8.2 8.3 Control Quality
9. Project Resource 1. Plan Resource Management 3. Acquire Resources 9.6 Control Resources
Management 2. Estimate Activity Resources 4. Develop Team
5. Manage Team
10. Project Communications 10.1 Plan Communications
Management Management 10.2 Manage Communications 10.3 Monitor Communications
1.Plan Risk
Management
11. Project Risk Management 2.Identify Risks 11.6 Implement Risk Responses 11.7 Monitor Risks
3.Perform Qualitative
Risk Analysis
4.Perform Quantitative
Risk Analysis
5.Plan Risk Responses
12. Project Procurement
Management 12.1 Plan Procurement
Management 12.2 Conduct Procurements 12.3 Control Procurements
13. Project Stakeholder 13.1 Identify 13.2 Plan Stakeholder 13.3 Manage Stakeholder 13.4 Monitor Stakeholder
Management Stakeholders Management Engagement Engagement
SN Panigrahi, Essenpee Business Solutions, India 31
SN Panigrahi, Essenpee Business Solutions, India 32
Systems Approach to Project Management
PMBOK® describes the fundamentals of project A Project can be viewed as a Total System which
management in terms of processes. Each Transforms Input into Output, and has a
Project Management Activity is Accomplished Feedback Mechanism to assure that the output
as a Process. A process has some Inputs. A Set
meets the goals and objectives set for the project.
of Tools and Techniques are then applied on
these inputs. As a Result some outputs are System - a set of things working together as parts of
produced. These outputs may further become a mechanism or an interconnecting network.
inputs to some other processes.
Two Processes
Identify Stakeholders
38
SN Panigrahi, Essenpee Business Solutions, India
Initiating Domain Process Group Tasks
1.Perform Project Assessment based upon available information, lessons learned from
previous projects, and meetings with relevant stakeholders, in order to support the
evaluation of the feasibility of new products or services within the given assumptions
and/or constraints.
3.Identify Stakeholders & Perform Stakeholder Analysis using appropriate tools and
techniques, in order to align expectations and gain support for the project.
4.Identify High Level Risks, Assumptions, and Constraints based on the current
environment, organizational factors, historical data and expert judgment, in order to
propose an implementation strategy.
What When
What are the Primary When is the project
Risks involved in the going to start and
Project? Primary Project Major Mile end?
Risks Charter Stones
Who What
Who all are involved What is the project
from the start of the Budget?
Project? Assumptions Broad
& Constraints Budget
Key
Signed off Stakeholders Formally
by the Project Authorizes the
Sponsor / Initiator Project Manager to
with Date SN Panigrahi, Essenpee Business Solutions, India Start the Project
41
Major Elements of Project Charter
The Six Sigma Project Charter – Elements :
The Business Case, which sets out why a project is important to an organization – the
Business Case
Need; Why Taken up – Justification; If Taken up what will be the Outcome & if Not Taken
up What will be the Consequences. Problem Statement
The Problem Statement / Opportunity Statement, which defines an issue and how it is
affecting the organization – Covers : What is the Problem (CTQ – Current) – Since When
the Problem Existing – Where is the Problem – How did you Come to Know – What is the Goal Statement
Impact
The Goal Statement, which should be in line with the problem you seek to solve, and Scope Statement
which should be SMART – Specific, Measurable, Attainable, Relevant and Time-bound.
The Scope Statement, which defines the limits of the project and shows both what should
Project Milestones
be included and what should be excluded.
The Project Milestones, outlining the key activities that need to be completed and the
projected dates of completion. Project Budget
The Project Budget, provides broad estimate of all costs that are likely to be incurred
A list of the Team Members that will be working on the project, which will depend on the Team Members
problem that needs solving and project scope.
Sign-Off with Date – Project Sponsor must Sign-off with Date in-order to Formally Lunch Sign-Off with Date
the Project
SN Panigrahi
Project Charter
Formally Authorizes the Project Manager to Start the Project
Includes the business case Explaining why the Project is Necessary & Project
Objectives
Define the High-Level Requirements, Project description and Boundaries –
Assumptions – Broad Scope & Major Milestones
Signed off by the Project Sponsor / Initiator with Name, Designation & Date
Further we create baselines for scope, schedule and cost against which we can then (in Monitoring
and Controlling) track our progress. And we continue to plan for how we will manage and engage the
all-important stakeholders throughout the project life cycle.
The primary uses of the PMP are to document planning assumptions and decisions, facilitate communication
among stakeholders, and document approved scope, cost, and schedule baselines.
By showing the major products, milestones, activities and resources required on the project, it is also a
statement of how and when a project's objectives are to be achieved.
The project manager creates the PMP following input from the project team and key stakeholders. The plan
should be agreed on and approved by at least the project team and its key stakeholders.
The PMP is mandatory for all projects. While it is a project-level document, it should be updated as
necessary, including for each increment.
4.Develop the Cost Management Plan based on the project scope, schedule,
resources, approved project charter and other information, using estimating
techniques, in order to manage project costs.
7.Develop the Procurement Management Plan based on the project scope, budget,
and schedule, in order to ensure that the required project resources will be available.
8.Develop the Quality Management Plan and define the quality standards for the
project and its products, based on the project scope, risks, and requirements, in order
to prevent the occurrence of defects and control the cost of quality.
Milestones typically Mark Critical Decision Points, the completion of major project tasks and the ends
of various project phases.
Deliverable -
Deliverable -1 Deliverable -2 Deliverable -3
4
Tangible
Quantifiable To be To a
Deliverable or
Results Delivered Customer
Intangible
Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, PMI Inc., 2017, Page 20
Client
SOW Activity
Sequencing
Activity
Definition
Work Activity Schedule
Breakdown Duration
Development
Estimate
Project Planning
Structure
Resource
Planning
Cost
Estimating
Resource
Pool Work
Packages
SN Panigrahi, Essenpee Business Solutions, India 56
Baselines
Baseline is the value or condition against which all future measurements will be
compared. The baseline is a point of reference. In project management commonly
Baseline referred baselines are – schedule baseline, cost baseline, scope baseline and quality
baseline.
It is the approved version of a schedule model with baseline start dates and baseline
Schedule Baseline finish dates..
Cost / Budget It is the approved version of the time-phased project budget, excluding any
Baseline management reserves.
58
SN Panigrahi, Essenpee Business Solutions, India
Executing Domain Process Group Tasks
1.Acquire and Manage Project Resources by following the human resource and procurement management
plans, in order to meet project requirements.
2.Manage Task Execution based on the project management plan by leading and developing the project team,
in order to achieve project deliverables.
3.Implement the Quality Management Plan using the appropriate tools and techniques, in order to ensure
that work is performed in accordance with required quality standards.
4.Implement Approved Changes and corrective actions by following the change management plan, in order to
meet project requirements.
5.Implement Approved Actions by following the risk management plan, in order to minimize the impact of
the risks and take advantage of opportunities on the project.
6.Manage the Flow of Information by following the communications plan, in order to keep stakeholders
engaged and informed.
7.Maintain Stakeholder Relationships by following the stakeholder management plan, in order to receive
continued support and manage expectations.
The Monitoring and Controlling Process Group presents a detailed set of skills and knowledge directly
applicable toward implementing the decisions needed to sustain the most active part of the project. While
moving forward with a project, a top project manager continuously reviews progress and makes necessary
adjustments to increase workflow effectiveness.
SN Panigrahi, Essenpee Business Solutions, India
60
Monitoring & Controlling Domain Process Group Tasks
Monitor and Control Project Work
Keeping stakeholders up to date on progress and team performance through reports and on-going
documentation contributes to project success. Regularly assessing progress related to scope, benchmark
goals, timeline, and budget helps to ensure that there are no unpleasant surprises as the project unfolds.
Verify Scope
As the project progresses through each phase, it is important to secure the documentation related to
completed portions of the project. Re-visiting another process groups to be sure that objectives have been
met reflecting any changes is part of the follow-through needed as the project continues toward completion.
Control Scope
If there have been adjustments to the budget, timeline, or the desired end-product, it is important to re-visit
the documentation related to the scope and mitigate any unresolved challenges. Maintaining effective
communication with stakeholders and related constituents will keep everyone updated and engaged in the
project’s success.
Control Schedule
Every project has a schedule baseline. As the project progresses adjustments are often necessary to address
unforeseen circumstances. Monitoring the project properly can decrease the chances that schedule issues
become major setbacks.
Control Costs
Many factors will affect cost throughout the project timeline. Keeping track of any changes in the budget is
important so that communication around the control of costs is clear and accurate.
From its name, it should be pretty obvious what happens here. Not only do you formally
close the project but you also Get Sign-off and Acceptance from the Customer. While
this should be self-evident, too often projects just fizzle out. People stop coming to the
meetings and everyone just shows up at the next one.
Best practice dictates that the rigor applied to the rest of the project should be applied here
as well. The project manager should formally close the project by archiving records,
holding a lessons learned session, making final payments, closing contracts and
celebrating and releasing the team.
And the lessons learned along with other historical information should be centrally
archived to be used as input to future projects to prevent reinventing the wheel.
64
SN Panigrahi, Essenpee Business Solutions, India
Closing Domain Process Group Tasks
1.Obtain Final Acceptance of the Project Deliverables from relevant stakeholders, in
order to confirm that project scope and deliverables were achieved.
2.Transfer the Ownership of Deliverables to the assigned stakeholders in accordance
with the project plan, in order to facilitate project closure.
3.Obtain Financial, Legal, and Administrative Closure using generally accepted practices
and policies, in order to communicate formal project closure and ensure transfer of
liability.
4.Prepare and Share The Final Project Report according to the communications
management plan, in order to document and convey project performance and assist in
project evaluation.
5. Collate Lessons Learned that were documented throughout the project and conduct
a comprehensive project review, in order to update the organization’s knowledge base.
6.Archive Project Documents and materials using generally accepted practices, in order
to comply with statutory requirements and for potential use in future projects and
audits.
Sacred Cow
Comparative Constrained Highest NPV Wins!
Approach Optimization Approach
Operating Highest IRR Wins!
Benefit Cost Ratio Linear programming
Necessity
Payback Period
74
Purpose of Project Management Plan (PMP)
Who will be
Involved
How it will be
Measured &
How it is to be Reported & How
Achieved information will
be
Communicated
Provide a
Purpose of Used as a
Comprehensive
Reference for
Baseline of what Project
any Decision &
has to be Management for Clarification of
achieved by the Plan (PMP) unclear areas
project
Business Case Documentation to justify the project investment. Cost benefits Analysis
Know the following two categories of project selection methods and their subsets for the
exam:
1.Benefit measurement method (comparative approach)
1. Murder Board – a panel of people who try to shoot down a new project idea
2. Peer Review
3. Scoring Models
4. Economic models – the following are economic models for selecting a project:
Project Selection
1. Present value; 2. Net present value; 3. IRR; 4. Payback period
5. Benefit-cost ratio
2.Constrained optimization methods (mathematical approach)
1. Linear programming
2. Integer programming
3. Dynamic programming
4. Multi-objective programming
SN Panigrahi, Essenpee Business Solutions,
India
78
Project Integration Management
Common Terminologies
You need to know the following about project charter for the exam:
•The project charter formally recognizes/authorizes the existence of the
project, or established the project. This means that a project does not exist without a
project charter
•It gives the project manager authority to spend money and commit corporate
Project Charter
resources.
•In most project situations, the project team does not report to the project manager in
the corporate structure
•The project charter provides the high-level requirements for the project
•It links the project to the ongoing work of the organization
Management plans are the strategy for managing the project and the processes in each knowledge
area. To reiterate to make sure we are all on the same page, a management plan covers how you will:
• Define
Management Plan
• Plan
• Manage
• Control
A project management plan is an integration function – it integrates all the knowledge area
management plans into cohesive whole. This plan also includes the baselines for the project. A project
management plan is a series of plans and baselines, rather than just a schedule. The project
management plan includes:
The project management plan contains scope, schedule, and cost baselines, against
which the project manager will need to report project performance. These baselines are
created during planning. Together these baselines are called the Performance
Performance Measurement
Measurement Baseline
Baseline
•Scope baseline
•Schedule baseline
•Cost baseline
The change management plan describes how changes will be managed and controlled and
may include:
•Change control procedures
•The approval levels for authorizing changes
•The creation of a change control board to approve changes
Change Management
•A plan outlining how changes will be managed and controlled
Plan
•Who should attend meetings regarding changes
•The organizational tools to use to track and control changes
There is a change management plan for the project as a whole. There are also change
management plans for each knowledge area, which are described in the individual
management plans.
Change Control A panel of stakeholders who are responsible for reviewing and
Board deciding which changes should be made to a project.
Straight line depreciation – the same amount of depreciation is taken each year
Depreciation Accelerated depreciation – product depreciates faster at the beginning. There are two types:
double declining balance and sum of years digits.
Description of the products or services being supplied along with the business need, product
Project SOW scope description and strategic plan. External projects: SOW received from the customer.
Internal projects: SOW provided by the sponsor or initiator of the project.
Enterprise
Consider culture and structure, resources availability, project management systems available,
Environmental
stakeholder risk tolerances, and marketplace conditions.
Factors
Lessons learned from previous projects, organization processes and procedures and
Organizational
corporate knowledge base containing historical data, issue and defect management database,
Process Assets
financial information, etc.
This is the integration part of the executing process group. In Direct and
Manage Project Execution, the project manager integrates all the executing
Direct and
processes into one coordinated effort to accomplish the project
manage project
management plan and product the deliverables. In addition, it involves
execution
requesting changes and completing the work accompanying approved
change requests.
5.Validate Scope
•Once the work is accomplished it needs to be validated against the
requirements
6.Control Scope
•Monitoring and Controlling the project scope across the project duration
w.r.t Scope Baseline
SN Panigrahi, Essenpee Business Solutions, India 87
Project scope is the work required to output a project’s deliverable. It is detailed set of
Scope deliverables or features of a project
WBS (Work Break Down Structure) shows the hierarchy of discrete work packages
WBS derived after Decomposition of Scope of Project. It must contain 100% of the work.
The WBS Dictionary describes each component of the WBS with milestones,
WBS Dictionary deliverables, activities, scope, and sometimes dates, resources, costs, quality.
Gold Platting Gold plating refers to adding the extra features that were not part of the product scope.
SN Panigrahi, Essenpee Business Solutions, India 88
TEMPLATE: BROAD SCOPE DEFINITION
In Scope Out of Scope Assumptions Constraints
(Exclusions)
(These are items that you (These are items that you (Knowledge about the (Known restrictions. These
are definitely are not project that is taken as could include
going to deliver / manage) responsible for – the being true or correct for any restrictions in
assumption is that the purposes of project start/finish date, time,
someone else will do planning. Assumptions are deliverable or milestone
them. Exclusions are circumstances and dates, budget
things that don’t form part events that need to occur limitations, resourcing
of your project, for the project to be limits, vendor
but influence on whether successful, but are outside restraints, etc.,
or not you can the total control of
successfully achieve your the project team)
objective.)
GAS-STEAM COMBINED
POWER PLANT
level 0
level 3
COMPRESSORS-1.3.1 GAS TREATMENT-1.3.2 ENCLOSURE-1.3.3
Planning Packages
level 4
COMPRESSOR 1 COMPRESSOR 2 FOUNDATIONS
1.3.1.1 1.3.1.2 1.3.1.3
level 5
DESIGN PROCUREMENT INSTALLATION
1.3.1.2.1 1.3.1.2.2 1.3.1.2.3 WORK PACKAGES
Bidding &
Conceptualization Procuremen Constructio
Design Contractin Closure Level 1
of Project t n
2.0 g 4.0
6.0 Control Account
1.0 5.0
3.0
Marking Ground
Foundatio Column Construction M & E Works
Drawing of Levellin Roofing Miscellaneous Level 2
n Casting of Walls Major Planning
5.1 Layout g 5.4 5.7 Works
5.2 5.5 5.6 5.8 Packages
5.3
WBS
Project
Scope
Statement
Output of Associated
Create WBS WBS
Dictionary
Process
** Accepted Deliverables - have been accepted through the Validate Scope process.
Input
Process Output
Verified
Validate Scope Accepted Deliverable
Deliverables
formal sign-off is obtained
SN Panigrahi, Essenpee Business Solutions, India 97
Project Schedule Management
Knowledge Area that includes the processes required to accomplish timely completion of the
project.
Initiation Planning Execution Monitoring & Close
Process Process Process Controlling Process
Group Group Group Process Group
Group
Plan Schedule
Management
Define Control
Activities Schedule
Sequence
Activities
Estimate Activity
Duration
Develop
Schedule SN Panigrahi, Essenpee Business Solutions, India98
Knowledge Area: Schedule Management
There are 6 Schedule Management processes:
1.Plan Schedule Management : Establishing Project Schedule in Schedule Management
Plan Document which will be used across project to control timelines as project evolves
and changes occur.
2.Define Activities : Breaking down the larger chunks of scope into actionable small
activities using the WBS by defining project activities
3.Sequence Activities : Establishing the relationships between the defined project
activities to ensure the sequence of activities are done in rightful manner
4.Estimate Activity Durations : How long will it take to ensure the estimated
resources perform the activity assigned
5.Develop Schedule : Based on all the available information from defined activities to
sequence activities to estimate resource & durations will aid to arrive at develop
schedule
6.Control Schedule : Monitoring and Controlling the project schedule across the
project duration w.r.t schedule baseline and achieve the project objectives
Total Float or Slack is the amount of time that a project task can be delayed
without causing a delay to the whole project (total float).
Float = Late Start (LS) – Early Start (ES)
Or
Float = Late Finish (LF) – Early Finish (EF)
Float or Slack
Free Float is the amount of time that a project task can be delayed without causing a
delay in any subsequent tasks.
Free Float = (ES of Successors) – (EF of Activity in Question)
Lead is an acceleration of the successor activity and can be used only on finish-to-
start activity relationships. It is overlap between tasks that have a dependency.
Lead Time Lead time refers to Period the A
successor activity will start FS – 2 Days
2 Days
before the previous activity finished.
B
Lag is a delay in the successor activity and can be found on all activity relationship
types.
A. Two days
B. One day
C. Four days
D. Not enough information
B-D-F-H D 1
17
E 0 Critical Path
B-D-G-H 18 F 2
B-E-G-H 19 Critical Path G 0 Critical Path
H 0 Critical Path
0 3 3 4 2 6
A C
0 0 6 6 9 9 5 11 9 4 13
Start F
0 0 0 4 4 4 5 9 11 2 15 15 4 19 0 0
B D H Finish
0 0 4 5 10 10 5 15 15 0 19 0
1 0
G
4 6 10 10 0 15
E
4 0 10
SN Panigrahi, Essenpee Business Solutions,
105
India
Estimate Activity Duration
Expert judgment can be used by using historical information to give duration estimates
Expert Judgment from similar projects. It can also be used to reconcile different estimating methods.
Based on previous activity (historic data) from similar activity or project with similar
nature (a form of expert judgment) - used when little is known on very similar scope
Analogous
- works well when project is small – rough estimation – generally less costly and
Estimating less time consuming, but less accurate. Analogous is a TOP DOWN estimating
method.
The above means, that adding a margin of 1 sigma we get a 68.25% of the confidence level of the
estimate, while adding a buffer of 2 sigmas, we should be able to tell in 95.46% confidence that the project
will be finished in the given time. It may be easily noticed, that that the most optimal solution seems a
buffer of 2 sigmas, as lower numbers are giving a low level of confidence, whereas higher - a significant
increase of the safety margins with a rather little increased confidence.
Tp = 11 (Worst Case) TE ± (n * σ)
TM = 6 (Confident) With 95% Confidence Level N = 2
•Schedule Compression may also can be achieved through Reducing Scope and / or cutting Quality, however not
accepted to compromise on scope and quality unless change request is accepted
SN Panigrahi, Essenpee Business Solutions, India 113
Project Cost Management
Project Cost Management includes:
• The processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs
• So that the project can be completed within the approved budget.
Plan Cost
Management
Estimate Control
Costs Costs
Determine
Budget
1. Work Package Cost Estimate = Activity Cost Estimates + Activity Contingency Reserve
2. Control Accounts = Cost Baseline = Work Package Cost Estimate + Contingency Reserve
3. Project Budget = Cost Baseline + Management Reserve
Earned Value Quantification of the “Worth / Value” of the work done to date.
(EV) EV tells you, in physical terms, what the project has accomplished or
Worth or Value of Work Completed as on given Point of Time.
Actual Cost Actual Cost Incurred or Spent on the project as on given Point of
(AC) Time
Budget At
The Budgeted Amount for the Total Work / Complete Project
Completion (BAC)
SN Panigrahi,
Variance at Completion The difference between the Estimated total cost and the VAC = BAC – EAC
(VAC) original budget
To Complete The efficiency needed to finish the project on budget, it is the TCPI = Remaining Work / Remaining Funds
Performance Index ratio between budgeted cost of work remaining and money = (BAC- EV) / (BAC – AC) – As per Original Budget
(TCPI) remaining = (BAC- EV) / (EAC – AC) – As per Re-Estimate
119
Basic Understanding of Terms
Budget At Completion (BAC) – Say 100
A B C D E
Review
Earned Value (EV) - 50
Actual
As per Planning
Planned Value (PV) - 60
EV = 50
PV = 60
AC = 70
BAC = 100
Variance VAC CV SV
How Efficiently are we using our Resources? Cost Performance Index (CPI)
How Effectively must we use our Remaining Resources? To Complete Performance Index (TCPI)
What is the Project Likely to Cost? Estimate at Completion (EAC)
A B C D E
Earned Value (EV) - 50
A B C D E
Earned Value (EV) - 50
A. ahead of schedule and under A. ahead of schedule and A. ahead of schedule and under
budget under budget budget
B. ahead of schedule and over B. ahead of schedule and B. ahead of schedule and over
budget over budget budget
C. behind schedule and under C. behind schedule and C. behind schedule and under
budget under budget budget
D. behind schedule and over D. behind schedule and over D. behind schedule and over
budget budget budget
Ans : Solution: D Solution: B
Solution: C
As of today, AC > EV = over As of today, AC > EV = over
As of today, AC < EV =
budget and EV < PV = budget and EV > PV = ahead
under budget and EV < PV =
behind schedule, so the of schedule, so the project is
behind schedule, so the project
project is both “behind “ahead of schedule and over
is “behind schedule and under
schedule and over budget”. budget”.
budget”. SN Panigrahi, Essenpee Business Solutions, India 125
1. Variance at Completion (VAC) - is a comparison of the original budget at completion (BAC)
and the revised forecast (EAC).
VAC = BAC – EAC
A negative VAC (<0) is an indicator that the project may exceed the BAC – project cannot
be completed with the approved budget - may require either an additional funding
allocation or the elimination of some of the project scope.
A positive VAC (>0) indicates the project will be completed in less than the budget - not
utilize the allocated budget – budget funds remain excess.
It can also be defined as “the opportunity (potential return) that will NOT be realized for the second best project
not selected”. Since there are limited resources such as human, time, money, etc., we cannot work on infinite
number of projects at the same time. Opportunity cost is a concept to help you judge which project(s) to take and
which project(s) NOT to take based on the relative potential returns of the project(s).
For example:
• Project A has a potential return of $25,000
• Project B has a potential return of $20,000
• Project C has a potential return of $10,000
The opportunity cost for selecting Project A for completion over Project B and C will be $20,000 (the
“potential loss” of not completing the second best project).
A. $1250
B. $2000
C. $2250
D. $2500
Ans :
C. $2250 – (Asset Cost – Scrap Value) / Useful Life = ($10K – $1K) / 4 = $2250 per year.
133
SN Panigrahi, Essenpee Business Solutions, India
Project
Quality
Management
Prevention Inspection
Criteria Driven
Driven Driven
Manage Quality is about
Quality planning is the Quality Control is about
utilizing all the elements
stage used to identify the ensuring that the products
defined in quality
quality criteria that are and services of the project
planning that are needed
relevant to the project and comply with relevant
to meet the customer’s
to plan how to satisfy quality standards and
requirements.
them. about eliminating the
It is a continuous process
causes of unsatisfactory
improvement.
It lays out the roles and performance.
responsibilities, resources, It involves managing the
procedures, and processes It is the ongoing quality
quality of the project
to be utilized for quality management and review
deliverables. It refers to
control and quality of the process of doing the
the actual testing of
assurance. work of the project during
product components and
its life cycle
the entire product before SN Panigrahi, Essenpee Business Solutions,
and during delivery. 134
India
Quality Grade
Quality is Conformance to the Grade is a Categorization of the
Requirements. product based on its
Quality is referred to Functions. Characteristics.
There is a big difference between the quality and grade. A product can be a high grade (high-end)
or a low grade (low-end), it is perfectly acceptable and there is no problem with it as long as it
fulfills its stated requirements.
On the other hand, a low-quality product is never acceptable and it is always a problem. Every
product must be of high quality regardless of its grade. A low-quality product is never desired.
Example : A camera with lots of functions is high grade and a camera which takes bad pictures is
low quality.
It may not be a problem if a suitable low-grade product (one with a limited number of features) is of high
quality (no obvious defects). In this example, the product would be appropriate for its general purpose of
use (Functionality)
The project manager and the project management team are responsible for managing the
trade-offs associated with delivering the required levels of both quality and grade
Low Grade is not a problem – low quality isSNaPanigrahi,
problem Essenpee Business Solutions,
India
135
Precision & Accuracy
1. Precision - Consistency in value of repeated measurements having fine cluster and little scatter.
A Measure of exactness - degree of cluster - process will repeat the same value
Precision is Consistency in value of repeated measurements having fine cluster and little scatter
3.Control Quality
•Process of managing the project quality in the defined tolerance levels, control
limits and ranges during the project execution.
SN Panigrahi
- Quality circle
Taguchi - Loss Function
Benefit
Appraisal Costs
$ Repair Costs
Prevention Costs
Appraisal Costs
Failure Costs
Internal Repair Costs
External
Failure Costs
Control Charts: The control chart is a graph used to study how a process changes
over time. Data are plotted in time order. A control chart always has a central line for
3. Control Charts
the average, an upper line for the upper control limit, and a lower line for the
lower control limit..
Histogram: The most commonly used graph for showing frequency distributions, or how often
4. Histogram each different value in a set of data occurs.
Pareto Chart: As a quality control tool, the Pareto chart operates according to the 80-20 rule. This
rule assumes that in any process, 80% of a process’s or system’s problems are caused by 20% of
5. Pareto chart major factors, often referred to as the “vital few.” The remaining 20% of problems are caused by
80% of minor factors.
Scatter Diagram: Graphs pairs of numerical data, one variable on each axis, to look for a
6. Scatter Diagram correlation between two variables wherein the values for each pair of a variable is
plotted on a graph in the form of dots
Stratification: A technique that separates data gathered from a variety of sources so that patterns
7. Stratification can be seen with different colours (some lists replace “stratification” with “flowchart” or “run
chart”).. SN Panigrahi, Essenpee Business Solutions, India 141
SN Panigrahi, Essenpee Business Solutions, India 142
Rule of Seven is used to filter out the random variation in a production process. shows the ‘trends’ that are caused
by the ‘assignable causes’ or non-random causes that required investigation and possible corrective action to be
taken.
Acquire
Plan Resources
Resource
Management
Develop Control
Estimate Team Resources
Activity
Resource Manage
Team
144
SN Panigrahi, Essenpee Business Solutions, India
Knowledge Area: Resource Management
Objectives
•Understand the different Human Resource Management Processes
•Their Inputs, Tools and Techniques, Outputs
RACI (Responsible, Accountable, Consulted, Informed) is an Example of RAM which shows the relationship
between activities and the team members.
Role Definition
Responsible Conducts the actual work/owns the problem. There should be at least one R (otherwise the
(“doer” of the work) work is not performed) and there can be multipl R’s (this is called team working)
Accountable Approves the completed work and is held fully accountable for it. There should be one and only one
(“owner” of the work) A
Consulted Has the information and/or capability to complete the work. Two-way communication (typically between
R and C) – Optional
(in the “Loop”)
Informed (Keep in the Is to be informed of progress and results. One-way communication (typically from R to I) - Optional
“Picture”)
Persons
Activity RAM SHYAM BHIM GOPAL RAMPAL MAHIPAL
Define A R I I C I
Design I A C I R R
Develop C A R C R
Test A R R R I I
Customer Approval R, A C SN Panigrahi,
Essenpee
I Business Solutions, India 149
Team Building – Bruce Tuckman Model – Five Stages of
Development
1 Forming Team Forms, meets, learns about project; Roles & Responsibilities are not
clear; PM’s Role : guide & direct the team, and establish clear
objectives.
3 Norming This is when people start to resolve their differences; know one-another
better; socialize; develop a stronger commitment to the team goal; start
progress towards it. PMs Role : Team Building - help team members take
responsibility
4 Performing The team reaches the performing stage when hard work leads, without
friction, to the achievement of the team's goal. The structures and processes
that you have set up support this well. PMs Role : Delegate; concentrate on The Duration of a particular phase
developing team members. depends on team dynamics, size &
5 Adjourning This is the stage of shelving / suspending the project leadership
Reward Power
Positional Reward power is (to some extent) tied to the formal power of the project manager. You
will earn the team’s support because team members think that you are capable of
Powers rewarding them if they perform well. Rewards may be monetary (salary increase, bonus,
promotion, etc.) or non-monetary (recognition, professional development, appreciation
letter, day off, etc.).
Punishment Power
Punishment Power comes with the formal power of the project
manager. Here, you will get your team’s obedience because the team
Types members are afraid that if they don’t perform their duties efficiently, they may
get punished. Here you use fear as a primary tool to get work done.
of Punishment power is also known as coercive power.
Power Expert Power
Being a subject matter expert itself is a great influential power. Team
members will respect you for your technical expertise. They trust you
because they think that you are an expert and know how to handle issues
Expert power is considered to be a positive power that influences team
Personal members to follow your lead.
Compromising
• This is lose-lose situation, since no party gets everything. This technique involves finding
solutions that bring some degree of satisfaction to both parties.
Withdrawal (Avoidance)
• In this technique, the parties retreat or postpone a decision on a problem. Dealing with
problems is a PMI-ism; therefore, withdrawal is not usually the BEST choice for resolving
conflict
Smoothing (Accommodating):
• This technique emphasizes agreement rather than differences of opinion
Forcing
• This technique involves pushing one viewpoint at the expense of another - win-loose
SN Panigrahi, Essenpee Business Solutions,
152
India
STYLE DESCRIPTION EFFECTS
Withdrawing/ Retreats from an actual or potential conflict Does not solve the problem
situation
Avoiding
Smoothing/ Emphasizes areas of agreement rather than Provides only short-term solution
areas of difference
Accommodating
Compromising Searches for the bargains for solutions that Does provides definitive resolution
bring some degree of satisfaction to all parties
Forcing Pushes one view-point at the expense of others; Hard feelings may come back in other
offers only win-lose solutions
forms
Confronting/ Problem Incorporates multiple viewpoints and insights Provides long-term resolution
from differing perspectives; leads to consensus
Solving and commitment
Provides ultimate resolution
/ Collaborating Treats conflicts as a problem to be solved by
examining alternatives;
Plan
Manage Monitor
Communication
Management Communication Communication
156
SN Panigrahi, Essenpee Business Solutions, India
Knowledge Area: Communications Management
Objectives
• Sources of information typically used to identify and define project communication requirements
include:
Stakeholder information and communication
The Number of potential communication channels = n(n – 1)/2
Organizational charts
Project organization and stakeholder responsibility, relationships and interdependencies
Development approach
Disciplines, departments, and specialties involved in the project
Logistics of how many persons will be involved with the project and at which locations
Internal information needs
External information needs
Legal requirements
159
You have six team members working under you. How many lines of communication will you have in your
communication plan?
(a) 16
(b) 15
(c) 21
(d) 30
Ans : C
Tips
You have six team members working under you N= 6+1 (You – Project Manager)
You are a Project Manager. Ten Team Members N = 10 +1 (You – Project Manager)
Reporting to You. Or You are Leading a Ten Member
Team
You are a Project Manager. You have Identified a N= 5 (You – Project Manager already Included in the
Team Size of 5. Team)
Sponsor Presented a Charter where in he Appointed N = 8 +1 (You – Project Manager)
You as a Project Manager. There are Total Ten
Stakeholders out of which Eight Team Members
Reporting to you. Other Two are Reporting Directly to
Sponsor and not to you.
SN Panigrahi, Essenpee Business Solutions, India 160
Question: You have four resources reporting to you. Due to some new contracts, you have decided to
add two more resources to your team. What is the total number of communication channels?
A: 21
B: 15
C: 6
D: 28
Ans A
Plan Risk
Management
Identify
Risks Implement Monitor
Perform Risk Risks
Qualitative Risk Responses
Analysis
Perform
Quantitative Risk
Analysis
Plan Risk
Responses 162
SN Panigrahi, Essenpee Business Solutions, India
Knowledge Area: Risk Management
There are 6 Risk Management processes, namely:
A positive risk is a condition or situation that is favorable to the project and will have a
Positive Risk good impact on any of your project objectives if it occurs.
A negative risk is a condition or situation that is unfavorable to the project and will
Negative Risk have a bad impact on one or more of your project objectives, if it occurs.
Issue is a Current Problem. This is a hot topic or a disputed matter; with an issue,
Issue there is disagreement among the project stakeholders. As a project manager, it will be
your responsibility to manage issues and note them in a log with their resolution.
Business risk implies uncertainty in profits or danger of loss and the events that
Business Risk could pose a risk due to some unforeseen events in future, which causes business to
fail / growth. Business Risks can be Positive or Negative & Can’t be Insured.
This is also used to manage identified risks. You will use this plan when your
Fallback Plan contingency plan proves ineffective or fails; it’s a fallback SN Panigrahi, Essenpee
167
You will use the contingency reserve for the fallback plan Business Solutions, India
Types of Risks
Risk tolerance is about the sensitivity of stakeholders or organizations towards
risks.
High tolerance means people are willing to take risks, while low tolerance means
Risk Tolerance people are not willing to take a high risk unless the benefit of taking the risk
outweighs the fear. Tolerance is shown in limits - Range.
For example, a 5% cost overrun is acceptable for an organization, but anything
above that is not.
This is a project team member who is assigned the responsibility of ensuring that the
risk response is effective and to plan additional risk responses if required.
Risk Owner Generally, the risk owner and risk action owner is the same person in a small or
medium type of project. However, if the project is large and complex, you can assign a
separate risk action owner.
Usually, you will assign a risk action owner if you have a large project where it is
difficult for the risk owner to manage the risk on their own and they need a helping
hand.
Risk Action Owner The risk action owner helps the risk owner manage the risk. The responsibility of a
risk action owner is to ensure that the agreed-upon risk responses are carried out as
planned.
Risk Avoidance - involves making changes to the project management plan to either eliminate the risk or
protect the negative impact of the risk on project objectives. Eg : Extending the schedule, changing the strategy,
or reducing the scope
Risk Transference - involves transferring risk impact to a third party along with the ownership of risk responses.
It doesn’t eliminate risk – risk exists but only being transferred from one party to the other – involves payment of
risk premium – most effective in dealing with financial risks. Eg : Insurance, Warrantee, Guarantees, Performance
bonds, contracts, agreements, outsourcing. In case of Cost – Plus contract, seller transfers the risk to the
buyer; whereas in case of Fixed –Price contract the risk is transferred by buyer to the seller
NTI – SN Panigrahi SN Panigrahi, Essenpee Business Solutions,
India
171
Risk acceptance is when no change in the project is made to accommodate the risk.
Active acceptance includes further action eg. setting aside contingency to offset the effect of
Active the risk.
Acceptance All unknown or residual risks follows acceptance strategy as no information available about
them & team will deal with those risks as they occur.
Passive acceptance requires no action beyond documenting the decision. This strategy is
used for low severity and low priority risks only. During dealing with this passive acceptance
Passive
in case Project management Team requires funds they may look for approval to get access to
Acceptance management reserves.
Made When the Likeliness of Risk Occurrence is Very Low or Its Impact is Very Low.
One simple way to remember this: remember disaster movies like “Titanic”, “Armageddon” or
“2012”. There are always those characters in the movie where they just accept that they are going
to die and of course there are the heros who take some action to get out alive. Think of the former
as “Passive Acceptance” and the heros as “Active Acceptance”.
SN Panigrahi, Essenpee Business Solutions, India 172
Responses for
Positive Risks
Exploit - involves strategies to ensure that the opportunity is definitely realized. Actions are specifically directed to
reduce or remove the uncertainty of the opportunity being missed. Eg : Assigning most experienced resource to reduce time
to complete; adopting new technology or upgrading technology
Enhance - involves strategies of monitoring and emphasizing risk triggers and identifying root causes to increase
probability of opportunity realization. Eg : Adding more resources to finish an activity early to realize opportunity.
Share - involves strategies of assigning partial or complete ownership of the risk to a third party who is in a better
position to make sure the opportunity is realized. Eg : Partnerships, joint ventures, team forming etc
Acceptance – Willing to take advantage of the opportunity if it arises and not pursuing it actively
It is a Primary Risk Response It is Not a Primary Risk For Unidentified Risks which
Strategy Response Strategy are Passively Accepted.
Used for handling Negative Risks It is activated when Primary There is No Pre-existing
proactively Response (Contingency Plan) Plan for workarounds
Taken only when risk event occurs Not Effective (Plan B)
Activated only for specific Pre- Funding for this is taken from
Accepted Risks with certain To be taken after the Management Reserves upon
triggers Contingency Plan Management Approval
(i.e. no proactive actions to be taken For Identified risks (known PM has No Authority to
to Avoid or Minimize (Mitigate) their unknowns) Use
occurrence) Developed during Plan Risk
Only for Identified risks (known Developed during Control
Responses process Risks Process.
unknowns)
Funded from Contingency Implementing
Developed during Plan Risk workarounds
Responses process Reserves can cause a Change
Funded from Contingency PM has Authority to Use Request.
Reserves
PM has Authority to Use
Sue is named the project manager of a software development project aiming to
automate manual tasks to save labour costs and time in the long run. Mid-way
through the project execution, a risk identified previously comes up. In the risk
register, this risk was marked as an accepted risk. Which of the following plan
should Sue consult to know how to handle this risk?
1.Contingency Plan
2.Workaround Plan
3.Fallback Plan
4.Project Cost Management Plan
Ans : B
Most of the people would be thinking option A to Inform the Management as Contingency plan was
not able to resolve it which is the primary risk response strategy for identified risk.
But this is not correct option as a PM your immediate next step should be to check for Fallback plan
in project Plan which is Option B as above we are talking about identified risk and primary response
has not work.
Workarounds are determined during which risk management
process?
1.Identify Risks
2.Perform Quantitative Risk Analysis
3.Plan Risk Responses
4.Control Risks
Answer : D
What is active risk acceptance?
Ans : A
Expected monetary value (EMV) is a risk management technique to help quantify and compare
risks in many aspects of the project. EMV is a quantitative risk analysis technique since it relies
on specific numbers and quantities to perform the calculations, rather than high-level
approximations like high, medium and low.
EMV = (Probability) x (Impact)
Risk #1: Your lead programmer will be poached. Cost of Replacement $10,000. Probability 50%
So $10,000 x 0.5 = -$5,000.
Project with Highest EMV should be Selected. Therefore Project A can be Selected
a. $90,000
b. $190,000
c. $70,000
d. $100,000
Answer is A
EMV = Probability X Impact
Probability Impact EMV
Risk A – Cost Over Run 30% $ 100,000 - $ 30,000
Risk B – Delay of Project 10% $ 200,000 - $ 20,000
Risk C – Improved Market Share 20% $ 400,000 + $ 80,000
Risk D – Cost Reduction 40% $ 150,000 + $ 60,000
Total EMV $ 90,000
Risk #1: Your lead programmer will be poached. Cost of Replacement $10,000. Probability 50%
So $10,000 x 0.5 = -$5,000.
a. $90,000
b. $190,000
c. $70,000
d. $100,000
Answer is A
EMV = Probability X Impact
Probability Impact EMV
Risk A – Cost Over Run 30% $ 100,000 - $ 30,000
Risk B – Delay of Project 10% $ 200,000 - $ 20,000
Risk C – Improved Market Share 20% $ 400,000 + $ 80,000
Risk D – Cost Reduction 40% $ 150,000 + $ 60,000
Total EMV $ 90,000
Plan
Conduct Control
Procurement
Procurement Procurement
Management
185
SN Panigrahi, Essenpee Business Solutions, India
Knowledge Area: Procurement Management
Objectives
•Typically for standard items of procurement or with a known Vendor repeated order,
quotation is requested
Tender Notice
• Primarily for the government work orders where the work is already
predefined with Quality, like road laying
Risk
Contract Type
SN Panigrahi, Essenpee Business Solutions,
India
190
Point of Total Assumption (PTA)
This concept is only related with fixed price incentive fee contracts and refers to the amount
above which the seller bears all the losses of an additional cost overrun. The concept work when
buyer and seller has agreed criteria for fixing the price, and buyer is willing to repay part of cost overrun
till it reaches a ceiling price.
Target Cost: This is the estimated budget, which the seller has planned for delivering the given project; it
can be looked as a project budget,in this type of contracts this is shared with the buyer and the process
of estimating project budget is also kept transparent.
Target Fee: This is the fee which the seller wants to charge for the work he is doing, this is the planned
fee, and the actual fee will depend upon how well the seller manages the project (cost overruns)
Target Price: This is the price the buyer is looking towards, this is a sum total of Target Cost + Target
Fee, both seller and buyer use this as a benchmark, if the final project cost less than this price, buyer and
seller will share the profit as per profit sharing agreement, if the price goes beyond the target price,
buyer and seller share the cost as per cost sharing agreement (subject to maximum ceiling of selling
price)
SN Panigrahi, Essenpee Business Solutions,
191
India
Share ratio: In this type of contract we will have two types of ratio, one for
sharing profit, which is used when the project cost less than the target cost
and another is cost sharing ratio which is used when the project cost more
than the target cost.
Ceiling Price: this price is put by the buyer to limit the cost liabilities, buyer
will not pay anything beyond this price, even if the actual project cost more
than the ceiling price buyer will not pay anything extra than the ceiling price.
Target Cost: 1,000,000
Target Profit for Seller: 100,000
Target Price: 1,100,000 (Target Cost + Profit for Seller)
Ceiling Price: 1,300,000 ( the maximum the buyer will pay)
Share Ratio: 80% buyer–20% seller for over-runs, 50%–50% for
under-runs.
PTA = ((1,300,000 – 1,100,000)/ 0.80) + 1,000,000 = 1,250,000.
Beyond the Point of Total Assumption, the seller’s profitability
decreases, and their initiative and interest to complete the project
may diminish too. Therefore, the PTA is also a risk trigger. As this
point is reached, the project risk increases, and more attention is
needed to complete the project at the earliest, with as little cost
deviation as possible.
Tender Notice It is process to call vendors for doing a certain job or provide certain service at a
competitive price. Usually done through Press Advertisements & Public Notices
Pre-Bid Pre-bid meetings are gatherings scheduled after an invitation for bids or request for
proposals is advertised. Their purpose is to clarify any concerns bidders may have with
Conference
the solicitation documents, scope of work and other details of the requirement.
SN Panigrahi, Essenpee Business Solutions, India 195
Source Selection Criteria
•Selection Criteria is often included as part of the procurement documents to bring
transparency and ensure competitiveness amongst the bidders.
•The selection criteria based on which the contract will be awarded is often
disclosed so that the bidders know upfront on what basis their bids will be
selected.
•In some cases this may be the early phase to narrow down and subsequently have
a follow-on round to ensure the qualified bidders get to know more intricate
details and subsequently re-bid for final award.
200
SN Panigrahi, Essenpee Business Solutions, India
Knowledge Area: Stakeholder Management
Objectives
•Understand the different Stakeholder Management Processes
•Their Inputs, Tools and Techniques, Outputs
Knowledge Area: Stakeholder Management
•It includes processes to ensure identification of stakeholders, effective communication,
engagement of them across project to garner their support/decisions for execution and
success of project objectives.
•Stakeholder Engagement towards their Satisfaction is by default one key project
objective for project success.
•Each Project Stakeholder will exert their influence on the project in one or the other
manner.
•Identifying key stakeholders, understanding their needs along with the relationships
within themselves is one area, a Project Manager has to keep close watch to develop
strategies to ensure the stakeholders are in favor of project objectives.
Identify Stakeholders
•Identification of key stakeholders before the project starts, during the project kick off and the project execution to
closure is critical towards the stakeholders engagement rightly and avoid the project being jeopardized.
Attitude
• It improves the depiction of the stakeholder
Time Bomb
community as a multidirectional entity and Example: Sleeping Giant
Positive Attitude
assists with the development of High Power
Low Interest
communication strategies. Make sure they know
Tripwire Irritant “what’s in it for them”.
Awaken their interest
and get their input and
support.
Interest
204
The term salience means “the quality of being
particularly noticeable, important or prominent,”
and so stakeholder salience means the
importance you give to your stakeholders.
C : Current Engagement
D : Desired Engagement
Responsibilit
Honesty
y Code of
Ethics and
Professional
Conduct
www.oliverlehmann.com
http://www.tutorialspoint.com/pmp-exams/pmp_mock_exams.htm.
https://www.pmlearningsolutions.com/
https://www.pmexamsmartnotes.com/
http://certification.about.com/od/projectmanagement/a/pmp_test_whiz.htm.
http://www.examcentral.net/pmp/pmp-exam-questions#.
http://www.preparepm.com/mock1.html.
http://pmhub.net/pmsuccess/Menu.htm.
http://www.ajithn.com/login.php.
http://free.pm-exam-simulator.com/.
http://www.passionatepm.com/free-pmp-exam-practice-test-questions.
SN Panigrahi, Essenpee Business Solutions, India 210
Knowledge Areas Initiating Planning Process Executing Process Monitoring & Closing Process
Process Group Group Group Controlling Process Group
Group
3.Direct and Manage 5.Monitor and
Project Integration 4.1 Develop Project 4.2 Develop Project Project Work Control Project Work 4.7 Close Project or
Management Charter Management Plan 4.Manage Project 6.Perform Integrated Phase
Knowledge Change Control
Out Put
1. Project Charter Project Management 1. Deliverables 1. Work Performance 1. Project document
2. Assumption Log Plan 2. Work performance Reports updates
data 2. Change requests • Lessons learnt
3. Issue Log 3. Project Plan register
4. Change requests updates 2. Final product,
5. Updates • Any component service or result
4. Project document transition
Updates 3. Final report
4. Organizational
process assets
updates
1. Lessons Learnt 1. Approved change
Register requests
2. Project 2.Project
management plan management plan
updates updates
• Any component • Any component
3. Organization 3. Project document
Process Assets updates
updates • Change Log
Ans : C
Check how much slack is available on this task
You work for a seller that is bidding on a contract. Which type of contract has
the MOST risk for your company?
A. CPIF
B. T&M
C. FP
D. CPAF
Ans : C
A. In this decision-making technique, one individual takes the responsibility for making the decision for the
entire group. Then, it is not an interpersonal and team skill that enhances the brainstorming process.
B. A decision-making technique that can be used (…) to identify the key issues and suitable alternatives to
be prioritized as a set of decisions for implementation. Criteria are prioritized and weighted before being
applied to all available alternatives to obtain a mathematical score for each alternative.
D. Because project managers often have little or no direct authority over team members in a matrix
environment, their ability to influence stakeholders on a timely basis is critical to project success. It is and
interpersonal and team skill but it does not enhance the brainstorming process.
The nominal group technique enhances brainstorming with a voting process used to rank the most
use-full ideas for further brainstorming or for prioritization.
[PMBOK 6th edition, Page 144] [Project Scope Management]
215
SN Panigrahi, Essenpee Business Solutions, India
The project team and you are working on the quality management plan. There are two changes related to
quality standards that require a detailed risk analysis. How should you perform this process?
A. In sequence with other planning processes and analyze risks after Plan Quality Management.
B. In parallel with other planning processes and analyze risks in the meantime.
C. You should focus on analyzing the two risks in the Executing Process Group.
D. You should have focused on analyzing all risks in the Initiating Process Group.
Ans : B
C & D. From the process of identifying individual project risks as well as sources of overall project risk and
documenting their characteristics in Identify Risks to the process of developing options, selecting strategies,
and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks in
Plan Risk Responses take part in the Planning Process Group.
A & B. Quality planning should be performed in parallel with the other planning processes. For example,
changes proposed in the deliverables in order to meet identified quality standards may require cost or schedule
adjustments and a detailed risk analysis of the impact to plans. Therefore, right answer is B. [PMBOK 6th
edition, Page 278] [Project Quality Management]
Ans : D
Ans : B
Ans : D
Mother Effect /
Earth Problem
a. Lease, 20 months
b. Lease, 24 months
c. Lease, 30 months
d. Buy it
Answer is D
Explanation: Let M equal the number of months where leasing break even with the buying option.
M = 20 months.
Therefore, buying will be the cheaper option after 20 months and since the machine is needed for 24 months, then buying
decision is justified.
Ans : A
A. Contingency reserves
B. Funding requirements
C. Management reserves
D. Organizational process assets
Ans : C
The total project budget includes the cost baseline plus the management
reserves. Therefore, the difference between the two is the management
reserves. Withheld for management control purposes, management reserves
are used for unforeseen risks that affect the project. The cost baseline includes
the work package estimates plus contingency reserves. The project manager
can use contingency reserves for identified risks should they occur.
Ans : A
A: To allow everyone to get to know each other and discuss project objectives.
B: To discuss the high level stakeholders’ requirements.
C: To discuss the next steps on the project.
D: To discuss the high level timeline of the project.
Ans : A
A. Hierarchal
B. Authoritarian
C. Charismatic
D. Associative
Ans : C
A.Gantt chart
B.Milestone chart
C.Fishbone diagram
D.Network diagram
Ans : C
1.Conduct Procurements
2.Plan Procurements
3.Control Procurements
4.Close Procurements
A. Risk Category.
B. Individual Project Risk.
C. Risk Response.
D. Risk Register.
Ans : A
X B. Risk categories provide a means for grouping individual project risks.
X C. Where a potential risk response has been identified during the Identify Risks process, it is recorded in the
risk register. This will be confirmed during the Plan Risk Responses process.
X D. The risk register captures details of identified individual project risks. The results of Perform Qualitative
Risk Analysis, Plan Risk Responses, Implement Risk Responses, and Monitor Risks are recorded in the risk
register as those processes are conducted throughout the project. The risk register may contain limited or
extensive risk information depending on project variables such as size and complexity.
A common way to structure risk categories is with a risk breakdown structure (RBS), which is a hierarchical
representation of potential sources of risk. The risk categories in the lowest level of the risk breakdown structure
can be used as a prompt list for individual project risks. An RBS helps the project team consider the full range of
sources from which individual project risks may arise. The organization may have a generic RBS to be used for
all projects, or there may be several RBS frameworks for different types of projects, or the project may develop
a tailored RBS. Where an RBS is not used, an organization may use a custom risk categorization framework,
which may take the form of a simple list of categories or a structure based on project objectives. Therefore,
right answer is A. [PMBOK 6th edition, Page 405,416] [Project Risk Management]
SN Panigrahi, Essenpee Business Solutions, India 230
1. Jerry recently took over a project after another project manager left. He needed to
determine how many communication channels existed to ensure he was effectively
reaching all his stakeholders. Looking through his stakeholder registry and removing
the prior PMP, the project has 43 members now. How many communication channels
exist?
A. 903
B. 946
C. 450
D. 900
Ans : B
Number of Communication Channels N = 43 +1
= n(n-1)/2
Rather than use Triangular Distribution while doing Three Point Estimation you choose to use Beta
Distribution. Based on your analysis and understanding you are confident that the project would be completed
with a total cost of 108,000 $.You also estimate that a best case estimate would be 90000 $ while a worst case
scenario would result in the costs incurred to shoot up to 138000 USD. What would the Three point Cost
estimate be using Beta Distribution ?
A. 112000 $
B. 110000 $
C. 101000 $
D. None of the above
The correct answer is B.The question states we should use Three point estimate using Beta
distribution. The formula for this estimation technique is (To + 4Tm + Tp )/ 6 where Tm = Most
Likely estimate , To = Estimate based on Best case scenario and Tp = Estimate based on Worst case
scenario. So the Three point estimate using Beta distribution is (4 *108000) + 90000 + 138000 / 6 =
660000/6 = 110000 $
A. 1,000
B. 1,750
C. 750
D. 1,200
Ans : D
EAC = ,AC + Bottoms - up ETC
The EAC is $1,200. Did you catch that the budget was no longer
valid? This should have clued you into using formula above. The
additional information you need was the new estimate to completion
(ETC), which was 750.
Ans : C
Ans : C
Ans : B
You’re managing a project, when your client tells you that an external problem
happened, and now you have to meet an earlier deadline. Your supervisor heard that in
a situation like this, you can use schedule compression by either crashing or fast-
tracking the schedule, but he’s not sure which is which. What do you tell him?
A. Crashing the project adds risks, while fast-tracking adds cost
B. When you crash a project, it always shortens the total duration of the project
C. Crashing the project adds cost, while fast-tracking adds risk
D. When you fast-track a project, it always shortens the total duration of the project
Ans : C
Ans : D
A.Good supervision
B.Job security
C.Regular promotions
D.Good salary
Ans : C
Ans : C
Ans : A
Ans : B
A. The risk management plan may include some or all of the following elements: Risk Strategy, Methodology, Roles and
responsibilities, Funding, Timing, Risk categories, Stakeholder appetite, Definitions of risk probability and impacts, Probability
and impact matrix, Reporting formats and Tracking documents.
C. The risk report may be updated to present agreed-upon responses to the current overall project risk exposure and high-
priority risks, together with the expected changes that may be expected as a result of implementing these responses.
D. Throughout the life cycle of a project, the project manager will normally face problems, gaps, inconsistencies, or conflicts that
occur unexpectedly and that require some action so they do not impact the project performance. The issue log is a project
document where all the issues are recorded and tracked.
The risk register is updated when appropriate risk responses are chosen and agreed upon. Updates to the risk register may
include but are not limited to; Agreed-upon response strategies, Specific actions to implement the chosen response strategy,
Trigger conditions, symptoms, and warning signs of a risk occurrence, Budget and schedule activities required to implement the
chosen responses, Contingency plans and risk triggers that call for their execution, Fallback plans for use when a risk that has
occurred and the primary response proves to be inadequate, Residual risks and Secondary risks that arise as a direct outcome
of implementing a risk response. Therefore, right answer is B. [PMBOK 6th edition, Page 448] [Project Risk Management]
Ans : D
Answer is C
The question implies that the Close Project or Phase process is underway. Actions and activities
necessary to transfer the project's products, services, or results to the next phase or to
production and/or operations is one aspect of project closure.
Transferring the completed assembly line to operations is an activity that is completed during the Close
Project or Phase process.
A. Supportive
B. Controlling
C. Directive
D. Project Management Staff
Ans : A
Ans : D
Ans : D
Ans : A
You are managing a project laying underwater fiber optic cable. The total cost of
the project is $52/meter to lay 4 km of cable across a lake. It’s scheduled to take 8
weeks to complete, with an equal amount of cable laid in each week. It’s currently
week 5 and your team has laid 1800 meters of cable so far. What is the SPI of your
project?
A. 1.16
B. 1.08
C. .92
D. .72
Joe is a project manager on a large software project. Very late in his project,
the customer asked for a huge change and wouldn’t give him any more time to
complete the project. At a weekly status meeting, the client demanded that the
project be completed on time. Joe told the client that he wasn’t going to do
any more status meetings until the client was ready to be reasonable about
the situation. Which conflict resolution technique was he using?
A. Forcing
B. Compromise
C. Withdrawal
D. Confronting
Ans A
SN Panigrahi, Essenpee Business Solutions,
India
251
You have five people working on you team, a sponsor within your company
and a client, all of whom need to be kept informed of your project’s
progress. How many lines of communications are there?
A. 28
B. 21
C. 19
D. 31
Ans : A
Ans : C
SN Panigrahi, Essenpee Business Solutions,
India
253
The lowest level at WBS is one of the following:
A. The task.
B. The activity.
C. The work package.
D. The element.
Ans : C
A.Decision-making
B.Cost Control
C.Overhead rate estimating
D.Team discussions
Ans : A
A. Team building
B. Analysis of alternatives
C. Convergent thinking
D. Uninhibited verbalization
Ans : C
Ans : C
Ans : A
Ans : D
A. 1.5
B. 1.6 BAC = 2,000
C. 1.7 EV = 1,200
D. 1.8 Ac = 1,500
Ans : B
TCPI = (BAC-EV)/(BAC-AC)
The TCPI is 1.6.
Did you realize when the question stated work complete of 1,200 that was the earned
value of the project? Remember we need to quantify work and the easiest way is using a
dollar amount. Considering the answer, is this a good thing or a bad thing? Since,
TCPI is > 1, the project is tracking on pace and no adjustment is need – which is a
good thing.
SN Panigrahi, Essenpee Business Solutions,
India
260
Your project, with a budget at completion of $1,500, currently has a planned value
of 400, earned value of 350, and actual cost of 450. The current work and all
variances to date are expected to continue; based on this, what is the estimate to
complete the project?
A. 1474
B. 1266
C. 1500
D. 1400
A. 1266
BAC PV EV AC
$1,500 $ 400 $ 350 $ 450
CPI SPI
0.78 0.88
EAC ETC
AC + (BAC-EV) / 1716 ETC = EAC – AC 1266
CPI*SPI
SN Panigrahi, Essenpee Business Solutions,
India
261
For the first three questions, assume you are managing the following project:
You are the project manager of a project that is budgeted to cost $1 million at completion. The project will
last ten months and its budget is spread evenly across each month. It is currently 50% complete and has so
far cost $750K but only produced value of $500K.
Ans
C. $300K – This problem is a good example of (1) not just memorizing the
formula but knowing what goes into it and (2) avoiding extraneous information.
The problem sets you up to think that you’ll be using this formula: PTA = [(Ceiling
– Target)/Buyer’s Share Ratio] + Target. Actually, you just need to know that the
Target Price is made up of both the Buyer’s Target Cost and the Seller’s Target
Profit. $1.8 million – $1.5 million = $300K in target profit for the seller.
Ans
B. 105 – The formula for determining the number of
communication channels on a project is [n(n-1)]/2,
where n is the number of project team members.
Don’t forget to include the project manager! In this
problem, n=15, but you may have accidentally
said n=14 if you forgot the PM.
You work for a seller that is bidding on a contract. Which type of contract has the
MOST risk for your company?
A. CPIF
B. T&M
C. FP
D. CPAF
Ans : C
SN Panigrahi, Essenpee Business Solutions,
India
266
Your company has two projects to choose from. Project A is a billing software
project for the Accounts payable department; in the end it will make the
company around $400,000 when it has been rolled out to all the employees in
that department. Project B is a payroll application that will make the company
around $388,000 when it has been put to use throughout the company. After a
long deliberation, your board chooses to go ahead with Project B. What is the
opportunity cost for choosing Project B over Project A?
A. $388,000
B. $400,000
C. $12,000
D. 1.2
Ans : B
a) $15,000
b) $5,000
c) $25,000
d) $30,000
The correct answer is C. Opportunity Cost is the potential return of the project not selected. In this case we did not
select Project A, so it is $25,000 – Next Best.
There is extra unrelated information in this question; IRR is not relevant when evaluating opportunity cost. Once all
of the unnecessary information is filtered out the questions is simply asking what is the dollar value associated with
Project A.
a) $5,000
b) $4,000
c) $9,000
d) $10,000
A. 12
B. 12.5
C. 13
D. 14
Answer: B
Let M represent the number of months. To break even you need to have
the cost of buying = to the cost of leasing.
M = 12.5 months
No if you intend to use that piece of equipment less than 12.5 months, it is better to lease it than buy. If you plan to
use it more than 12.5 months then you may consider buying it to save money for the project.
Do understand how this technique help the project manager to optimize the cost of the project and save money by
choosing the best alternative.
SN Panigrahi, Essenpee Business Solutions, India 271
SN Panigrahi, Essenpee Business Solutions, India 272
You have completed the work breakdown structure for the project. In order to move ahead, you are
planning to get an approval from the customer on the WBS. However, the customer is not interested in
seeing the minute details. She is more interested in seeing significant information. Which of the following
process will generate the deliverable customer is looking for?
Ans : B
A. Create the SOW yourself since you are the project manager
B. Look for the SOW in your organizational process assets (OPAs)
C. Ask your customer to provide you with the SOW
D. Ask your CEO to provide you with the SOW
Ans : C
Explanation: Since your company has been awarded the contract, you would need the project's procurement
SOW agreed upon in the Conduct Procurements process for selecting a seller or in the contract, if there is a
signed agreement in place. Among the four answer choices, the best option is to ask the customer for the SOW.
Asking the customer (i.e., the buyer) for the SOW ensures you have the version that was approved from the
customer's perspective. In addition, collaborating with the initiating company allows you to have a better
understanding of the project purpose, objectives, and expected benefits that will help in crafting the project charter.
You are the project manager of a project that is budgeted to cost $1 million at completion. The
project will last ten months and its budget is spread evenly across each month. It is currently
50% complete and has so far cost $750K but only produced value of $500K.
A. $0 – Schedule Variance = Earned Value – Planned Value, or SV = EV – PV. The project’s current value at
50% completion is stated in the problem as $500K. To determine the Planned Value, use the project’s original
BAC times percentage complete: $1 million * 50% = $500K. SV = EV – PV = $500K – $500K = $0. The
project is on schedule.
A. 0.67
B. 1
C. 1.5
D. 2
A. $500K
B. $750K
C. $1 million
D. $1.25 million
D. $1.25 million – The variance is expected to go away, so use the formula AC + BAC – EV = $700K
+ $1 million – $500K = $1.2 million.
A. 4.6 days
B. 5 days
C. 6 days
D. 9.3 days
C. 6 days – Your typical PERT estimate is shown by the formula (P + 4L + O)/6, but this problem wants
you to use the triangular PERT estimate instead. (P + L + O)/3 = (10 + 5 + 3)/3 = 18/3 = 6 days. Did you
use the wrong formula because you were moving too fast? Remember to slow down!
B. 105 – The formula for determining the number of communication channels on a project is [n(n-1)]/2,
where n is the number of project team members. Don’t forget to include the project manager! In this
problem, n=15, but you may have accidentally said n=14 if you forgot the PM.
A. $150K
B. $200K
C. $300K
D. $1.5 million
C. $300K – This problem is a good example of (1) not just memorizing the formula but knowing what goes
into it and (2) avoiding extraneous information. The problem sets you up to think that you’ll be using this
formula: PTA = [(Ceiling – Target)/Buyer’s Share Ratio] + Target. Actually, you just need to know that the
Target Price is made up of both the Buyer’s Target Cost and the Seller’s Target Profit. $1.8 million – $1.5
million = $300K in target profit for the seller.
A. 0
B. 3
C. 7
D. 10
B. 3 – Network diagram math questions can be tricky, because they are almost like logic questions
rather than math. For this one, know that free float (which is float on an activity) = ES of following
activity – ES of present activity – present activity duration. We are determining the free float for
Activity X. ES of following is easy because it is stated as 27. The duration of Activity X is also stated
as four days. You need to use the ES information (day 20) and the duration (4 days). So since free
float = ES of following activity – ES of present activity – present activity duration = 27 – 20 – 4 = 3.
A. $1,359,252
B. $1,567,398
C. $1,784,972
D. $2 million
B. $1,567,398 – Get those PV & FV formulas on your brain dump. Again, this is one of those problems
that may or may not surface on your exam. It did for me! (But depreciation didn’t.) Present Value = FV /
[(1 + r)^n], where r is the rate of return and n is the number of years = $2 million / [(1 + .05)^5].
A. Project A
B. Project B
C. Project C
D. This problem cannot be solved without knowing the interest rate for each project.
C. Project C – For project evaluation dealing with internal rate of return (IRR), return on investment
(ROI), and net present value (NPV), simply pick the greatest value. Easy!
A. $1250
B. $2000
C. $2250
D. $2500
C. $2250 – (Asset Cost – Scrap Value) / Useful Life = ($10K – $1K) / 4 = $2250 per year. It is possible,
though not certain, that you will encounter a depreciation problem on your PMP exam, though I
happened not to encounter one. Add the formulas to your brain dump anyway — a point is a point.
Explanation:The Identify Stakeholders process is the process of identifying all people or organizations
impacted by the project and documenting relevant information regarding their interests, involvement, and
impact on project success. Both the Develop Project Charter process and the Identify Stakeholders process
are part of the Initiating Process Group which should be completed before proceeding to the processes in
the Planning Process Group. In this scenario, since the project charter has been developed and approved,
the Identify Stakeholders process should be performed next.
Based on this scenario, the sponsor can be classified as high-power and low-interest; therefore, the correct
answer is to keep the sponsor satisfied.
Ans : B
Explanation:In this scenario, the project sponsor requested a document that provides specific information
about the product requirements of your current project. The requirements traceability matrix is a grid that
links product requirements from their origin to the deliverables that satisfy them. Typical attributes used in
the requirements traceability matrix may include a unique identifier, a textual description of the requirement,
the rationale for inclusion, owner, source, priority, version, current status, and status date. Additional
attributes to ensure that the requirement has met stakeholders' satisfaction may include stability, complexity,
and acceptance criteria.
Ans : B
Explanation:The question states that project planning is about to begin which suggests that project
initiation has been completed. The project charter is created during the Develop Project Charter process
as part of project initiation. The project team uses the project charter as a starting point for initial project
planning. The type and amount of information in the project charter varies depending on the complexity of
the project and the information known at the time of its creation. At a minimum, the project charter should
define the high-level information about the project that will be elaborated in the various components of the
project management plan.
Ans : A
Explanation:The question suggests that the project manager is performing the Collect Requirements
process, which is the process of determining, documenting, and managing stakeholder needs and
requirements to meet project objectives. A context diagram is one of the tools and techniques that might
be used during the Collect Requirements process. A context diagram is a visual depiction of the product
scope showing a business system (process, equipment, computer system, etc.), and how people and
other systems (actors) interact with it. Of the available choices, developing the context diagram is the
best way to implement the stakeholder’s suggestion.
Ans : B
Explanation:The Peter Principle states "In a hierarchy, every employee tends to rise to his/her level of
incompetence." Most project team members are motivated by an opportunity to grow, accomplish, and
apply their professional skills to meet new challenges. Their achievements continuously promote them
within an organization to a certain level until they are unable to perform. Sam might have risen to his
incompetency level. While the topic of this question is not included in the PMBOK® Guide, the Project
Management Professional (PMP)® Examination Content Outline, June 2015, covers cross-cutting
knowledge and skills with which PMP aspirants are expected to be familiar.
Note, the PMBOK® Guide is provided as a reference to indicate that the Acquire Resources process
described in the scenario.
Ans : D
Corrective action based on causes
Ans : B
Explanation:All of the available answers seem like possible options in this scenario, but the question is
specifically asking what you should do 'first'. Although you have already analyzed the situation and you know
what corrective actions are required, you must follow the proper change control procedure. A configuration
element is a project artifact that has been placed under configuration control. Any change to a configuration
element should be formally controlled and will require a change request. Since the question describes a
situation requiring a change to a configuration element, the first thing you should do is submit a change
request and have it approved before you can implement the changes.
Ans : A
Explanation:
Monitor and Control Project Work is the process of tracking, reviewing, and reporting overall progress to meet
the performance objectives defined in the project management plan. Of the available choices, only comparing
actual project performance against the project management plan is performed during the Monitor and Control
Project Work process.
members of the CCB. Based on this scenario, which of the following activities might be performed by members of the
CCB?
A. Creating a change request
B. Implementing approved change requests to achieve the project's objectives
C. Evaluating changes to project artifacts not specified in the configuration management plan
D. Monitoring implementation of approved change requests as they occur
Ans : A
Explanation:The change control board (CCB) is a formally chartered group responsible for reviewing,
evaluating, approving, deferring, or rejecting change requests. The CCB can include project stakeholders,
and a change may be requested by any stakeholder involved with the project. Therefore, it is possible for a
member of the CCB to create and submit a change request.
Ans: A
Explanation:The to-complete performance index (TCPI) is a measure of the cost performance that is
required to be achieved with the remaining resources in order to meet a specified management goal,
expressed as the ratio of the cost to finish the outstanding work to the remaining budget. A TCPI value
equal to 1.0 means you are right on budget, and as long as you maintain the present cost performance
index (CPI), you should not exceed the project budget. A TCPI value greater than 1.0 means you need
to take a stricter cost management approach or you will exceed your budget at completion (BAC). A
TCPI value less than 1.0 indicates you are within your budget and have done an excellent job of
managing project costs.
Ans : A
Explanation: Based on the scenario described, the project team is performing the Estimate Activity Durations
process. An input to this process is the resource breakdown structure (RBS) which is a hierarchical list of team
and physical resources related by category and resource type that is used for planning, managing, and
controlling project work. Each descending level represents an increasingly detailed description of the resource
until the information is small enough to be used in conjunction with the WBS to allow the work to be planned,
monitored, and controlled.
Ans : B
Explanation:This scenario is an example of statistical sampling since it involves the team selecting 20 out
of 50 engineering drawings at random to measure accuracy and completeness. Statistical sampling is
among the data gathering techniques that can be used as part of the Control Quality process. Statistical
sampling is often applied when inspecting the entire population would be too costly or time-consuming. In
this instance, given that the project is on a tight schedule and budget, statistical sampling makes sense to
use to inspect the engineering drawings.
E. Ans : B
F. Explanation:Design for X (DfX) is a set of technical guidelines that may be applied during the
design of a product for the optimization of a specific aspect of the design. In this scenario, technical
guidelines are being applied to design a new modular home that optimizes its manufacturability. DfX
provides the most accurate and precise definition of the technique being used in this scenario and is,
therefore, of the available choices, is the best answer to the question asked.
Ans : D
Explanation:The assumption log is a project document used to record all assumptions and constraints
throughout the project life cycle. The assumption log is created as an output of the Develop Project Charter
process, as such limited information is available to create this project document. High-level strategic and
operational assumptions and constraints are normally identified in the business case before the project is
initiated and will flow into the project charter. Lower-level activity and task assumptions are generated
throughout the project. The assumption log is used to record all assumptions and constraints throughout the
project life cycle. Therefore, of the available options, the project business case is the best source of
information to use in the development of the assumption log.
Ans : A
Explanation:To answer this question, first, determine under which knowledge area the described activities
fall. With reference to sponsors and stakeholders, you may guess that it is Stakeholder Management.
However, the activities of collection, creation, distribution, storage, and monitoring project information fall
under Communications Management.
Next, determine what process group is related to these activities. Is it Planning or Monitoring & Controlling?
No, the task is not to develop the communication models in Planning, nor is the task to identify if the planned
communications artifacts and activities have had the desired effect. Instead, the current activities are mostly
collection, creation and distribution and delivery, which take place while executing the work of the project. An
important clue is that you are distributing work performance reports, which is an output of the Direct and
Manage Project Work process in the Integration knowledge area, in the Executing process group.
Therefore, the correct answer is that these activities fall under Manage Communications.
SN Panigrahi, Essenpee Business Solutions, India 305
All of the below are inputs to Define Scope process EXCEPT:
1.Project Charter
2.Requirements Document
3.Organizational process assets
4.Project Management Plan
CORRECT: A
A. 11
B. 14
C. 9
D. 13
Ans : A
Explanation:Ideally, to learn about all identified risks on the project, the project sponsor would have to
review the risk register. However, the question states that the project manager is about to start project
planning, implying that the risk register, which is created during the Identify Risks process, is not yet
available. At this point in the project, only the project charter can serve the needs of the project sponsor as
it contains a list of high-level risks that were identified at the time the project charter was drafted and
approved.
Ans : A
Explanation:The scenario implies you are performing the Manage Stakeholder Engagement process which
is concerned with communicating and working with stakeholders to meet their needs, address issues, and
foster involvement. One of the inputs to this process is the project management plan which provides
guidance regarding stakeholder communications, risk management, change management, and stakeholder
engagement. Specifically, the stakeholder engagement plan contains information on how to manage
stakeholder expectations thus helping to determine how to engage the stakeholders effectively.
Ans : B
Explanation:Central to knowledge management is having the right processes and people with the right
knowledge. Having documents that identify the people and their capabilities are essential to identifying
current knowledge and the gaps that may exist. Keep in mind that the question is asking for the document
that will be 'least' beneficial in this process. The requirements documentation provides a description of how
individual requirements meet the business need for the project. Requirements documents do not identify the
people or processes needed, whereas the other options, namely the lessons learned register, the resource
breakdown structure and project team assignments are useful in determining what is required for a
knowledge management system. Therefore, of the available choices, reading the requirements
documentation would be the least beneficial for establishing a knowledge management system for the
project and is, therefore, the best answer to the question asked.
A. Ask the team members to record any issues they encounter into the issue log
B. Review the stakeholder register with the new team members
C. Schedule a meeting with the new team members and all project stakeholders
D. Submit a change request to update the stakeholder engagement plan
Ans : B
Explanation:The stakeholder register is a project document that contains all current information about the
stakeholders. The stakeholder register includes stakeholder identification information, assessment
information, and the stakeholder classification. It is used by the project team to maintain information about
the stakeholder's expectations and interests with the project. By reviewing the stakeholder register with the
new team members, the project manager can provide them with the information about each project
stakeholder, politics surrounding the project, and other relevant details about the project and the
stakeholders that may help the new team members to get up to speed with the overall dynamics of the
project and engage effectively with the project stakeholders.
If Yes
Then Click
“Like”
https://www.youtube.com/channel/UCVZ
ScNa_leR8XbYINEwTFwQ/videos
Project Management
PMP Certification Training
FIDIC Forms of Contract
Contact Details:
SN Panigrahi
9652571117
snpanigrahi1963@gmail.com SN Panigrahi, Essenpee Business
316
Solutions, India