Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

DETAILED

ENGINEERING
REQUIREMEN
TS FOR THE
CONSTRUCTIO
N OF NEW
FIRE STATION

POLILLO FIRE STATION


POLILLO, QUEZON BFP R4-A
TABLE OF CONTENT
Detailed Engineering as required for Paragraph 17.6 Rule IV in relation
to ANNEX “A” of the Revised IRR of RA 9184’s 2016

1. Survey
2. Site Investigation
3. Soil and Foundation Investigation
4. Construction Materials Investigation
5. Preparation of Design Plans
6. Preparation of Technical Specifications
7. Preparation of Quantity and Cost Estimates
8. Preparation of Program of Work
9. Preparation of Proposed of Construction Schedule (and estimated Cash
Flow for Project with schedule of over 6 months)
10.Preparation of Site or Right – of – Way Plans including Schedule of
Acquisition
11.Preparation of Utility Relocation Plan
12.Preparation of Submission Design Report
13.Environmental Impact Statement for critical projects as defined by the
Department of Environment and Natural Resources (DENR)
14.Preparation of minimum requirements for Construction Safety and Health
Program for the project being considered
15.Preparation of Bid / Tender Documents

You might also like