The document provides an overview of shipboard crane design and maintenance. It explains that shipboard cranes are usually electro-hydraulic and perform hoisting, luffing, and slewing functions. It then describes twin cranes that allow lifting of double loads. The document outlines extensive maintenance procedures for cranes, including daily inspections when in use, regular maintenance checks, annual thorough surveys, and retesting cranes every 4-5 years. It also discusses crane operation procedures and keeping of spare parts.
The document provides an overview of shipboard crane design and maintenance. It explains that shipboard cranes are usually electro-hydraulic and perform hoisting, luffing, and slewing functions. It then describes twin cranes that allow lifting of double loads. The document outlines extensive maintenance procedures for cranes, including daily inspections when in use, regular maintenance checks, annual thorough surveys, and retesting cranes every 4-5 years. It also discusses crane operation procedures and keeping of spare parts.
The document provides an overview of shipboard crane design and maintenance. It explains that shipboard cranes are usually electro-hydraulic and perform hoisting, luffing, and slewing functions. It then describes twin cranes that allow lifting of double loads. The document outlines extensive maintenance procedures for cranes, including daily inspections when in use, regular maintenance checks, annual thorough surveys, and retesting cranes every 4-5 years. It also discusses crane operation procedures and keeping of spare parts.
• Shipboard cranes of bulk carriers are usually of electro-hydraulic design. • A crane is normally required to do three functions-namely, to hoist (or lower), to luff and to slew. • Hoisting is the raising of the crane wire whilst the crane jib remains in constant position. • Luffing is the raising or lowering of the crane jib. • Slewing is the swinging round (or rotating) of the crane. • It is common for shipboard cranes to be level Luffing. This means that if the craned is topped from maximum to minimum radius, or vice versa, the crane hook will maintain a level path, allowing the load to move horizontally. • The power which enables the crane to hoist, luff and slew is provided by electric motors which drive hydraulic pumps. The hydraulic pumps drive the hydraulic motors which drives the hoisting, Luffing and slewing winches/drives. • Twin cranes (also called Gemini cranes) have been fitted to some conbulk and forest product ships. These are two independent cranes of equal capacity mounted on a common platform. The common platform can be rotated independently and the cranes can be slewed relative to the platform. Each can be used by itself, with each serving adjoining holds, but when a heavy lift is required is required the jibs are slewed parallel to one another and a lifting beam is attached between the crane hooks. This arrangement allows the lifting of loads up to twice the safe working load of one crane. The speeds of hoisting and luffing motions of the cranes are synchronized to ensure smooth operation. When the cranes are operated in the twin mode the individual slewing motions are inoperable and only platform slewing motion can be used. Operation of the platform slewing motion causes the platform to rotate and with it the two cranes, with their jibs parallel, thus enabling large loads to be safely slewed. • If the shipboard cranes are intended to be used with grabs, as grabbing cranes they are likely to be fitted with rope-operated grabs, for which the crane will be provided with two rope drums (third for luffing of beam, also)and two wire ropes, one to hold the grab and the other to open and close it. Alternatively, electro-hydraulic grabs which are easy to fit to existing cranes and grabs can also be operated by remote radio control. This system replaces the simple but inefficient self-dumping grabs which are used on a single fall of wire rope. Crane maintenance: The detailed maintenance required by cranes depends upon their construction, and must be learnt from their instruction manuals, which provide detailed guidance as to frequency of service, materials and tools to use and items to inspect. The main areas which require attention are the following: • Daily, when cranes are being used to work cargo: Inspect runner wires for wear or damage. Check the rig for damage for damage and for fastenings becoming slack. Check the limits and cutout switches. Carry out oiling and greasing as necessary. Ensure the ventilation for the crane motors is open, to prevent overheating. • Before arrival in port: Follow the procedures recommended by the crane manufacturers. They should include all the inspections and listed for regular maintenance (as below) • Regular maintenance, (normally described in makers manual of planned maintenance system): a) The filters of the hydraulic system must be regularly cleaned or renewed and the hydraulic oil must be changed as required by the manufacturers or as guided by the results of Lubricating oil tests. b) Oil in the gearboxes to be checked and topped up to the correct level and changed at the required intervals. c) Suitable grease must be applied to all moving parts of the system, such as the bearings of winches and sheaves, the turret bearings, pivot points or hinges for jib and roller slewing ring. When crane is required to operate regularly in temperature below freezing, grease, should be low temperature grease. d) Wire rope should be regreased when they are visibly dry or when ‘bald spots’ form in the grease on the outer surface, or when corrosion exists. e) Wire ropes must be inspected for flattening and kinking, and for broken, worn or corroded wire, and must be condemned when more than 5 percent of the wires in any length of ten rope diameters are damaged. For example, if the wire ripe is 24 mm and is of 6 x 37 construction, the total numbers of wire rope is 222, of which 5 percent is 11. So, if more than 11 broken stand are found in a length of (24 x 10) mm= 240 mm- the rope must be condemned (i.e. discarded and renewed). f) The brakes for hoisting winch and for slewing and luffing machinery must be inspected for contamination with oil, for damage to the adjustments, and for wear. Where necessary they must be degreased – for example, wit trichloroethylene- or the linings must be renewed. g) All parts of the crane must be inspected for damage and for fastenings or fittings which have become loose, worn or fractured as a consequence of blows, vibration or working in a seaway. Loose or damaged slewing ring securing bolts, for example, would seriously reduce the safe lifting capacity of the crane. h) Crane winch drums must be inspected to ensure that the wire ropes remain firmly attached to them and the attachment must be freed when necessary and then refastened to ensure that it can be freed when necessary. Wire must be correctly spooled on to the drums without crossing turns. i) Deck cranes are provided with limit switches to prevent over-hoisting, over-lowering, and luffing, slewing or travelling beyond permitted limits. When a limit switch operates the crane cannot pass the limit, but still retains the power to move away from the limit. Limit-switches and their over-ride keys must be tested frequently and certainly before each port visit to ensure that they work and they are properly adjusted to operate in a correct position. The over-ride keys should be kept safely in the care of a responsible officer. j) The emergency cutout stops all power to all controls on the crane, by tripping the main electrical breaker, as soon as it is activated. The brakes on the hoisting and luffing winches are spring- loaded, and will close tight if power is lost, holding the crane and its load fixed. The emergency cutout can be activated by the crane operator and will operate automatically if there is a power failure or if crane is overloaded. The emergency cutout is tested by hitting the cutout button, and by overloading under controlled conditions when the cranes are retested. k) High temperature trips and low oil level trips, if fitted, must also be checked regularly and maintained in good condition. l) The crane cab and machinery must be kept clean and light bulbs must be renewed. Cracked or broken windows and plastic windows which have become opaque or dull must be renewed. The sun visor is essential to prevent the driver from being dazzled and must be maintained in good condition. m) Heaters for the crane are normally on a separate power circuit to that for driving the crane. They should be remained switched on throughout the voyage to keep the electrical equipment for the crane warm and dry. The correct operation of the cooling fans should be confirmed. n) The crane maintenance programme is likely to depend upon the crane operating hours, so a record of these should be kept. o) Electrical maintenance should include the occasional checking of all terminal screws in the switchgear cabinets, terminal boxes on the equipment itself, and tightening if slack. p) Sheaves should be inspected for damage from time to time, particularly when the crane is being used with a self dumping grab. The operation of such grabs can cause a ‘ripple’ in the wire rope fall, which may jump out of its own sheave and finish up in the next sheave, or jammed between two sheaves. q) The planned maintenance programme for a handymax bulk carrier requires, at six monthly intervals, inspection of sheaves and the brake linings for wear down. Renewal of hoisting and luffing wires should be when required or every 1000 working hours or two years, whichever comes first.
• Spares to be carried: A minimum stock of all items that could malfunction from the smallest electrical switch or relay to a complete main hydraulic motor and pump must be carried. There is usually a requirement of at least two spare hoisting and luffing wires to be carried by a ship with four cranes.
• Annual thorough survey :
a) The annual thorough survey of a crane is carried out by a surveyor representing a statutory authority or a classification society, and the nature and extent of the survey is described in the classification society publications. Besides covering all the areas listed above under ‘maintenance’, the structure of the crane will be carefully examined for strength with hammer testing and drilling of the material when found necessary. Sheaves may be unshipped for inspection. The grease of the slew bearing may be sent to laboratory for testing the iron particles in it to ascertain the wear of the bearing. b) The cranes must be retested at four or five- yearly intervals, or more often if found necessary.
Operation of the cranes:
a) The ship’s officers can keep the limit switches override key in their possession, thus ensuring that the limits cannot be overridden without their knowledge. Keys to the cabinet containing the main power breaker should be kept by the duty officer who can then be certain that the crane cannot be restarted by an unauthorized person after it has been immobilized. It is good practice to immobilize the cranes at the end of the working day and any time that they are maintained. b) It may be necessary to override a limit switch to stow or unstow the crane jib, or to move it to other exceptional positions whilst it is carrying no load. This must be done under the supervision of a competent ship’s personnel. c) Cranes must be driven smoothly. d) When shore gang is employed to drive cranes they will require careful supervision from ship’s officers to ensure that they use ship’s equipment safely and do not damage it.