Professional Documents
Culture Documents
Composite Solutions The Design and Construction of Mechanically Stabilized Earth Structures in Areas With Challenging Ground Conditions
Composite Solutions The Design and Construction of Mechanically Stabilized Earth Structures in Areas With Challenging Ground Conditions
2
PRC Licensed Civil Engineer; MSCE (Geotechnical Engineering)
2
Faculty, Bicol University, College of Engineering, Legazpi City;
2
Geotechnical Consultant, PGA-Earth Structure Solutions, Inc.
2
PRC Licensed Civil Engineer; MSCE (MSCE Structural and Geotechnical Engineering)
3
President, EM2A Partners and Company, Inc.;
3
President, Philippine GeoAnalytics, Inc.;
3
President, PGA-Geopier, Inc.;
3
PRC Licensed Civil Engineer; MSCE (Geotechnical Engineering) Engineer;
3
PICE Accredited Geotechnical Specialist;
Abstract: Uniaxial extruded HDPE geogrid-reinforced Mechanically Stabilized Earth (MSE) walls and slopes are gaining
popularity locally as versatile alternatives to rigid gravity walls, and reinforced concrete retaining structures. Advances in
material sciences and technology, field and laboratory performance testing, as well as advanced computational methods have
all contributed to the development and commercial viability of this technology. With the recent push to increase infrastructure
outside of the congested urban centers, more construction works are being constructed in vast, wide open expanses of land.
Inevitably, there will be cases wherein the in-situ soils would not be strong enough to adequately support the additional loads
imposed by MSE structures. Given these, some form of ground improvement on the subsurface soils would be necessary for
such earth structures to have satisfactory short -and- long term performance. This paper contains several case histories of MSE
projects built in such areas where combinations of geotechnical issues exist.
1
walls in which the soil is reinforced by thin, artificial
1 INTRODUCTION reinforcing elements (steel, fabric, fibers, etc.) (Budhu,
These structures are normally utilized in retaining walls,
The reinforcement of soil has long been practiced in ancient steep fills, bridge abutments, seawalls, dikes, earth
times. Recent advances in construction technologies and embankments and the like. Although the basic principles
methodologies have brought about the manifestation of this of MSE have been used throughout history, MSE was
ancient soil stabilization technique into its current form, and developed in its current form in the 1960s and has slowly
new techniques continue to emerge and develop. These evolved into becoming one of the technologies of choice for
retaining structures play a vital role in stabilizing slopes retaining structures.
(FHWA, 2001). Geosynthetic-reinforced Mechanically
Stabilized Earth (MSE) walls are currently gaining
popularity as versatile alternatives to rigid gravity walls and
reinforced concrete retaining structures in construction
projects where there are soil retention and grade separation
requirements.
2.1 History
Typically, these MSE structures are gravity-type retaining Fig. 2 MSE wall main components (Image courtesy of
2
E’GRID Geosynthetics)
These are:
a) determination of the wall or slope’s geometry
b) establishment of engineering properties of the in-situ soils
based on site exploration and testing,
c) determination of loads and hydrologic conditions,
d) hazard identification,
e) setting of performance criteria,
f) selection of reinforcement to be used (HDPE, steel, etc.)
g) selection of type facing to be used (vegetated, precast Fig. 3 Circular slip surface with overlying soil mass
concrete, polymer gabions, etc.) subdivided into vertical slices. (From Duncan & Wright,
internal stability analyses, 2005)
h) external stability analyses (bearing capacity, global slope
stability, etc.) The equations for the factor of safety calculations by both
i) detailing (internal and external drainage, connection/s, Ordinary Method of Slices and Simplified Bishop
below ground reinforcement, etc.) procedures are primarily based on the assumptions that the
only driving forces are due to the weight of the soil mass,
It is imperative that the designer have a firm grasp on the and the only resisting forces are those due to the shear
project’s specifics (i.e. loads, design height/s, slope strength of the soil.
geometry, in-situ soil parameters etc.) and required Oftentimes, there are additional known driving forces
performance criteria (i.e. allowable settlement, tolerances for involved such as slopes that have water adjacent to them or
tilt, compaction requirements, etc.) to come up with a robust slopes that support additional surcharge loads due to traffic
yet cost-effective design. and heavy equipment or stockpiled materials.
3
With the recent push to increase infrastructure spending in geogrids, and a 1.0 m high wrap-around wall using E’Grid
undeveloped areas throughout the Philippine archipelago, 50R HDPE uniaxial geogrids. A geotextile separator was
more and more construction works of considerable size and incorporated in the design to prevent washing out of soils
scale are being constructed in vast expanses of land. It is from the structure.
inevitable that in some of these projects, some portions of
the MSE works would fall in areas with challenging Post Construction Observations
geotechnical and topographical conditions. There will be After Geopier ground improvement measures (Impact Piers
cases wherein the in-situ soils, in their natural state, would and GP3) were installed, the pace of the construction was
not be strong enough to adequately support the additional significantly faster as the base of the MSE was stabilized
loads imposed by these MSE structures. There will also be significantly and heavy machineries were able to enter to
cases wherein the heavy loads imposed by these earth proceed with earth moving works. Due to the alternating
structures would trigger settlement well beyond the construction sequence and the combination of geosynthetic
tolerances of these ductile structures. There have also been systems used, there were barely any signs of excessive
cases where these MSE structures are underlain by settlement or tilting on the wall face even years after its
liquefiable ground. It is in these instances that some form of construction.
ground improvement on the subsurface soils would be
necessary for such earth structures to have satisfactory short- 4.2 Case Study 2 – Mechanically Stabilized Earth (MSE)
term and long-term performance. Wall for an Industrial Facility
4 CASE STUDIES This sample case is a seaward land reclamation project for
an industrial plant facility with heavily loaded process
This paper contains several case histories of MSE projects structures. The industrial plant facility is located within a
built in such areas where a combination of two or more petrochemical complex in Batangas. The site is sitting in a
engineering issues (slope stability, erosion, bearing capacity, hilly terrain fronting Batangas Bay to the West. Areas are
liquefaction, excessive settlement, topographic constraints, predominantly filled up as the general area was reclaimed
etc.) exist. The design analyses and construction of these from the sea. The resulting maximum average reclaimed fill
composite systems will likewise be discussed. height is approximately 19.0 meters.
4.1 Case Study 1- Design and Build of Slope Protection Issues and Challenges
Works in Metro Manila Owing to the peculiar location of the project site, and the
reclamation activities to be conducted, flooding, scouring,
The first sample case presented herein is a design and build slope instability, settlement and seismic issues were
project for a private development in Metro Manila requiring identified as problems that need to be addressed. The soil
a 1.5km long earth retaining structure and 200+m of two- investigation conducted shows that the subsurface soils
sided creek bank protection. (approximately 1.0 to 11.0-meter depth) were generally
relatively poor to medium in density. The relatively poor
Issues and Challenges underlying soils would have been both highly compressible
The biggest challenge for this project is the difficulty in and subject to large deformations during shaking from a
working in the project site due to space constraints, weak large earthquake event. The deformations would be beyond
and unstable soils, plus the need to accomplish the work tolerable limits. The proposed embankment needs to be
within a tight time frame. During the construction phase, the supported on either piles or improved ground. Also, there
monsoon season was fast approaching, and creek protection was a sand layer near the riverbed that was potentially
works along the creek had to be completed at least up liquefiable.
somewhere slightly above the mean flood level so that
construction works could be undertaken continuously. Design Solution
After evaluating the results of the analyses, a complex slope
Additionally, during the start of the excavation works, it was with an E’Grid Polymer Gabion-faced bottom tier MSE and
found out that the soils along the creek had both liquefiable a Green-Faced E’Grid RSS using 65R, 90R and 130R
and highly compressible layers. E’Grid uniaxial geogrids was designed. The complex slope
has a total height of 19.0 m (6.0 m E’Grid Polymer Gabion
Design Solution Wall + 13.0 m Vegetated Wall). Impact Piers were installed
The perimeter wall was protected by an MSE Wall using as ground improvement measures to increase the shear
E’Grid 50R HDPE uniaxial geogrids and polymer gabions strength of foundation soils, minimize differential settlement
using E’Grid 3030 PP biaxial geogrids. The facing of the and reduce the risk of possible large seismically induced
wall was vegetated to render the wall more aesthetically deformations.
pleasing.
4.3 Case Study 3 – Geogrid-Reinforced Mechanically
The creek bank was protected by a 2.0m high polymer Stabilized Earth (MSE) Wall with ESS-Shield Precast
gabion mattress (106m both sides) using 3030 E’Grid biaxial Panel Facing supported by Rammed Aggregate Piers
4
This sample case project features a geosynthetic- In summary:
reinforced MSE Wall with pre-cast concrete panel • The modern application of soil reinforcement began
facing elements supported by Geopier Impact piers for as early as the 1960s.
a toll road in Metro Manila. • MSE walls and slopes have slowly started to gain
ground locally as the system of choice for earth
Historically, the backfill of pre-cast concrete panel- retention projects due to their relative lower costs
faced MSE walls have been typically reinforced by and inherent ductility.
metal strips. Metal strips have at times been observed • MSE walls come in different shapes and sizes, with
to eventually corrode (even when coated with a thin different reinforcements and facing elements.
rust protection material). This corrosion is especially • Proper compaction of properly selected backfill
worrisome if it happens at the point of connection soils though very important is often overlooked.
between the facing element and the soil reinforcement • Detailing is key for long-term stability.
strip. • MSE walls can be used in a myriad of situations,
under varying geotechnical and topographic
Recent advances in materials and manufacturing conditions. If designed properly (and with the help
technology have made it possible to reinforce MSE of ground improvement measures), these can still
fills with HDPE geogrids. Geogrids are ideal for this be built in areas underlain by soft soils or steep
particular application as these will not corrode nor slopes.
degrade due to the chemical attack of the concrete and • Analyze and evaluate more than one mode of
the backfill material. Geogrids also provide a larger failure when assessing the internal and external
amount of soil coverage within the reinforced zone. stability of reinforced walls and slopes.
• The use of Geopier Rammed Aggregate Piers as
Issues and Challenges ground improvement measures for MSE walls and
During the construction of the MSE wall, it was found out slopes underlain by compressible or liquefiable
that there were pockets of weak, compressible material that ground proved to be effective in several instances.
could cause potential excessive settlement of the structure. If
left untreated, these weak soils could also potentially cause ACKNOWLEDGMENT
slope instability.
The authors wish to acknowledge with gratitude the
After conducting confirmatory borings to verify the initial Philippine Institute of Civil Engineers for this opportunity to
observations from the foundation excavation works, it was contribute to the local geotechnical engineering field and to
deemed that the subsurface soils for that particular part of share knowledge to fellow Filipino civil engineers. Also,
the project was in fact weak as initially suspected. Using the thanks go out to members of the PGATECH Group of
updated soil parameters, the designer’s stability analyses Companies, E’GRID Geogrids, and Geopier Foundation
yielded unsatisfactory factors of safety for both static and Company (USA) for sharing their resources and providing
seismic conditions making ground improvement necessary. key technical information used in this paper.
Design Solution
It was determined that the use of Geopier Impact Piers REFERENCES
would be a cost-effective ground improvement measure to
reinforce the in-situ weak soils underlying the proposed pre- Budhu, Muni. 2011. Soil Mechanics and Foundation, 3 rd
cas concrete panel-faced MSE wall. Edition, John Wiley and Sons, Inc., USA.
Bilaro, Anna, May 2013. Mechanically Stabilized Earth
Impact Piers were once again utilized to increase the shear Walls. PICE Regional Technical Conference, Legazpi City,
strength of the weak foundation soils and minimize potential Albay.
differential settlements. Das,Braja M. 1994. Principles of Geotechnical Engineering,
3rd Edition. PWS Publishing Company20 Park Plaza,
5 CONCLUSION Boston, Massachusetts 02116.
Department of Public Works and Highways (DPWH),
Compared to traditional and conventional solutions in earth Standard Specifications for Highways Bridges and
retaining structures, MSE walls offer a remarkable Airports.
advantage when it comes to economic and technical aspects. Morales, M.K., Abdullah, R.E., and Morales, E.M., 2018,
With the assistance of research and development from the Performance of Mechanically Stabilized Earth Walls
geosynthetic industry, construction in challenging sites Supported on Rammed Aggregate Piers for a Full-Scale
becomes possible. In cases where weak subsurface soils are Trial Embankment, 11ICG Conference, Seoul, So. Korea.
present at the project site, the versatility of these ductile Duncan, JM and Wright, S. 2005. Soil Strength and Slope
structures allow them to be used with cost-effective ground Stability. John Wiley and Sons, Inc., Hoboken, New
improvement measures. Jersey.
5
FHWA, 2009. Design and construction of Mechanically
Stabilized earth walls and reinforced soil slopes – Volume
I. Federal Highway Administration Publication No.
FHWA-NHI-10-243, US Department of Transportation,
Washington, D.C., USA, 332p.
FHWA, March 2001. Mechanically Stabilized Earth Walls
and Reinforced Soil Slopes Design and Construction
Guidelines. Federal Highway Administration Publication
No. FHWA-NHI-00-043, US Department of
Transportation, Washington, D.C., USA.
Morales, Mark. 2018. Lectures and Presentations for MS
Program. Institute of Civil Engineering, University of the
Philippines, Diliman, Quezon City.
MSEW and ReSSA Software copyrighted by © Adama
Engineering Inc.
National Structural Code of the Philippines, 2015 Volume I
– Buildings, Towers and other Vertical Structures.
NCMA, 2009. Design manual for segmental retaining walls,
3rd Edition, National Concrete Masonry Association
(NCMA), Virginia, USA.
Product Presentations of PGA-Earth Structure Solutions, Inc
Rajagopal, Karpurapu, April 2017. Use of Geosynthetics for
construction in soft clays. IGS Educate the Educators
Presentation Seminar, Philippines.
Yoo, Chungsik. April 2017. Advanced Topic on
Geosynthetic-reinforced soil walls. IGS Educate the
Educators Presentation Seminar, Philippines.