Texaco Refinery, Milford Haven Chemical Processing 1994: Timeline of The Accident

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Texaco Refinery, Milford Haven Chemical

Processing 1994
Timeline of the accident
0215: Operators started to introduce raffinate into splitter
1241: Alarm says high pressure at top of tower due to
tower (to distill & separate gasoline components – the tower
compression of gases by rising liquid level - Operators opened
was >100’ tall)
manual valve to vent gases into the relief system (which vented
0309: Hi level alarm actuated & failed to actuate.
unflared gas into atmosphere via a blowdown drum)
0330: Level indication showed 9’ and feed was stopped by
Operators also turned off two burners in furnace (assume this
operators (but level was actually at ~13’) would reduce pressure) & opened valve to allow liquid to go
0500: Lead operator in satellite CR for ISOM unit gives briefing from bottom of tower to storage tanks
to CCR and leaves to go home (early) This hot liquid flowed through a heat exchanger with liquid
0600: New CCR operator arrives (to start his 30th consecutive entering tower, raising temperature of liquid entering tower by
day doing 12 hour shifts) 141 deg F.
0715: Day supervisor arrives (late, so he had missed handover) 1300: Contract workers returned from lunch to temporary
0951: Startup resumed (splitter tower was already over-filled) trailers near blowdown drum
-  Auto level control valve left closed because of ‘conflicting 1314: Hot feed causes boiling and level rise that tower is filled
instructions’ completely and spills into vapour line, causing pressure relief
1000: Furnace lit to start feed heating valves in vapour line to open. 52000 gallons of liquid thereby
1050: Day supervisor leaves site – no supervisor in CCR contrary vents to blowdown drum, where it overflows and drains into a
to rules – single operator now running 3 units including ISOM process sewer, setting off control room alarms. High-level alarm
in blowdown drum failed to actuate. Geyser of liquid and
unit
vapour erupts from vent above blowdown drum. Hot gasoline
1200: Splitter tower level reaches 98’ (15x normal level) but
forms a large vapour cloud, which was ignited by a running
level instrument says 8.4’ and gradually falling. Screen displays
truck engine nearby. Explosion and fire ensued, 15 killed, 180
did not show flow in and out on same screen, nor calculate
injured. Temporary trailers housing contractors were destroyed
total liquid in tower - Maintenance contractors left temporary in blast.
trailers for a lunch

Root Cause Lesson learnt


Inadequately addressed controlling major hazard risk 1) Safety management systems (SMS)
Did not provide adequate resources to prevent major Store, retrieve and review incident information from the
accidents; budget cuts impaired process safety history of similar plants.
performance at the Texas City refinery. 2) Human factors
Hire trained operators, conduct training
3) Plant design
safety critical alarms are distinguishable from other
operational alarms
Action taken 4) Plant modifications
formal, controlled procedure for hazard identification
Replace and repair the damaged plant
and operability analysis for modifications (including
Detailed discussions between HSE and the company
emergency modifications)
Replacement of damaged plant; extensive
5) Inspection systems
programmes
All safety critical parts of the plant should be inspected
Increased inspection frequency
6) Emergency planning
Fire brigades; the availability of adequate water supplies
for fire-fighting and vessel cooling

Mackenzie, C., Holmstrom, D., & Kaszniak, M. (2007). Human Factors Analysis of
References the BP Texas City Refinery Explosion. PsycEXTRA Dataset. doi:
10.1037/e578062012-015

1. Nur Farah Hanim Binti Rosli PA17004


2. Arti Amalin Binti Abd Ghani PA17080
Group 3. Anis Athirah Binti Adnan PA17020

members 4. Nur Alia Farahanin Binti Mohd Tajuddin PA17037


5. Suezetty Binti Sulaiman PA17062
6. Hairi Nazwan Bin Haron PA17033

You might also like