Millennium Erectors Corporation: 9445 Retiro ST., Guadalupe, Makati City

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

Millennium Erectors Corporation

9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 063


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : April 29, 2014
Contract Package Shift : Day
Working Time : from 7:00AM to 4:00PM Weather : Sunny

Daily Construction Report


MANPOWER
Staff NO MH NO MH Equipments NO HRS.
1. Project Manager 1 8 1. Leadman 3 24 1. Cut off machine 1 8
2. QA/QC 2 16 2. Carpenter 2 16 2. Mini Dump Truck 1 8
3. Site Engineer 2 16 3. Mason 4 32 3. Circular Saw 1 8
4. Electrical Engineer 1 8 4. Tile Setter 3 24 4. Service Vehicle 1 8
5. Mechanical Coordinator 1 8 5. Welder 1 8 5. Power Washer 2 16
6. Cost Engineer 0 0 6. Laborer 51 408 6. Grinder 6 48

7. Safety Officer 1 13 Total 64 512 7. Auto level 1 8


8. Project Nurse 0 0 TRADECON 8. Mech.Concrete Vib. 1 8
9. CAD Operator 1 8 KALAYAAN 4 32 9. Hammer Drill & Rotary 10 80

10. Timekeeper 1 10 ICC 18 144 10. Chipping Gun 1 8


11. Foreman 1 8 ROSTRAM 3 24 11. Welding machine 5 40
Total 11 95 S&H 12 96 12. Hand Drill 6 48
ARLO 8 64 13. Cutting Tools 2 16

General Services NO MH YYD 2 16 14. Vacuum Cleaner 2 16


1. Spot Checker 2 26 V. ROQUE 12 96

2. Electrician 1 13 G. S. GO 4 32
3. Electrical Aide 2 26 CARSON 0 0
4. Line and Grade 0 0 CARDRIAN 2 16

5. L&G Helper 1 13 POLYGON 0 0


6. Warehouse Man 1 13 STELSEN 1 8

7. Warehouse Aide 1 13 SCHINDLER 3 24


8. Pump Tender 1 13 Total 69 552
9. Utility 3 39 SUBCON
Total 12 156 FIVE STAR 1 8
CHER 21 168

Operator NO MH FRANCISCAN 0 0
1. Driver 1 13 BIO 101 0 0

Total 1 13 MIGHTY 29 232


FMPI 0 0

Total 189 1512 Prepared by :

NO MH ___________________________

Description of Activities Performed Today: MEC


GRAND TOTAL 277 2288
1. Masonry works @ GF to 32nd floor
2. Painting works Interior @ 31st -32nd floor
3. Installation/Rectification of tiles @ 24th - 32nd floor Received by:

4.Puchlisting @ 9th-32nd floor

5. Ceiling works @ 32nd floor __________________________________


6. Painting works @ common areas DAAA
7. Rectification of Epoxy paint @ stair 1 & Common areas
8. Painting of Main Doors & T/B 31st-32nd
Millennium Erectors Corporation
9445 Retiro St., Guadalupe, Makati City

Project : Oriental Gardens Makati (Lilac Tower) Report No. : 002


Location : Don Chino Roces Ave. corner Export Drive, Makati City Date : August 24, 2011
Contract Package Shift : Night
Working Time : from to Weather :

Daily Construction Report


MANPOWER
Staff NO MH General Services NO MH Operator NO MH
1. Project Manager 1. Time Keeping 1. Driver

2. Superintendent 2. Warehouse 2. Tadano Oprt.


3. Site Engineer 3. Line & Grade 3. Backhoe Optr.

4. Quality Control 4. Electrician 4. Mini Loader Optr


5. Office Engineer 5. Utility 5. Genset Optr.

6. Autocad Operator 6. Leadman 6. Bulldozer Optr.

7. Safety Officer 7. Vibratory Roller Optr.


8. Project Nurse 8. Dumptruck Optr.

Total 0 0 Total 0 0 Total 0 0

Carpenter NO MH Welder NO MH Labor NO MH


1. Curanto 1. 1.

2. Total 2.

3. 3.
4. Steelman NO MH 4.

5. 1.

Total 0 0 Total 0 0 Total 0 0

Grand Total 0 0

Equipments NO HRS. Equipments NO HRS.


1. Backhoe
2. Mini Loader
3. L-300 FB

Description of Activities Performed Today:

Remarks:

Prepared by: Received by:

Jose P. Maaliw
MEC DAAA
\ NO MH
1. 5 87
Total 5 87