Construction Program of Quarters Building, Type 4, MBNR: Days From To 118 Days 18/05/2020 13/09/2020 35 Days

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

Construction program of Quarters building DAYS FROM to

,type 4,MBNR 118 days 18/05/2020 13/09/2020


1 Super Structure-G floor 35 days
2 Barbending & Shuttering for slab 11 days 18/05/2020 28/05/2020
3 Roof beam and slab &curing 18 days 29/05/2020 15/06/2020
Finishing work 34 days
4 Brick work upto Lintel 15 days 16/06/2020 30/06/2020
5 Internal Plaster for Ground floor 6 days 25/06/2020 01/07/2020
6 Waterproofing of terrace floor 2 days 16/06/2020 18/06/2020
7 External plastering 5 days 28/06/2020 02/07/2020
8 plumbing and sanitary 5 days 02/07/2020 06/07/2020
9 Door panel fixing 4 days 07/07/2020 10/07/2020
10 windows fixing 4 days 07/07/2020 10/07/2020
11 Tiling 9 days 11/07/2020 19/07/2020
12 External painting 6 days 30/08/1900 04/09/2020
13 Internalpainting 7 days 05/09/2020 11/09/2020
Super Structure-1st floor
14 column upto slab level 7 days 17/06/2020 22/06/2020
15 Barbending & Shuttering for slab 11 days 23/06/2020 03/07/2020
16 Roof beam and slab &curing 18 days 04/07/2020 21/07/2020
Finishing work
17 Brick work upto Lintel 15 days 22/07/2020 06/08/2020
18 Internal Plaster for 1st floor 6 days 03/08/2020 08/08/2020
19 Waterproofing of terrace floor 2 days 22/07/2020 23/07/2020
20 External plastering 5 days 07/08/2020 11/08/2020
21 plumbing and sanitary 5 days 11/08/2020 15/08/2020
22 Door panel fixing 4 days 16/08/2020 19/08/2020
23 windows fixing 4 days 20/08/2020 23/08/2020
24 Tiling 6 days 24/08/2020 29/08/2020
25 External painting 6 days 30/08/1900 04/09/2020
26 Internalpainting 7 days 05/09/2020 11/09/2020
27 Punch point c;earing 2 days 12/09/2020 13/09/2020
DAYS FROM to
construction program of OHE Building ,MBNR 160 days 5/23/2020 10/30/2020
1 Sub Structure 43 days
a Footing Pit Excavtion (24 pits) 2 days 3/17/2020 3/19/2020
b Pcc for Footing (24 No.s) 6 days 5/23/2020 5/24/2020
c Barbending & Shuttering for footing (12 No.s) 3 days 5/25/2020 5/27/2020
d Rcc for footing (12 No.s) 2 days 5/28/2020 5/29/2020
a Barbending & Shuttering for footing (12 No.s) 3 days 5/30/2020 6/1/2020
b Rcc for footing (12 No.s) 2 days 6/2/2020 6/3/2020
c Column upto plinth level 6 days 6/4/2020 6/10/2020
d Back filling of footing 1 day 6/11/2020 6/11/2020
a substructure masonry 6 days 6/12/2020 6/18/2020
b Barbending & Shuttering for Plinth beam 6 days 6/19/2020 6/25/2020
c Rcc for plinth beam 2 days 6/26/2020 6/27/2020
d Backfilling of plinth 4 days 6/28/2020 7/1/2020
2 Super Structure ground floor 30 days
2.a column upto slab level 6 days 7/2/2020 7/7/2020
2.b Barbending & Shuttering for slab 9 days 7/8/2020 7/16/2020
2.c Roof beam and slab &curing 15 days 7/17/2020 8/1/2020
3 Finishing work 41 days
3.a Brick work upto Lintel 8 days 8/2/2020 8/9/2020
3.b Internal Plaster for Ground floor 5 days 8/10/2020 8/14/2020
3.c Waterproofing of terrace floor 2 days 8/2/2020 8/3/2020
3.d External plastering 5 days 8/15/2020 8/19/2020
3.e plumbing and sanitary 5 days 8/20/2020 8/24/2020
3.f Door panel fixing 4 days 8/25/2020 8/29/2020
3.g windows fixing 4 days 8/30/2020 9/2/2020
3.h Tiling 9 days 9/3/2020 9/11/2020
3.i External painting 6 days 10/19/2020 10/25/2020
3.j Internalpainting 7 days 10/24/2020 10/30/2020
4 Super Structure-1 st floor 30 days
4.a column upto slab level 6 days 8/3/2020 8/8/2020
4.b Barbending & Shuttering for slab 9 days 8/9/2020 8/16/2020
4.c Roof beam and slab &curing 15 days 8/17/2020 9/1/2020
5 Finishing work 56 days
5.a Brick work upto Lintel 8 days 9/2/2020 9/9/2020
5.b Internal Plaster for 1st floor 5 days 9/10/2020 9/14/2020
5.c Waterproofing of terrace floor 2 days 9/2/2020 9/3/2020
5.d External plastering 5 days 9/15/2020 9/19/2020
5.e plumbing and sanitary 5 days 9/20/2020 9/24/2020
5.f Door panel fixing 4 days 9/25/2020 9/29/2020
5.g windows fixing 4 days 9/30/2020 02-010-2020
5.h Tiling 9 days 9/3/2020 10/12/2020
5.i External painting 6 days 10/13/2020 10/18/2020
5.j Internalpainting 7 days 10/19/2020 10/26/2020
6 Structural erection 7 days 9/30/2020 10/5/2020