Generally Accepted Scheduling Principles

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 282

PREADSHEE

GENERALLY ACCEPTED
SCHEDULING PRINCIPLES

Introduction Explains the meaning and use of GASP 1

Valid GASP A table showing the 5 main elements required


2 to validate a schedule, its narrative and essential

Effective GASP A table showing the 3 main elements required


3 to make a schedule effective

PASEG to
GASP
Shows the roadmap/matrix from the Planning
4 and Scheduling Excellence Guide (PASEG) to the
Integrated
Master Describes how to use and manage an Integrated
5 Master Schedule (IMS)
Schedule

IMS Integration Integration of Management tools explained6

IMS
Architecture
Explains the organizational structure of the7 Work Scope

Schedule
Hierarchy
Explains how to satisfy many project stakeholders
8 the program should maintain several levels o
Top down vs.
Bottom up Explains how top down and bottom up planning
9 are used and what they mean
Planning
Schedule
Modeling List schedule modeling techniques and things
10 to promote and things to avoid when using them
Techniques
Level of Effort
(LOE)
Explains the meaning of LOE and things to
11avoid and things to promote when using it

Apportioned
Effort (AE)
Explains the meaning of apportioned effort
12and shows and example

Schedule
Margin
Explains the meanning of schedule margin13to mitigate risk of not meeting contractual milestone

Resource
Loaded Explains the integration of Cost/Schedule 14
to ensure they are link and traceable
Schedules
Non-resource
Loaded Explains how non-resource loaded schedule
15 still can facilitate resource analysis and drive reso
Schedule
Subproject/Exte
rnal Schedule Explains how customer and subcontractors
16 schedules should be integrated with the main sche
Integration
Interface
Handoff Explains the benefits of having interface handoff
17 milestones
Milestones

Schedule
Visibility Tasks
Explains the meaning and alternative methods
18
Horizontal
Traceability
Explains its meaing and its importance 19

Vertical
Traceability
Explains its meaing and its importance 20

Task Coding Essential process to ensure horizontal and


21vertical traceability explained
Baseline
Change Explains the importance of having a structured
22 approach to changes in the baseline of the proje
Management
Rolling Wave
Planning
Rolling wave planning procedure explained
23

Schedule
Performance Graphic depicting schedule performance reporting
24
Reporting

Schedule
Penetration
Graphic depicting the need for increase schedule
25 penetration according to the associated risk

Lag use 1 Advises on lag use and alternatives 26

Lag use 2 Advises on lag use and alternatives 27

Desirable
Programmatic
Checklist for desirable programmatic conditions
28 and the accompanying behaviors
Undesirable
Programmatic
Checklist for undesirable programmatic conditions
29 and the accompanying behaviors

IMS Analysis IMS metrics and their management value checklist


30

Acceleration
Techniques
Acceleration techniques checklist 31

Schedule
Health Schedule health checklist 32
Checklist

Schedule
Health Sample
Schedule health Sample 33

Schedule
Margin How to do it through the Project Life Cycle34
Assessment
Risk &
Opportunity Checklist of Risk and Opportunities at different
35 project stages
Processes

Critical Path
Length Index
Critical Path Length Index explanation 36

Critical Path
Length Index Critical Path Length Index Sample 37
Sample

Baseline
Execution Index BEI explanation 38
Current
Execution Index
CEI explanation 39

Schedule Rate
Chart
SRC explanation, things to promote and things
40 to avoid

Duration Based
vs. Scope
Based %
Duration based vs. Scope based Percentage
41 Complete
complete
Business
Rhythm 1
Business Rhythm for the analysis, status and
42 maintenace of the IMS

Business
Rhythm 2
Calendar of Business Rhythm 43

Business
Rhythm 3 Weekly Calendar 44
Schedule
Review Schedule Review Checklist 45
Checklist
Vertical
Horizontal Sample vertical horizontal integration 46
Integration

Earned Value
Analysis (EVA) EVA Chart 47
Roles &
Responsibilities
of Program
Describes the roles and responsibilities of48
Program Personnel
Personnel

Task Naming
Convention
Recommendation on Task Naming Convention
49

Planner/Schedu
ler Skills & Recommends the skills needed by a Planner/scheduler
50
Training

Scheduling in
the Production Scheduling in the Production Environment51Explained
Environment
O TO THIS SP
TO GO
TO THIS
SPREAD
SHEET
Introduction!A1

Valid GASP'!A1

Effective GASP'!A1

PASEG TO GASP!A1

IMS!A1

IMS Graphic'!A1

IMS Architecture'!A1

Schedule Hierarchy'!A1
Top down vs Bottom up'!A1

Schedule Modeling Techniques'!A1

Level of Effort'!A1

Apportioned Effort'!A1

Schedule Margin'!A1

Resource Loaded Schedules'!A1

Non-resource loaded Schedule'!A1

Subproject-External Sch. Integr'!Print_Area

Interface Handoff Milestones'!A1

Schedule Visibility Tasks'!A1


Horizontal Traceability'!A1

Vertical Traceability'!A1

Task Coding'!A1

Baseline Change Mgmt'!A1

Rolling Wave Planning'!A1

Schedule Performance Reporting'!A1

Schedule Penetration'!A1

Lag Use 1'!A1

Lag Use 2'!A1

Desirable Programatic'!A1
Undesirable Programmatic'!A1

IMS Analysis'!A1

Acceleration Techniques'!A1

Schedule Health Checklist'!A1

Schedule Health Sample'!A1

Schedule Margin Assessment'!A1

Risk & Opportunity'!A1

Critical Path Length Index'!A1

CPLI Sample'!A1

Baseline Execution Index'!A1


Current Execution Index'!A1

Schedule Rate Chart'!A1

Dur based vs Scope based % comp'!A1

Business Rhythm 1'!A1

Business Rhythm 2'!A1

Business Rhythm 3'!A1

Schedule Review Checklist'!A1

Vertical Horizontal Integration'!A1

EVAl'!A1
Roles & Responsibilities of PP'!A1

Task Naming Convention'!A1

Planner Scheduler Skills & T'!A1

Scheduling in Production '!A1


TO GO
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN M

Info!A1
TO GET BACK TO MAIN MENU:
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
Issues Log
TO GET BACK TO MAIN MENU:

Info!A1
Action Items
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
Work Breakdown Structure
TO GET BACK TO MAIN MENU:

Info!A1
Roster
TO GET BACK TO MAIN MENU:

Info!A1
Roles and Responsibilities
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
Resource Commitment Matrix
TO GET BACK TO MAIN MENU:

Info!A1
Assumptions and Constraints
TO GET BACK TO MAIN MENU:

Info!A1
Decision Log
TO GET BACK TO MAIN MENU:

Info!A1
Communication Plan
TO GET BACK TO MAIN MENU:

Info!A1
Stakeholder Analysis
TO GET BACK TO MAIN MENU:

Info!A1
Expectations
TO GET BACK TO MAIN MENU:

Info!A1
Change Control Log
TO GET BACK TO MAIN MENU:

Info!A1
Deliverable Acceptance Log
TO GET BACK TO MAIN MENU:

Info!A1
PERT Analysis
TO GET BACK TO MAIN MENU:

Info!A1
Delphi Exercise
TO GET BACK TO MAIN MENU:

Info!A1
Timesheet Totals
TO GET BACK TO MAIN MENU:

Info!A1

The more risk, more penetration needed


Timesheet
TO GET BACK TO MAIN MENU:

Info!A1
Initial Project Size Estimate
TO GET BACK TO MAIN MENU:

Info!A1
Resource Loading
TO GET BACK TO MAIN MENU:

Info!A1
Project Quality Metrics
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
ACK TO MAIN MENU:
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
ACK TO MAIN MENU:
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO MAIN MENU:
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:

Info!A1
TO GET BACK TO MAIN MENU:
TO GET BACK TO MAIN MENU:

Info!A1

You might also like