ATCT Tower Structure Master Schedule 2020/5/4

标 Task Name Duration Start Finish 前置任务 2020 2021


识 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11

0 ATCT Tower Structure Master Schedule 293 days 2020/5/1 2021/3/9 ATCT Tower Structure Master Sch

1 1 Preliminary 80 days 2020/5/1 2020/7/20 Preliminary

2 1.1 Site Set Up 30 days 2020/5/1 2020/5/30 Site Set Up

3 1.2 Temporary Road 15 days 2020/6/1 2020/6/15 Temporary Road

4 1.3 Climbing Formwork System 60 days 2020/5/21 2020/7/20 23SF Climbing Formwork System

5 1.4 Tower Crane 45 days 2020/6/5 2020/7/20 23SF Tower Crane

6 2 Design 44 days 2020/5/7 2020/6/19 Design

7 2.1 Piling 7 days 2020/5/7 2020/5/13 Piling

8 2.1.1 Received Approved 60% Design 1 day 2020/5/7 2020/5/7 Received Approved 60% Design

9 2.1.2 Construction Design 3 days 2020/5/8 2020/5/10 8 Construction Design

10 2.1.3 Approval of Construction Design 3 days 2020/5/11 2020/5/13 9 Approval of Construction Design

11 2.2 Structure (Schedule for Pile Cap) 31 days 2020/5/20 2020/6/19 Structure (Schedule for Pile Cap)

12 2.2.1 Received Approved 60% Design 1 day 2020/5/20 2020/5/20 Received Approved 60% Design

13 2.2.2 Construction Design 15 days 2020/5/21 2020/6/4 12 Construction Design

14 2.2.3 Approval of Construction Design 10 days 2020/6/5 2020/6/14 13 Approval of Construction Design

15 2.2.4 Shop Drawing 5 days 2020/6/15 2020/6/19 14 Shop Drawing

16 3 Pilling Work 22 days 2020/5/14 2020/6/4 Pilling Work

17 3.1 Piling Construction 19 days 2020/5/14 2020/6/1 10 Piling Construction

18 3.2 Post Testing 3 days 2020/6/2 2020/6/4 17 Post Testing

19 4 Tower Structure 258 days 2020/6/5 2021/3/9 16 Tower Structure

20 4.1 Excavation and Cutting Pile 15 days 2020/6/5 2020/6/19 18 Excavation and Cutting Pile

21 4.2 Pile Cap 15 days 2020/6/20 2020/7/4 15 Pile Cap

22 4.3 B1 (h=4.6m) 15 days 2020/7/5 2020/7/19 21 B1 (h=4.6m)

23 4.4 GF (h=7.8m) 20 days 2020/7/20 2020/8/8 22 GF (h=7.8m)

24 4.5 2F (h=5.8m) 10 days 2020/8/9 2020/8/18 23 2F (h=5.8m)

25 4.6 3F (h=4.55m) 7 days 2020/8/19 2020/8/25 24 3F (h=4.55m)

26 4.7 4F (h=8.0m) 12 days 2020/8/26 2020/9/6 25 4F (h=8.0m)

27 4.8 5F (h=8.0m) 12 days 2020/9/7 2020/9/18 26 5F (h=8.0m)

28 4.9 6F (h=8.0m) 12 days 2020/9/19 2020/10/5 27 6F (h=8.0m)

29 4.10 7F (h=8.0m) 12 days 2020/10/6 2020/10/17 28 7F (h=8.0m)

30 4.11 8F (h=8.0m) 12 days 2020/10/18 2020/10/29 29 8F (h=8.0m)

31 4.12 9F (h=8.0m) 12 days 2020/10/30 2020/11/15 30 9F (h=8.0m)

32 4.13 10F (h=8.0m) 29 days 2020/11/16 2020/12/14 10F (h=8.0m)

33 4.13.1 Core Work 12 days 2020/11/16 2020/11/27 31 Core Work

34 4.13.2 Platform Work 10 days 2020/12/5 2020/12/14 33FS+7 days Platform Work

35 4.14 11F (h=8.0m) 29 days 2020/12/15 2021/1/12 32 11F (h=8.0m)

36 4.14.1 Core Work 12 days 2020/12/15 2020/12/26 33 Core Work

37 4.14.2 Platform Work 10 days 2021/1/3 2021/1/12 36FS+7 days Platform Work

38 4.15 12F (h=4.2m) 23 days 2020/12/27 2021/1/18 12F (h=4.2m)

39 4.15.1 Core Work 6 days 2020/12/27 2021/1/1 36 Core Work

40 4.15.2 Platform Work 10 days 2021/1/9 2021/1/18 39FS+7 days Platform Work

41 4.16 13F (h=4.2m) 23 days 2021/1/2 2021/1/24 13F (h=4.2m)

42 4.16.1 Core Work 6 days 2021/1/2 2021/1/7 39 Core Work

43 4.16.2 Platform Work 10 days 2021/1/15 2021/1/24 42FS+7 days Platform Work

44 4.17 14F (h=4.2m) 23 days 2021/1/8 2021/1/30 14F (h=4.2m)

45 4.17.1 Core Work 6 days 2021/1/8 2021/1/13 42 Core Work

46 4.17.2 Platform Work 10 days 2021/1/21 2021/1/30 45FS+7 days Platform Work

47 4.18 15F (h=4.45m) 23 days 2021/1/14 2021/2/5 15F (h=4.45m)

48 4.18.1 Core Work 6 days 2021/1/14 2021/1/19 45 Core Work

49 4.18.2 Platform Work 10 days 2021/1/27 2021/2/5 48FS+7 days Platform Work

50 4.19 15.5F (h=2.25m) 7 days 2021/2/6 2021/2/22 49 15.5F (h=2.25m)

51 4.20 16F (h=6.7m) 15 days 2021/2/23 2021/3/9 50 16F (h=6.7m)

Prepared by: 关键拆分 Milestone 关键


Checked by:
Task Summary
Approved by:

Cana Sino Construction Corporation 1 /1