Brief Introduction To Earned Value Management (EVM)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 43

Brief Introduction to

Earned Value Management (EVM)

12/25/06 EVM Introduction 1

12/25/06 EVM Introduction 1


Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

12/25/06 EVM Introduction 2

12/25/06 EVM Introduction 2


The Problem

• A successful program manager says: “We completed the project


we promised to deliver in the time we promised and with the
budget we asked for.”
• The standard source of information about the status of the
project is the status of the budget, which only tells you how
quickly and how completely you are spending the money you
have.
• What you really want to track is how quickly and how
completely you are accomplishing the work you promised to do.
• The coupling of money spent to work done
(under) Budget
Variance

or schedule consumed is loose and nonlinear.


• Also, the expenditure track is a (behind) (ahead)

one-dimensional projection of a Schedule


Variance
two-dimensional problem.
12/25/06 EVM Introduction 3
(over)
12/25/06 EVM Introduction 3
Why You Need to Know Both
Cost and Schedule Variances

• Project A is in good shape, under budget and ahead of schedule.


• Project B is over budget, but if we realize (under) Budget
Variance
it is ahead of schedule, we can
slow the effort to save money. D
A
• Project D’s cost variance looks
better than A’s, but if we (behind) (ahead)
realize it is behind schedule, Schedule
Variance
we can spend more to catch up.
• Project C looks just like B if we C B
only look at the cost variance, but
we can’t slow down to save money. (over)
And it looks just like D if we only look at
schedule, but we can’t spend more to catch up. It’s time to rescope!
12/25/06 EVM Introduction 4

12/25/06 EVM Introduction 4


So What Do We Have to Work With?

1. DEFINE THE WORK AND ORGANIZE TEAMS


CONTRACT BUDGET BASE

MANAGEMENT RESERVE (MR)

2. SCHEDULE THE WORK

NE
LI
SE
BA
Each chunk of work
3. ALLOCATE BUDGETS corresponds to a
chunk of budget and
100
a chunk of schedule.
40
60
15
25
30
TIME
30
12/25/06 EVM Introduction 5

12/25/06 EVM Introduction 5


The Basic Idea

• For each chunk of work, define its ‘value’ as the budget


assigned to it.
• When you complete that chunk of work, you have ‘earned’ its
value.
• The total earned value to date gives you a point on the ($,time)
graph – the Budgeted Cost of Work Performed (BCWP).
• You could compare this to the actual amount of work that you
were supposed to have completed by this point in the schedule,
as measured by its budgeted cost – the Budgeted Cost of Work
Scheduled (BCWS), another point on the ($,time) graph.
• You could also compare it to the actual amount spent to
complete the chunks of work done to date – the Actual Cost of
Work Performed (ACWP), a third point on the ($,time) graph.
• Look at what information these comparisons give about the
status of the project.
12/25/06 EVM Introduction 6

12/25/06 EVM Introduction 6


Budgeted Cost of Work Scheduled
(BCWS)

Total Budget = $5,000


to be spent over 5 months
We plan to deploy 1 stand
each month at an estimated
cost of $1,000.
Month 1 Month 2 Month 3 BCWS each month = $1,000
BCWS = $1,000 BCWS = $1,000 BCWS = $1,000

Month 4 Month 5
BCWS = $1,000 BCWS = $1,000

Each
Eachdollar
dollarof
ofBCWS
BCWSrepresents
representsaaspecific
specificdollar
dollarof
ofwork
work
scope.
scope.BCWS
BCWSis isaggregated
aggregatedand
andsummed
summedas asthe
theperformance
performance
measurement
measurementbaseline.
baseline.
12/25/06 EVM Introduction 7

12/25/06 EVM Introduction 7


Budgeted Cost of Work Performed
(BCWP)

We’re at the end of the


second month, but only
1 stand is complete.
Value of work performed
= $1,000

You
Youearn
earnvalue
valuethe
thesame
sameway
way
as
asititwas
wasbudgeted
budgetedin inthe
thebaseline.
baseline.

12/25/06 EVM Introduction 8

12/25/06 EVM Introduction 8


Schedule Variance
(SV)

BC WS Of the work we scheduled to have done,


BUDGET BASED

how much did we budget for it to cost?

BC WP Of the work we actually performed,


how much did we budget for it to cost?

SCHEDULE
SCHEDULEVARIANCE
VARIANCEisisthe
thedifference
differencebetween
betweenwork
workscheduled
scheduled
and
andwork
workperformed
performed(expressed
(expressedininterms
termsof
ofbudget
budgetdollars)
dollars)

formula:
formula: SV
SV$$==BCWP
BCWP--BCWS
BCWS
example:
example: SV
SV==BCWP
BCWP--BCWS
BCWS==$1,000
$1,000--$2,000
$2,000
SV= -$1,000
SV= -$1,000 (negative
(negative==behind
behindschedule)
schedule)

12/25/06 EVM Introduction 9

12/25/06 EVM Introduction 9


Schedule Variance
(SV)

5,000

BCWS
“the baseline”
sv
$
BCWP
“earned value”

TIME 5 months

12/25/06 EVM Introduction 10

12/25/06 EVM Introduction 10


Actual Cost of Work Performed
(ACWP)

Labor came to $1,300,


and materials cost
$1,100. That first stand
cost $2,400!

actual
actualexpenditures
expendituresvs.
vs.budget
budget

12/25/06 EVM Introduction 11

12/25/06 EVM Introduction 11


Cost Variance
(CV)

PERFORMANCE BASED
BC WP
Of the work we actually performed,
how much did we budget for it to cost?

AC WP Of the work we actually performed,


how much did it actually cost?

COST
COSTVARIANCE
VARIANCEisisthe
thedifference
differencebetween
betweenbudgeted
budgetedcost
cost
and
andactual
actualcost
cost

formula:
formula: CV
CV$$==BCWP
BCWP--ACWP
ACWP
example:
example: CV
CV==BCWP
BCWP--ACWP
ACWP==$1,000
$1,000--$2,400
$2,400
CV= -$1,400
CV= -$1,400 (negative
(negative==cost
costoverrun)
overrun)

12/25/06 EVM Introduction 12

12/25/06 EVM Introduction 12


Cost Variance
(CV)

5,000

ACWP
“actual cost”
cv

$ BCWP
“earned value”

TIME 5 months

12/25/06 EVM Introduction 13

12/25/06 EVM Introduction 13


Note That We Can Isolate
Schedule and Cost Variances

5,000

BCWS

ACWP
cv
$ sv

BCWP

TIME 5 months

schedule variance = BCWP - BCWS = negative number behind


behindschedule,
schedule,
cost variance = BCWP - ACWP = negative number over
overcost
cost
12/25/06 EVM Introduction 14

12/25/06 EVM Introduction 14


Where are the significant problems?

sorted by CV ($)
By tracking and sorting on variances, we
can isolate the troublesome WBS
elements. WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC
1 3600 PCC Zepka 28.99 34.09 0.850 ↑ -296.2 -17.62 ↔ -187.2
2 3200 COMMUNICATIONS Tideman 34.63 41.03 0.844 ↓ -130.8 -18.49 ↔ -87.0
3 G&A GEN & ADMIN 33.67 36.11 0.932 ↓ -45.2 -7.26 ↔ -36.8
4 2200 SYS ENGINEERING Price 85.04 94.35 0.901 ↓ -26.4 -10.95 ↔ 0.0
5 3800 I&A Troop 35.40 37.08 0.955 ↓ -24.2 -4.75 ↔ -24.8
6 2100 PROJ MANAGEMENT Brown 45.70 48.51 0.942 ↔ -17.4 -6.16 ↔ -3.2
7 2300 FUNC INTEGRA Price 71.62 75.23 0.952 ↓ -17.4 -5.03 ↔ -30.8
8 5200 MANAGEMENT DATA Simmons 84.18 98.10 0.858 ↓ -13.2 -16.54 ↑ -16.0
9 3100 SENSORS Smith 20.87 21.49 0.971 ↓ -10.6 -2.94 ↔ -21.6
10 4000 SPARES Blair 17.87 18.90 0.945 ↑ -7.8 -5.78 ↔ -6.2
11 6200 SYSTEM TEST Hall 60.82 61.66 0.986 ↑ -5.6 -1.38 ↔ -2.0
12 5100 ENG DATA Novak 38.51 52.80 0.729 ↓ -4.6 -37.10 ↔ 0.0
13 MR MGT RESERVE 0.00 0.00 0.0 ↔ 439.2
14 UB UNDIST BUDGET 0.0 0.0
15 COM COST OF MONEY 0.0 0.0
16 3700 DATA DISPLAY Troop 41.13 41.13 1.000 ↔ 0.0 0.00 ↔ 0.0
17 OV OVERHEAD 0.0 0.0
18 6100 TEST FACILITIES Smart 100.00 98.02 1.020 ↔ 2.0 1.98 ↔ 0.0
19 3500 COMP PROGRAMS Pino 46.46 44.66 1.040 ↓ 3.4 3.87 ↔ -1.4
20 6300 PCC TEST Bond 23.13 22.64 1.021 ↓ 4.2 2.10 ↔ 0.0
21 3400 ADPE Zepka 41.89 39.79 1.053 ↓ 12.6 5.02 ↔ 4.6
22 3300 AUX EQUIP Tideman 27.57 24.33 1.133 ↓ 78.2 11.73 ↓ 8.4

12/25/06 EVM Introduction 15

12/25/06 EVM Introduction 15


Performance Indices

We can also get a sense of the overall performance


of the project by tracking performance indices.

COST
COSTPERF
PERFINDEX
INDEX(CPI)
(CPI) == BCWP
BCWP
1.2 ACWP
ACWP
“GOOD”

SCHED
SCHEDPERF
PERFINDEX
INDEX(SPI)
(SPI)== BCWP
BCWP
1.1 BCWS
BCWS

TIME
1.0
CPI

.9
“BAD”

SPI
.8

12/25/06 EVM Introduction 16

12/25/06 EVM Introduction 16


Budget at Completion
(BAC)
The most important markers of the overall
performance of the project look at
predictions of the variances at the end.
These require several quantities, the first sum of all BCWS = BAC
being the Budget at Completion. $5,000
$5,000

$
$
$ $

$
$
$
time

When
Whenall
allwork
workhas
hasbeen
beenphased,
phased,the
thecumulative
cumulativeBCWS
BCWS==BACBAC
e.g.,
e.g., $5,000
$5,000==$5,000
$5,000
12/25/06 EVM Introduction 17

12/25/06 EVM Introduction 17


What will be the final cost?

• Estimate at Completion (EAC)


– defined as actual cost to date + estimated cost of work remaining
– usually develop comprehensive EAC at least annually
• reported by WBS in cost performance report
– should examine on monthly basis
– consider the following in EAC generation:
• performance to date
• impact of approved corrective action plans
• known/anticipated downstream problems
• best estimate of the cost to complete remaining work
– also called latest revised estimate (LRE), indicated final cost, etc.

ACWP + ETC = EAC

12/25/06 EVM Introduction 18

12/25/06 EVM Introduction 18


Getting the Estimate at Completion

Just a few little glitches….


We should be able to do
the complete job….ack…

let’s see, for about $7,500

12/25/06 EVM Introduction 19

12/25/06 EVM Introduction 19


Determining EAC via Statistics

• Common EAC Formulae:

EAC = BAC/CPI

= ACWPcum + Budgeted Cost of Work Remaining


CPI3

= ACWPcum + Budgeted Cost of Work Remaining


.8(CPI) +.2(SPI)

= ACWPcum + Budgeted Cost of Work Remaining


CPI * SPI

12/25/06 EVM Introduction 20

12/25/06 EVM Introduction 20


Other methods of EAC calculation

• “Grass Roots” or formal EAC

– detailed build-up from the lowest level detail


– hours, rates, bill of material, etc.

• Average of statistical formulae

• Show range of EACs (optimistic, most probable,


pessimistic)

• Complete schedule risk analysis for remaining work,


estimate work remaining

12/25/06 EVM Introduction 21

12/25/06 EVM Introduction 21


Variance at Completion
(VAC)

B AC what the total job is supposed


to cost

what the total job is expected


E AC to cost

VARIANCE
VARIANCEAT
ATCOMPLETION
COMPLETIONisisthe
thedifference
differencebetween
betweenwhat
whatthe
thetotal
total
job
jobisissupposed
supposedto
tocost
costand
andwhat
whatthe
thetotal
totaljob
jobisisnow
nowexpected
expectedto
tocost.
cost.
FORMULA:
FORMULA: VAC
VAC==BAC
BAC--EAC
EAC
Example:
Example: VAC
VAC==$5,000
$5,000--$7,500
$7,500
VAC
VAC==--$2,500
$2,500 (negative
(negative==overrun)
overrun)

12/25/06 EVM Introduction 22

12/25/06 EVM Introduction 22


Variance at Completion
(VAC)

VAC = Budget at Completion - Estimate at Completion


= BAC - EAC
EAC
VAC

BAC

TIME

12/25/06 EVM Introduction 23

12/25/06 EVM Introduction 23


VAC is Particularly Important
for Government Contracts

• Variance at Completion vs. Contractor Loss


– Positive VAC:
• EAC < BAC underrun contractor gain
– Negative VAC:
• EAC > BAC share area contractor partial loss
• EAC > ceiling overrun contractor loss (100%)

• Government develops top level EAC for comparison


– Government will limit progress payments if EAC is greater than
ceiling
– Government needs forecast of fund requirements

• May still have time to change the final outcome

12/25/06 EVM Introduction 24

12/25/06 EVM Introduction 24


Probably the Biggest
Selling Point for EVM

• A survey of over 800 military programs showed that no program


ever improved performance better than the following EAC
calculation:

EAC = BAC/CPI,

at the 15%-complete point in the program.


• Thus, there is strong empirical evidence that EVM translates early
information into essential guidance for program re-baselining.

12/25/06 EVM Introduction 25

12/25/06 EVM Introduction 25


EVM Analyses

There are a wide variety of indicators to play with in EVM.

Term Symbol Formula Checklist Actions


% Done BCWP Ratio of work accomplished in terms of the total amount of work to do.
Percent Complete
BAC

BCWP Ratio of work accomplished against money spent (an efficiency rating: Work
Cost Performance Index CPI or PF
or Performance Factor ACWP Done for Resources Expended)

To Complete BAC - BCWP Ratio of work remaining against money remaining (Efficiency which must be
Performance Index TCPI or VF achieved to complete the remaining work with the expected remaining money)
EAC - ACWP
or Verification Factor

SPI BCWP Ratio of work accomplished against what should have been done (Efficiency
Schedule Performance Index
BCWS Rating: Work done as compared to what should have been done)

Ratio of Schedule Variance (SV) in terms of average amount of work


Schedule Correlation SC or S/C PCUM accomplished (in weeks or months). It indicates a correlation to program true
SV schedule condition
1) BAC Calculation of a projected Estimate At Completion to compare with the CAM's
PF Estimate At Completion:
Independent Estimate IEAC
2) 1) Ration of total work to be done against experienced cost efficiency
At Completion BAC - BCWP 2) Sunk costs added to a ratio of remaining work against weighted cost and
ACWP +
.8CPI + .2SPI schedule efficiencies

BCWPcum
Average Performance PCUM Duration (wks or mos) Average rate at which work has been accomplished since work began
Since ACWP Began

BCWPcum
Duration (wks or mos)
Average Expected Average rate at which work must be accomplished in the future to finish on the
P TO GO From Time Now to
Performance To Finish date the CAM has forecasted for completion of the work.
Manager's Stated
Completion Date

12/25/06 EVM Introduction 26

12/25/06 EVM Introduction 26


EVM Analyses

There are a wide variety of analytic techniques to play with in EVM.

• Sort on significant variances


– eliminate almost complete, just starting, etc.
• Graph and analyze trends
• Look at comparative data
– e.g. cumulative performance vs. projected performance
• Examine written analysis by contractor
– does it answer why?
– adequacy of corrective action plans
• Analysis of schedule trends, critical path
• Analysis of EAC realism
what
whatare
arethe
thedrivers?
drivers?
what
whatcan
canwewedo
doabout
aboutthem?
them?
12/25/06 EVM Introduction 27

12/25/06 EVM Introduction 27


Graphical EVM Analyses

MEGA HERZ ELEC & VEN Cost/Schedule Variance


F04695-86-C-0050 MOH-2 RDPR FPI POP: 01 MAR 1992 - 15 SEP 1993
1992 1993
Percent of Dollars

MAY JUN JUL AUG SEP OCT NOV DEC JAN


30.0

20.0
Overall cost and schedule trend
10.0
0%
0.0
-6%
-7% -11%
-10.0

-20.0

-30.0

BCWS 0.3 0.6 1.0 1.4 2.2


Dollars In Millions
2.5 4.2 5.6 7.3
At Completion
KTR
20.8
PO
20.8
EAC realism
BCWP 0.2 0.5 0.9 1.4 2.2 2.7 3.8 5.3 6.9 20.8 20.8
ACWP 0.2 0.5 0.9 1.5 2.2 3.0 4.2 5.6 7.3 20.8 23.0
CV 0.0 -0.0 -0.0 -0.1 0.0 -0.3 -0.5 -0.3 -0.5 0.0 -2.2 MEGA HERZ ELEC & VEN F04695-86-C-0050 RDPR FPI
SV -0.1 -0.1 -0.1 -0.0 -0.0 0.2 -0.4 -0.3 -0.4 Element: 3600 Estimates at Completion Name: PCC
Cost Drivers, Cause 1992 1993

Dollars In Millions
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN
8.0

PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0
COST VARIANCE CURRENT FUNDING: 10.0 AS OF: JAN 93
SCHEDULE VARIANCE PO EPC: 24.0 OPR: MR B. TECH
PROJ FUNDING: 23.0 PROGRAM: Mohawk Vehicle

7.0

graphs
graphsshow
showoverall
overalltrend...
trend...
6.0

are
areyou
yougetting
gettingbetter,
better,
or
orworse?
worse? 5.0
BAC 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.5 5.5 5.8
LRE 5.4 5.4 5.4 5.4 5.5 5.5 5.5 5.7 5.7 6.0
CUM CPI 5.1 5.7 5.9 6.0 6.3 5.8 6.5 7.6 6.8 6.8

12/25/06 EVM Introduction 28

12/25/06 EVM Introduction 28


Example: Using Performance Efficiencies (1)

Will the contractor come in on budget?

COST PERFORMANCE INDEX:

CPI = cost efficiency for work performed to date


(The value of work accomplished for each dollar spent)
WORK
BCWP ACCOMPLISHED $1000
= ACWP = ACTUALS = $2400 = .42

HISTORY
Compare the CPI to the TCPI-BAC:
TCPI(BAC) = Efficiency necessary to complete on budget FUTURE
WORK
= BAC-BCWP = REMAINING = $5000 - $1000 = $4000
BAC-ACWP $2600 = 1.54
BUDGET $5000 - $2400
REMAINING

12/25/06 EVM Introduction 29

12/25/06 EVM Introduction 29


Example: Using Performance Efficiencies (2)

SCHEDULE PERFORMANCE INDEX:

SPI = schedule efficiency with which work has been accomplished


(The rate at which work is being accomplished)

WORK
= BCWP = ACCOMPLISHED = $1000 = .50
BCWS WORK $2000
SCHEDULED

12/25/06 EVM Introduction 30

12/25/06 EVM Introduction 30


Example: Using Performance Efficiencies (3)

IS THE CONTRACTOR'S EAC (LRE) REASONABLE?


Compare the CPI to the TCPI-LRE

TCPI(LRE) = Efficiency necessary to complete at the contractor’s estimate

WORK
= BAC-BCWP = REMAINING = $5000 - $1000 = $4000 = 1.00
LRE-ACWP ESTIMATE $6400 - $2400 $4000
REMAINING
reasonable?

Cumulative performance to date (CPI) = .42

Contractor has been performing at 42% efficiency, but expects to


complete remaining work at 100% efficiency!

12/25/06 EVM Introduction 31

12/25/06 EVM Introduction 31


Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

12/25/06 EVM Introduction 32

12/25/06 EVM Introduction 32


Getting at the Value

SOFTWARE
INTEGRATION
PROGRAM
SELECTED
PSWBS
ELEMENTS Product Master
Development Planning

SELECTED Ada Software Standards


Products Tools
REPORTING
ELEMENTS

Ada Ada Ada


Study Conversion Approach
CWBS
EXTENSION
FUNCTIONAL CPCI #1 CPCI #2 CPCI #3
MOS MOLE MAC
ORGANIZATION

Control Control Control


Control Account W
B
Marketing Ada
Account
S
Applications Account Account

D
A
T
Software
A
Secure Control
VP/GM Engineering Engineering Systems Account
S
U
Work M
Packages M
A
Operations
Hardware LAN Control Control BCWS R
Engineering Applications Account Account BCWP I
ACWP Z
BAC Planning A

Responsibility Matrix
EAC Packages T
I
O
N
OBS DATA SUMMARIZATION

12/25/06 EVM Introduction 33

12/25/06 EVM Introduction 33


Control Account Elements

Work Packages Planning Packages


Detailed, short-span tasks, or Future work that has not been
material items, required to detail planned as work packages.
accomplish the CA objectives, They are always scheduled to
typically in the near term occur in the future.

Task 1 Work Packages


Work Packages Task 2 have budgets
and schedules.
Task 3
Task 4
Planning Packages
Task 5

12/25/06 EVM Introduction 34

12/25/06 EVM Introduction 34


Work Packages

• Development of Control Account Plans


– MAY break down the control account budget into smaller work
packages CONTROL ACCOUNT PLAN
$ $ $

• Work Package
Work Pkg #1
$ $ $
Work Pkg #2
• subset of control account $ $ $
Work Pkg #3
• reasonably short in duration
• single element of cost (e.g., labor)
• single technique for earning value
• consistent with detail schedules
• has same characteristics as control account
– scope of work
– milestone completion criteria
– single performing organization
– start and end dates
12/25/06 EVM Introduction 35

12/25/06 EVM Introduction 35


Work Package Characteristics

• Work packages are discrete and measurable.

• Work packages yield products or accomplishments, such as


– design drawing package
– conduct design review
– install stand

• Often done in rolling wave


– detailed plans made for near term work packages
– planning packages are for future work and are not detailed
– CAMs periodically plan another increment of work packages

12/25/06 EVM Introduction 36

12/25/06 EVM Introduction 36


Ways of Earning Value

• Should be a quantitative and discrete way to measure the work


– Discrete
• physical, tangible end product
– Apportioned
• discrete, dependent on another discrete work package
• example: quality assurance
• planned as historical estimating factor (e.g., 7%)
– Level of Effort
• no tangible end product
• basis of measurement: time
• when clock starts ticking, you automatically accumulate earned value
• no schedule variance
• example: management personnel
• May tie in with success criteria or technical measure
• e.g., successful completion of a specific test, reliability growth curve

12/25/06 EVM Introduction 37

12/25/06 EVM Introduction 37


Methods for Assigning Earned Value

Method How Value is Earned

0/100 no EV at opening, 100% EV at close of WP

50/50 50% EV at opening, 50% EV at close of WP

Units Completed same budget value for identical units

Equivalent Units planned unit standards, allows partial credit

Weighted Milestone each milestone weighted based on planned


resources
ideal to have a milestone each month

Percent Complete subjective (least desirable)

12/25/06 EVM Introduction 38

12/25/06 EVM Introduction 38


Suggested for LWA

• 0/50/100 measurement
• Typical work package length is 80 hours.
• Work package status is reported at status meetings, held every
two weeks.
– May just be that 50% of work packages are reported at weekly
status meetings.
• EV is 0% (of budget for work package) if it has not yet been
started, or is only now starting.
• EV is 50% if work is underway.
• EV is 100% if work is complete.
• If work package is at 50% two status meetings in a row, it is
flagged as a potential issue.
• Avoids subjectivity of “% done”; compromises on granularity of
tracking, frequency of reporting
• Puts the onus on doing the WPs right, up front.
12/25/06 EVM Introduction 39

12/25/06 EVM Introduction 39


Outline

• Introduction to the basic rationale and elements of EVM

• Issues of actually implementing an EVM tracking scheme

• Background materials

12/25/06 EVM Introduction 40

12/25/06 EVM Introduction 40


A Spectrum of Implementation

Commercial or Defense Major


Government Defense
Small
Where Companies Larger Companies Organic Contractors

Foreign
Countries

DoD Non-Major DoD Major


corporate
Contracts Contracts
When as desired policy,
“enterprise
FFP (>12 months)
contracts? >$70M RDT&E
wide” <$6M* >$6M
>$300M Prod

streamlined, tailored to CPR


Reports no paper? needs C/SSR

ANSI/EIA-748-1998
Core EV Principles Tailored Applications (32 criteria)
*with judgment

12/25/06 EVM Introduction 41

12/25/06 EVM Introduction 41


Earned Value Management:
History

• 1959 PERT and PERT/Cost


— Milestone Charts And Rate-of-Expenditure • 1985 NASA Johnson Space Flight Center—PMS
Curves • 1987 DOD—Revised DOD C/SCSC JIG
— Dollars Spent Vs Estimates Of Percent • 1988 NASA Marshall SFC—Revised PMS
Complete (DD 1097) (MMI 8020.7C, 44 Criteria)
• 1963 Earned Value Concept (MINUTEMAN) • 1989 Australian DOD—DODI 7000.2
• 1964 Cost Accomplishment Concept (TITAN III) • 1990 Canadian DOD—PMS
• 1966 AF—Cost/schedule Planning And Control • 1991 DODI 5000.2 replaces DODI 7000.2
Specification (C/SPCS)
• 1992 National Oceanic And Atmospheric
• 1967 DOD—Cost/Schedule Control Systems Administration (NOAA)—PMS
Criteria (C/SCSC) (DODI 7000.2)
• 1993 Swedish FMV—C/SCSC
• 1972 DOD—-Revised DODI 7000.2 and Issued the
• 1994 Internal Revenue Service (IRS)—C/SCSC
Joint Implementation Guide (JIG)
• 1994 Federal Bureau Of Investigation (FBI)
• 1972 NASA Marshall Space Flight Center—C/SPC
—C/SCSC
• 1975 DOE—Performance Measurement System
• 1996 DODR 5000.2-R replaces DODI 5000.2
(PMS)
C/SCSC revised from 35 to 32 criteria
• 1976 DOD—Revised the C/SCSC JIG
• 1996 Revised JIG—Renamed Earned Value
• 1980 DOD—Revised the C/SCSC JIG Management Implementation Guide (EVMIG)
• 1982 National Security Agency—Earned Value • 1997 EVMIG Revised
• 1983 NASA—Goddard Space Flight Center—PMS • 1998 MIL-STD 881B replaced by MIL HDBK 881
• 1984 FAA & NASA Lewis Research Center—PMS

12/25/06 EVM Introduction 42

12/25/06 EVM Introduction 42


EVM Resources

• Books • Software [continued]


; Earned Value ; Dekker TRAKKER
Quentin W. Fleming & Joel M. Koppleman Dekker Ltd.
; Cost/Schedule Control Systems Criteria Contact: Ron Barry (909) 384-9000
Quentin W. Fleming Web: http://www.dtrakker.com
; Project Performance Measurement ; MicroFrame Project Manager (MPM)
Robert R. Kemps MicroFrame Technologies, Inc.
; Visualizing Project Management Contact: Carl Amacker (415) 616-4000
Kevin Forsberg, Ph.D., Hal Mooz and Web: http://www.microframe.com
Howard Cotterman • Internet
• Software ; Project Management Institute
; Artemis Views http://www.pmi.org
Artemis Management Systems ; US DoD Earned Value
Contact: Patrick Perugini (303) 581-3102 http://www.acq.osd.mil/pm
Web: http://www.artemispm.com ; Earned Value Bibliography
; Cobra http://www.uwf.edu/~dchriste/ev-
Welcom Software bib.html
Contact: Diana Melton (281) 558-0514
Web: http://www.wst.com

12/25/06 EVM Introduction 43

12/25/06 EVM Introduction 43

You might also like