Professional Documents
Culture Documents
Brief Introduction To Earned Value Management (EVM)
Brief Introduction To Earned Value Management (EVM)
Brief Introduction To Earned Value Management (EVM)
• Background materials
NE
LI
SE
BA
Each chunk of work
3. ALLOCATE BUDGETS corresponds to a
chunk of budget and
100
a chunk of schedule.
40
60
15
25
30
TIME
30
12/25/06 EVM Introduction 5
Month 4 Month 5
BCWS = $1,000 BCWS = $1,000
Each
Eachdollar
dollarof
ofBCWS
BCWSrepresents
representsaaspecific
specificdollar
dollarof
ofwork
work
scope.
scope.BCWS
BCWSis isaggregated
aggregatedand
andsummed
summedas asthe
theperformance
performance
measurement
measurementbaseline.
baseline.
12/25/06 EVM Introduction 7
You
Youearn
earnvalue
valuethe
thesame
sameway
way
as
asititwas
wasbudgeted
budgetedin inthe
thebaseline.
baseline.
SCHEDULE
SCHEDULEVARIANCE
VARIANCEisisthe
thedifference
differencebetween
betweenwork
workscheduled
scheduled
and
andwork
workperformed
performed(expressed
(expressedininterms
termsof
ofbudget
budgetdollars)
dollars)
formula:
formula: SV
SV$$==BCWP
BCWP--BCWS
BCWS
example:
example: SV
SV==BCWP
BCWP--BCWS
BCWS==$1,000
$1,000--$2,000
$2,000
SV= -$1,000
SV= -$1,000 (negative
(negative==behind
behindschedule)
schedule)
5,000
BCWS
“the baseline”
sv
$
BCWP
“earned value”
TIME 5 months
actual
actualexpenditures
expendituresvs.
vs.budget
budget
PERFORMANCE BASED
BC WP
Of the work we actually performed,
how much did we budget for it to cost?
COST
COSTVARIANCE
VARIANCEisisthe
thedifference
differencebetween
betweenbudgeted
budgetedcost
cost
and
andactual
actualcost
cost
formula:
formula: CV
CV$$==BCWP
BCWP--ACWP
ACWP
example:
example: CV
CV==BCWP
BCWP--ACWP
ACWP==$1,000
$1,000--$2,400
$2,400
CV= -$1,400
CV= -$1,400 (negative
(negative==cost
costoverrun)
overrun)
5,000
ACWP
“actual cost”
cv
$ BCWP
“earned value”
TIME 5 months
5,000
BCWS
ACWP
cv
$ sv
BCWP
TIME 5 months
sorted by CV ($)
By tracking and sorting on variances, we
can isolate the troublesome WBS
elements. WBS DESCRIPTION Proj Ofcr %Comp %Spent CPI CV CV CV % VAC VAC
1 3600 PCC Zepka 28.99 34.09 0.850 ↑ -296.2 -17.62 ↔ -187.2
2 3200 COMMUNICATIONS Tideman 34.63 41.03 0.844 ↓ -130.8 -18.49 ↔ -87.0
3 G&A GEN & ADMIN 33.67 36.11 0.932 ↓ -45.2 -7.26 ↔ -36.8
4 2200 SYS ENGINEERING Price 85.04 94.35 0.901 ↓ -26.4 -10.95 ↔ 0.0
5 3800 I&A Troop 35.40 37.08 0.955 ↓ -24.2 -4.75 ↔ -24.8
6 2100 PROJ MANAGEMENT Brown 45.70 48.51 0.942 ↔ -17.4 -6.16 ↔ -3.2
7 2300 FUNC INTEGRA Price 71.62 75.23 0.952 ↓ -17.4 -5.03 ↔ -30.8
8 5200 MANAGEMENT DATA Simmons 84.18 98.10 0.858 ↓ -13.2 -16.54 ↑ -16.0
9 3100 SENSORS Smith 20.87 21.49 0.971 ↓ -10.6 -2.94 ↔ -21.6
10 4000 SPARES Blair 17.87 18.90 0.945 ↑ -7.8 -5.78 ↔ -6.2
11 6200 SYSTEM TEST Hall 60.82 61.66 0.986 ↑ -5.6 -1.38 ↔ -2.0
12 5100 ENG DATA Novak 38.51 52.80 0.729 ↓ -4.6 -37.10 ↔ 0.0
13 MR MGT RESERVE 0.00 0.00 0.0 ↔ 439.2
14 UB UNDIST BUDGET 0.0 0.0
15 COM COST OF MONEY 0.0 0.0
16 3700 DATA DISPLAY Troop 41.13 41.13 1.000 ↔ 0.0 0.00 ↔ 0.0
17 OV OVERHEAD 0.0 0.0
18 6100 TEST FACILITIES Smart 100.00 98.02 1.020 ↔ 2.0 1.98 ↔ 0.0
19 3500 COMP PROGRAMS Pino 46.46 44.66 1.040 ↓ 3.4 3.87 ↔ -1.4
20 6300 PCC TEST Bond 23.13 22.64 1.021 ↓ 4.2 2.10 ↔ 0.0
21 3400 ADPE Zepka 41.89 39.79 1.053 ↓ 12.6 5.02 ↔ 4.6
22 3300 AUX EQUIP Tideman 27.57 24.33 1.133 ↓ 78.2 11.73 ↓ 8.4
COST
COSTPERF
PERFINDEX
INDEX(CPI)
(CPI) == BCWP
BCWP
1.2 ACWP
ACWP
“GOOD”
SCHED
SCHEDPERF
PERFINDEX
INDEX(SPI)
(SPI)== BCWP
BCWP
1.1 BCWS
BCWS
TIME
1.0
CPI
.9
“BAD”
SPI
.8
$
$
$ $
$
$
$
time
When
Whenall
allwork
workhas
hasbeen
beenphased,
phased,the
thecumulative
cumulativeBCWS
BCWS==BACBAC
e.g.,
e.g., $5,000
$5,000==$5,000
$5,000
12/25/06 EVM Introduction 17
EAC = BAC/CPI
VARIANCE
VARIANCEAT
ATCOMPLETION
COMPLETIONisisthe
thedifference
differencebetween
betweenwhat
whatthe
thetotal
total
job
jobisissupposed
supposedto
tocost
costand
andwhat
whatthe
thetotal
totaljob
jobisisnow
nowexpected
expectedto
tocost.
cost.
FORMULA:
FORMULA: VAC
VAC==BAC
BAC--EAC
EAC
Example:
Example: VAC
VAC==$5,000
$5,000--$7,500
$7,500
VAC
VAC==--$2,500
$2,500 (negative
(negative==overrun)
overrun)
BAC
TIME
EAC = BAC/CPI,
BCWP Ratio of work accomplished against money spent (an efficiency rating: Work
Cost Performance Index CPI or PF
or Performance Factor ACWP Done for Resources Expended)
To Complete BAC - BCWP Ratio of work remaining against money remaining (Efficiency which must be
Performance Index TCPI or VF achieved to complete the remaining work with the expected remaining money)
EAC - ACWP
or Verification Factor
SPI BCWP Ratio of work accomplished against what should have been done (Efficiency
Schedule Performance Index
BCWS Rating: Work done as compared to what should have been done)
BCWPcum
Average Performance PCUM Duration (wks or mos) Average rate at which work has been accomplished since work began
Since ACWP Began
BCWPcum
Duration (wks or mos)
Average Expected Average rate at which work must be accomplished in the future to finish on the
P TO GO From Time Now to
Performance To Finish date the CAM has forecasted for completion of the work.
Manager's Stated
Completion Date
20.0
Overall cost and schedule trend
10.0
0%
0.0
-6%
-7% -11%
-10.0
-20.0
-30.0
Dollars In Millions
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN
8.0
PMB: 20.4 % COMP: 32.9 MR: 0.4 KTR MR LRE: 0.0 PO MR LRE: 0.0
COST VARIANCE CURRENT FUNDING: 10.0 AS OF: JAN 93
SCHEDULE VARIANCE PO EPC: 24.0 OPR: MR B. TECH
PROJ FUNDING: 23.0 PROGRAM: Mohawk Vehicle
7.0
graphs
graphsshow
showoverall
overalltrend...
trend...
6.0
are
areyou
yougetting
gettingbetter,
better,
or
orworse?
worse? 5.0
BAC 5.1 5.1 5.1 5.1 5.1 5.1 5.1 5.5 5.5 5.8
LRE 5.4 5.4 5.4 5.4 5.5 5.5 5.5 5.7 5.7 6.0
CUM CPI 5.1 5.7 5.9 6.0 6.3 5.8 6.5 7.6 6.8 6.8
HISTORY
Compare the CPI to the TCPI-BAC:
TCPI(BAC) = Efficiency necessary to complete on budget FUTURE
WORK
= BAC-BCWP = REMAINING = $5000 - $1000 = $4000
BAC-ACWP $2600 = 1.54
BUDGET $5000 - $2400
REMAINING
WORK
= BCWP = ACCOMPLISHED = $1000 = .50
BCWS WORK $2000
SCHEDULED
WORK
= BAC-BCWP = REMAINING = $5000 - $1000 = $4000 = 1.00
LRE-ACWP ESTIMATE $6400 - $2400 $4000
REMAINING
reasonable?
• Background materials
SOFTWARE
INTEGRATION
PROGRAM
SELECTED
PSWBS
ELEMENTS Product Master
Development Planning
D
A
T
Software
A
Secure Control
VP/GM Engineering Engineering Systems Account
S
U
Work M
Packages M
A
Operations
Hardware LAN Control Control BCWS R
Engineering Applications Account Account BCWP I
ACWP Z
BAC Planning A
Responsibility Matrix
EAC Packages T
I
O
N
OBS DATA SUMMARIZATION
• Work Package
Work Pkg #1
$ $ $
Work Pkg #2
• subset of control account $ $ $
Work Pkg #3
• reasonably short in duration
• single element of cost (e.g., labor)
• single technique for earning value
• consistent with detail schedules
• has same characteristics as control account
– scope of work
– milestone completion criteria
– single performing organization
– start and end dates
12/25/06 EVM Introduction 35
• 0/50/100 measurement
• Typical work package length is 80 hours.
• Work package status is reported at status meetings, held every
two weeks.
– May just be that 50% of work packages are reported at weekly
status meetings.
• EV is 0% (of budget for work package) if it has not yet been
started, or is only now starting.
• EV is 50% if work is underway.
• EV is 100% if work is complete.
• If work package is at 50% two status meetings in a row, it is
flagged as a potential issue.
• Avoids subjectivity of “% done”; compromises on granularity of
tracking, frequency of reporting
• Puts the onus on doing the WPs right, up front.
12/25/06 EVM Introduction 39
• Background materials
Foreign
Countries
ANSI/EIA-748-1998
Core EV Principles Tailored Applications (32 criteria)
*with judgment