COST in

S.No COMPONENT NOTATION


Million Rs.

1 Gross value for workdone upto this quarter A 87.5

2 Gross value for workdone upto last quarter B 47

3 Gross value of workdone since previous quarter C = A -B 40.5

Full assesed value of Secured Advances fresh


4 paid in this quarter D 4.6

Full assesed value of Secured Advances


5 E 1.12
recovered in this quarter
Full assesed value of Secured Advances for
6 which Escalation is payable in this quarter F=D-E 3.48
7 Advance Payment during this quarter G 0
8 Advance Payment recovered during this quarter H 0

Advance payment for which Escalation is


9 payable in this quarter I = G -H 0

Extra Items to be paid as per prevailing market


10 rates J 2.92
11 M=C+F+I-J 41.06
12 N = 0.85 M 34.901
Less cost of material supply by the Dept. &
13 recovered during this quarter K 0

Less cost of services rendered at fixed charges &


14 recovered during this quarter L 0
15 Cost of Work for which Escalation is applicable W = N - ( K+L) 34.901
BASE PRICE
QUANTITY (P) in Rs / BASE PRICE
S.No MATERIAL (Q) in MT MT INDEX C.I0

1 Cement 3200 6200 6200


Reinforcem
2 ent Steel 400 47500 47500
PERIOD
PRICE EXTRA PRICE
INDEX C.I FORMULA in Million Rs.
Q x P x (C.I -
6800 C.I0) / C.I0 1.92
Q x P x (C.I -
50000 C.I0) / C.I0 1
Total Extra
Amount 2.92