Professional Documents
Culture Documents
2016 C L D 1833
2016 C L D 1833
[Islamabad]
Before Miangul Hassan Aurangzeb, J
ATLAS CABLES (PVT.) LIMITED----Appellant
Versus
ISLAMABAD ELECTRIC SUPPLY COMPANY LIMITED and another----Respondents
R.S.A. No.2 of 2016, decided on 16th May, 2016.
(a) Contract---
----Force majeure, doctrine of--- Applicability---Force majeure refers to legal or physical
prevention and not economic activity which is not profitable---Change in economic or market
circumstances, affecting profitability of a contract or the case in which parties' obligation can be
performed is not regarded as being a force majeure event.
Advanced Law Lexicon by P. Ramanatha Aiyar, 3rd Edition; Halsbury's Laws of
England, 4th Edition, Volume 51; Dhanrajamal Gobindram v. Shamji Kalidas AIR 1961 SC
1285; M/s. Alopi Parshad v. Union of India AIR 1980 SC 588; Brauer & Co. (Great Britain),
Ltd. v. James Clark (Brush Materials), Ltd. [1952] 2 All ER 497 and Thames Valley Power Ltd.
v. Total Gas and Power Ltd. [2006] 1 Lloyd's Rep. 441 rel.
(b) Contract Act (IX of 1872)---
----S. 126---Contract of guarantee or surety---Scope---Guarantee, genesis of---Guarantee
envisages two contracts, one between principal debtor and creditor and second between creditor
and surety---Guarantee has its genesis in underlying contract between principal debtor and the
creditor---Irrevocable and unconditional bank guarantees are normally couched in a language
whereby bank undertakes to give money to the beneficiary on demand without demur or
protest---If a bank guarantee is unconditional stipulating that the bank should pay, on demand,
without demur and that the beneficiary is the sole judge not only on the question of breach of
contract but with respect to the amount or loss or damage, the obligation of the bank has to be
discharged in the manner provided in the bank guarantee---When such demand is made, the bank
is not permitted to probe into the disputes between the parties---Court should not interfere
directly or indirectly to withhold payment, otherwise trust in commerce internal and international
may be irreparably damaged.
Haral Textiles Milited v. Banque lndosuez Belgium, S.A. 1999 SCMR 591; Shipyard K.
Damen International v. Karachi Shipyard and Engineering Works Ltd. PLD 2003 SC 191 and
Standard Construction Company (Pvt.) Limited v. Pakistan, through Secretary M/o
Communications and others 2010 SCMR 524 rel.
(c) Contract---
----Construction of contract---Principle---First rule of construction of a contract or a document is
to ascertain intention of parties to it.
(d) Contract Act (IX of 1872)---
----S. 74---Liquidated damages and penalty---Distinction---Liquidated damages are recognized
as a genuine pre-estimate of losses suffered due to another party's breach of contract, whereas
penalty is a sum of money so stipulated in terrorem so as to drive a party to fulfil a contract.
Muhammad Karimuddin v. Kanza Food Industries Ltd. 1989 MLD 3900 rel.
(e) Specific Relief Act (I of 1877)---
----Ss. 42 & 54---Contract Act (IX of 1872), Ss. 73, 74 & 126---Suit for declaration and
injunction---Performance bonds, encashment of---Liquidated damages and penalty---Recovery---
Plaintiff company entered into a contract of supply and the Bank issued performance bonds in
support of plaintiff---Due to change in market situation, plaintiff failed to supply goods as per
contract, therefore, defendant sought encashment of performance bonds and also sought recovery
of damages as well as liquidated damages---Suit and appeal filed by plaintiff company were
concurrently dismissed by Trial Court and Lower Appellate Court---Validity---Damages had to
be first pleaded and thereafter proved by leading trustworthy and cogent evidence---Damages
required evidence regarding details of losses actually suffered and liquidated damages, as a rule,
required positive evidence to show actual loss suffered by party claiming the damages---Even
fixed amount stipulated in contract as liquidated damages could not be recovered if quantum of
actual loss suffered was not proved through sufficient evidence---Defendant did not plead or
prove any loss caused by breach of contract by plaintiff, therefore, it could not encash
performance bond which was furnished to compensate defendant for the losses it was to suffer
on account of such breach--- Defendant was not entitled to invoke provisions of performance
bond or encash the same unless it was established through adjudicatory process that plaintiff
committed default of the provisions of purchase orders and as a result of the default defendant
suffered damages---Once such default on the part of plaintiff and loss suffered by defendant as a
result of such default was proved, performance bonds could have been encashed to the extent of
such loss---High Court set aside judgments and decrees passed by two courts below and suit was
partially decreed in favour of plaintiff---Second appeal was allowed accordingly.
Jamia Industries Ltd. v. Pakistan Refinery Ltd. PLD 1976 Kar. 644; Pakistan Engineering
Consultants v. PIA Corporation 1993 CLC 1926; Pakistan Engineering Consultants v. P.I.A.
Corporation 1989 SCMR 379; Zeenat Brother (Pvt.) Ltd. v. Aiwan-e-Iqbal Authority PLD 1987
Kar. 183; China International Water and Electric Corporation v. WAPDA 2001 YLR 2191;
Mehboob Enterprises v. Karachi Development Authority 1997 MLD 3085; Mercury Corporation
v. Pakistan Steel Mills Corporation (Private). Ltd. 2000 YLR 734; Messrs A.Z. Company,
Karachi v. Government of Pakistan and another PLD 1973 SC 311; Sandoz Limited v.
Federation of Pakistan 1995 SCMR 1431; Muhammad Farooq Azam v. Bank Al-Falah Limited
2015 CLD 1439; Bhai Panna Singh and others v. Bhai Arjun Singh and others AIR 1929 Privy
Council 179; Saudi-Pakistan Industrial and Agricultural Investment Company (Pvt.) Ltd.,
Islamabad v. Messrs Allied Bank of Pakistan PLD 2003 SC 215; Messrs Khanzada Muhammad
Abdul Haq Khan Khattak and Co. v. WAPDA through Chairman WAPDA, and another 1991
SCMR 1436; Industrial Development Bank of Pakistan v. Messrs Baloch Engineering Industry
(Pvt.) Ltd. 2010 CLD 591; Messrs United Bank Limited v. Messrs M. Esmail and Company
(Pvt.) Limited 2006 CLD 394; Allied Bank of Pakistan Limited, Faisalabad v. Messrs Asisha
Garments 2001 MLD 1955; National Development Finance Corporation v. Moona Liza Fruit
Juices Limited 1999 YLR 500 and Messrs HITEC Metal Plast (Pvt.) Ltd. v. Habib Bank Limited
PLD 1997 Quetta 87 ref.
(f) Qanun-e-Shahadat (10 of 1984)---
----Arts. 117 & 120---Damages---Onus to prove---Scope---Burden to prove actual loss is on the
party who claims damages or compensation, even in the cases of liquidated damages.
Rashid Hanif for Appellant.
Muhammad Khalid Zaman for Respondent No.1.
Dates of hearing: 1st, 2nd, 18th, 22nd and 24th March, 2016.
JUDGMENT
MIANGUL HASSAN AURANGZEB, J.---Through the instant Regular Second Appeal
under Section 100 of the Code of Civil Procedure, 1908, ("C.P.C."), the appellant, M/s. Atlas
Cables (Pvt.) Limited, assails the judgment dated 04.01.2016, passed by the Court of the learned
Additional District Judge, Islamabad, whereby the appellant's first appeal against the judgment
and decree dated 15.04.2015, passed by the Court of the learned Civil Judge, Islamabad (West),
was dismissed. Vide the said judgment and decree dated 15.04.2015, the learned Civil Court
dismissed the appellant's suit for declaration and permanent injunction.
2. The facts essential for the disposal of the instant appeal are that after a tender bidding
process conducted by the Islamabad Electric Supply Company ("respondent"), for the supply of
ACSR RABBIT ("Cable"), the following three purchase orders were issued to the appellant:--
1. Purchase order No.1188, dated 07.01.2006, for the supply of 1,300 Km. of Cable
for a total contract price of Rs.38,047,750/-.
2. Purchase order No.1255, dated 13.05.2006, for the supply of 1,000 Km. of Cable
for a total contract price of Rs.36,800,000/-.
3. Purchase order No.1811, dated 20.02.2009, for the supply of 1,800 Km. of Cable
for a total contract price of Rs.77,290,200/-.
3. These three purchase orders shall hereinafter collectively be referred to as "the POs". The
terms and conditions of the POs are more or less the same. Under the terms of the POs, the
appellant was required to furnish performance bonds for an amount equal to 5% value of the POs
in favour of the Chief Executive Officer of the respondent. These performance bonds were
required to be issued by a scheduled bank of Pakistan and were to be valid for one year from the
date of the completion of the supply of material.
4. The appellant had furnished the following three performance bonds issued by Habib
Metropolitan Bank Limited in favour of the respondent:-