Professional Documents
Culture Documents
Stakeholder Management Assignment - Haarika
Stakeholder Management Assignment - Haarika
Haarika Reddy K
RICS – CPM (Batch 04)
Topic:
Q1. Study the Bandra Worli Sea Link Project and identify the stake holders. Find out if the
project delay was caused due to improper stake holder engagement and how that
stakeholder / stake holders could have been managed better
Project introduction:
The Bandra–Worli Sea Link (officially known as Rajiv Gandhi Sea Link) is a bridge that links
Bandra in the Western Suburbs of Mumbai with Worli in South Mumbai. It is a cable-stayed
bridge with pre-stressed concrete-steel viaducts on either side. It is a part of the proposed
Western Freeway that will link the Western Suburbs to Nariman Point in Mumbai's main
business district.
This bridge was commissioned by the Maharashtra State Road Development Corporation
(MSRDC), and built by the Hindustan Construction Company.
The sea-link of 5.6 kms reduces travel time between Bandra and Worli during peak hours
from 20–30 minutes to 10 minutes. As of October 2009, this sea link had an average daily
traffic of around 37,500 vehicles.
The schedule of this project was delayed by about 5 years and cost over-run by about 5
times the initial estimate. The cost of the project was 1634 crore rupees as against the initial
estimated cost of about 300 crore. Construction began in the year 2000. The first four of the
eight lanes of the bridge were opened to the public on 30 June 2009. All eight lanes were
opened on 24 March 2010. Charging a toll of almost Rs 70 (for a car) for the 5.6-km sea link
is one of the highest tolled roads in the state.
Stakeholder Role
Contractor
Hindustan construction company (HCC)
Dar-Al Handasah Project mangers
Mumbai Metropolitan Region Development Authority Initiator and planner for the city
Central Water and Power Research Station
(CWPRS) Research and feasibility
Jacob engineering India pvt limited Design consultants
HNTB Consultants
Some of the External stake holders mentioned above had approached Ministry of
Environmental Affairs with claims/ objections on following issues:
Ministry of
Environmental
Affairs
Some of the internal stake holders’ decisions which impacted the project progress:
Improper pre-feasibility analysis
Selection process of the design consultant and subsequent change of the Design
consultant
Change in design from “Arch Bridge” to “Cable tray” – resulted in delay in
completion of Stage-IV of the project
Violation of various environmental compliances like not holding a mandatory
public hearing prior to environmental clearance
Delay in commencement of works on account of IPL filed by the external stake
holders though project was awarded in year 2000 by MSRDC
Dynamic stake holder influence is observed as the progress of the project:
The activists who were external stake holders gained interest and power as the
project progressed with the help of media.
The activists’ power reduced as the High court resolutions were passed in favour
of the project decisions and environmental clearances.
The internal-primary stake holders like MSRDC, BWSL and HCC initially had high
power but the same reduced as the project progressed
The recovery of the financed project costs is a matter questionable even today
hence resulting in loss the internal stake holders’ power.
Starting from its planning phase BWSLP lacks proper management, it has violated various
norms for environmental compliances that has to be followed in India. And they are as listed
below:
Public hearing:
It is to be noted that public participation is an extremely crucial component of
governance and has to be treated seriously. Above all the affected population
has a right to be informed about any project that has been undertaken. But all the
members of local community and other concerned citizens have stated that they
were not consulted.
Bombay environmental action group initiated and sent a letter to Mumbai
municipal road development authority (MMRDA) regarding their objections,
comments and suggestions however no response was received.
BEAG also sent a letter dated 8th of September 1998 to ministry of environment
and forest stating their objections and suggestions and even this time there was
no response.
All these incidents clearly point to the fact that the environmental clearance was
given to the project without holding a mandatory public hearing.
The various aspects of Stakeholder management in the project given above indicate that a
better stakeholder engagement plan would have resulted in handling the project in a better
way. Hence, the following stake holder engagement plan is recommended.
Involve the general public and residents to reduce the dissatisfaction by way of conducting:
Public briefings
Community fairs
Field trips
Media releases
The above would have resulted in saving time and money of the internal stake holders.
The following are to be organised for the stake holders who are legitimate and have great
interest in the project:
Citizen committees
Fish bowling
Consensus
The following are to be organised for the stake holders who have little power and have less
interest in the project:
Public involvement
Scenario testing
Consensus conferences
Conclusions:
The project is definitely a success in Engineering and Architectural aspect, but has failed
in terms of Financial and Stakeholder management. Better project planning and improved
stakeholder engagement would have saved costs, time and resources and would have
resulted in better project cost recovery.