Visual Inspection Equipment

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7

Visual Inspection Equipment

 Magnifying Glass
 Microscope
 Magnifying Mirror
 Borescope
o Endoscopes or Endoprobes
 Flexible Fiber Optic Borescopes
o Working lengths are normally 60 to 365 cm with diameters from 3 to 12.5mm
 Video Imagescope

WPS & PQR Check List


JOINTS

 in groove design
 backing in single sided weld
 backing and chemical composition
 in root spacing
 nonfusing retainers

Base Metal

 in group number
 Limits impact
 Qualified
 pass > 1/2 in. (13 mm)
 T Limits Qualified (Short Circuit Arc)

Filler Metals

 Size
 Diameter
 Diameter > 1/4 in. (6 mm)
 Flux/Wire Classification
 Alloy flux
 AWS classification
 Filler
 Consumable insert
 Filler metal product form (Solid/metal or flux-cored)
 Supplemental Filler Metal
 Supplemental Powder Filler metal
 Supplemental Powder Filler metal
 Alloy elements
 Flux designation
 Limits (Short Circuit Arc)
 AWS Classification
 Flux Type
 Flux/Wire Classification
 Recrushed Slag
 Flux

Positions

 Position

Preheat

PWHT

Gas

 Trailing or f composition
 Single, mixture or %
 Flow rate
 Backing flow
 Backing or f composition
 Shielding o

Electrical Characteristics

 Heat input
 Transfer Mode
 Pulsing
 Current or Polarity
 I & E Range
 Tungsten electrode

Technique

 String/Weave
 Orifice cup, or nozzle size
 Method of cleaning
 Method of back gouge
 Oscillation
 Tube to Work distance
 Multi to single pass per side
 Single to multi electrodes
 Closed to out of chamber welding
 Electrode spacing
 Manual or Automatic
 Peening
PQR
 Welding Process – SMAW

 Process Type - Manual

 Position - Flat

 PQR No

 WPS No

 Base Metal part (Material Spec., Type (or) Grade ASTM A 516 Grade 60

 Thickness/Pipe Diameter

 Filler Metals E7018

 Join Design

 Weld Type : Complete joint penetration, Weld Grove.

 Joint Type : Butt joints

 Backing Option : Method ( Mechanical )

NDT PROCEDURES
NDT shall be performed in accordance with agreed written procedures that, as a minimum give detailed
information on the following aspects:

 Applicable code or standard


 Materials and dimensions
 Testing parameters and variables
 Assessment of imperfections
 Reporting and documentation of results
 Reference to applicable welding procedures
 Acceptance criteria
 Welding process
 Joint configurations and dimensions
 Technique
 Equipment, main and auxiliary
 Sensitivity
 Calibration techniques and calibration references
 Testing parameters and variables
 Assessment of imperfections
 Reference to applicable welding procedures
 Personnel qualifications
Piping Pre-hydro Checklist
 Project Number:
 Owner:
 Job No:
 Test Package No:
 Location:
 Area:
 Specification:
 Flow Diagram:
 Drawing:
 Attribute Requirement Sat/Unsat Remarks
 Fabrication and Installation
 Identification, Class, Mark No. Verify
 Location Verify Per Drawing
 Cleanliness Inspect
 Protection (Caps, etc.) Inspect
 Bending Verify Per Procedure
 Installed Per Isometric Verify Per Drawing
 Slope (If Required) Verify Per Drawing / Spec
 Support And Bracing Per Spec.
 Inspect Type, Welding, Location,
 Weep Holes In Dummy Legs,
 Workmanship
 Valve / Component/ Inst. Installation
 Inspect Tagging, Orientation, Flow
 Direction, Vents & Drains & Test
 Nipples, Taps, Vents, Drains (Plugged) Verify Per Spec
 Mechanical Connections / Studs /
 Gaskets Inspect Per Spec
 Workmanship & Installation
 Inspect, Verify Correct And Complete
 Welding
 Welding Procedures / Welder
 Qualification
 Verify Acceptable And Current
 End Preparation, Fit-up,
 Workmanship
 Verify Weld Inspection In-Process
 Cold Spring Gap Inspect
 NDE Personnel Qualifications Confirm Acceptance
 NDE Type, Amount & Results Confirm Complete & Accepted
 Final Weld Visual/PWHT Inspected And Accepted
 Hanger Installation
 Identification, Location And Spacing Verify Per Drawing
 Nameplate Info., Type & Installation Verify Per Drawing
 Piping Supervisor / Inspector:
 Welding Supervisor / Inspector:
 Quality Assurance Manager

AWS Heat Treatment Sheet


PREHEAT:AWS D1.1, Table 3.2 Prequalified Minimum Preheat and Interpass Temperature °F (°C)

Thickness 3 to 20 mm (1/8 to 3/4 in.) incl.: 32°F (0°C)

Over 20 thru 38 mm (3/4 to 1-1/2 in.) incl.: 50°F (10°C)

Over 38 thru 65 mm (1-1/2 to 2-1/2 in.) incl.: 150°F (65°C)

Over 65 mm (2-1/2 in): 225°F (110°C)

For SMAW process, above preheat data is with low hydrogen electrodes.

When the base metal temperature is below 32°F (0°C), preheated to a minimum of 70°F (20°C)

Preheat and interpass temperature shall be sufficient to prevent cold cracking.

Guideline on Alternative Methods for Determining Preheat/Interpass: See Annex XI of AWS D1.1

POSTWELD HEAT TREATMENT:


PWHT requirements shall be based on Welding Procedure Specification (WPS)

AWS D1.1, 5.8 Stress-Relief Heat Treatment: Where required by the contract

drawings or specifications, welded assemblies shall be stress relieved by heat treating.

(See AWS D1.1, 5.8.1, Requirements for stress-relief treatment;

Table 5.2, Minimum Holding Time; Table 5.3, Alternate Stress-Relief Heat Treatment)

See AWS D1.1, 5.8.3, Steels Not Recommended for PWHT


Surface :
Roughness, Erosion, Corrosion, Oxidation, Frictional Characteristics, Residual Stress Cracking,

Cohesion, Graded Composition

- Microstructrual Analysis

- Compositional Analysis

- Structural Analysis

- Mechanical Property Analysis

- Chemical Property Analysis

Painting Process Materials


Work Shop 1st Layer Etching Primer Spary 130
2nd Layer Rust Resisting Paint Spary 170
3rd Layer Rust Resisting Paint Spary 170
Field 4th Layer Phthalic Resin Coating Brush 110
5th Layer Phthalic Resing Coating Brush 10 S
Test Pack
 Isometric Drawing

 Material Certificate

 Welding Inspection Report(Visual Inspection Report)

 Welder Qualification certificate

 WPS

 NDT Reports

 PWHT

 Hydro Test
Welding Inspection Reports
 Weld No

 Draw No

 Material Specifications

 Welder No

 Weld Date

 Visual Inspection

 NDT RT/MT

 PWHT

 Remarks

You might also like