Professional Documents
Culture Documents
University of Mauritius
University of Mauritius
University of Mauritius
FACULTY OF ENGINEERING
MAY 2009
4 May 2009
NO. OF 4 NO. OF 4
QUESTIONS SET QUESTIONS TO BE
ATTEMPTED
INSTRUCTIONS TO CANDIDATES
Question 1
(b) The table below lists all the activities on a particular construction project.
TBD: to be determined
IPA: Immediately preceding activities
(i) Determine the durations of activities I,J and K using data given in below;
Activity “I” is screed work and for this particular project the total surface area
to be screed is 12,000 square feet. The team responsible for this Activity has a
production rate of 2000 square feet per day.
[1 mark]
Activity J is subdivided into 3 sub- activities and performed by 3 different
team with the following production rates of 2 days/act.,1 day/act. and 3
days/act. respectively. [2 marks]
Activity K is carried by 2 teams. Team 1 has 10 people and the other one has 2
times more people. Team 2 works at night and team 1 works during the day.
People working during the day are 2 times more productive than those
working at night.
Given that the night production rate is 5 m2/night /person and that the total
area to be covered for Activity K is 2000m2, determine the duration of Activity
K.
[3 marks]
[continued next page]
Page 1 of 3
CONSTRUCTION MANAGEMENT – CIVE6207
Question 1 [continued]
(iv) Update the Network diagram based on following available data, at the
end of day 14.
(c) Based on the above exercise which activities influence the overall project
duration?
[4 marks]
Question 2
3 2m
2m
1
Proposed construction
Area
5m 4
5
5m
2
Main Road
Page 2 of 3
CONSTRUCTION MANAGEMENT – CIVE6207
Question 2 [continued]
Position
(c) List 5 safety measures that you would recommend the contractor to fully
comply to.
[5 marks]
Question 3
(a) Describe in chronological order three types of estimates that estimators come
across during the lifespan of any construction project.
[15 marks]
(b) Do you think that an estimator can come up with a budget just by reading the
client’s brief? Justify your answer.
[5 marks]
Question 4
(b) Describe, with full justifications, which of the two procurement methods
would you recommend a client to adopt on the following two projects;
(i) A bridge linking two towns has just collapse and this is impacting
greatly on the economy of the towns.
[7 marks]
(ii) The client wants to construct a school for handicapped children but
unfortunately, only 30% of the estimated budget is available.
[8 marks]
Page 3 of 3