Site no.250-Prototype no.

48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250 KAP5-Site No.250-(AL-MUJAHIDIN DEPARTMENT BRANCH


9-Apr-15 9-Apr-15
COMPLETION)-Prototype
29-Mar-17 no.48-ASIR Zone 29-Mar-17
250.1 Project Milestones 9-Apr-15 29-Mar-17 9-Apr-15 29-Mar-17
250.1.6 General Milestones 9-Apr-15 29-Mar-17 9-Apr-15 29-Mar-17
250.1.4 Engineering Works Milestones 9-Apr-15 11-Jul-15 9-Apr-15 11-Jul-15
250.1.1 Shop Drawings Milestones 12-Jul-15 2-Apr-16 12-Jul-15 2-Apr-16
250.1.1.1 Shop Drawings Submittal Milestones 12-Jul-15 16-Mar-16 12-Jul-15 16-Mar-16
250.1.1.2 Shop Drawings Approval Milestones 12-Jul-15 2-Apr-16 12-Jul-15 2-Apr-16
250.1.2 Procurement Milestones 26-May-15 23-Jun-16 26-May-15 23-Jun-16
250.1.3 Construction Milestones 9-May-15 12-Feb-17 9-May-15 12-Feb-17
250.1.3.1 Site Construction Milestones 9-May-15 12-Feb-17 9-May-15 12-Feb-17
250.1.3.2 Main Building Milestones 12-Jul-15 31-Jul-16 12-Jul-15 31-Jul-16
250.1.3.3 Barrack Milestones 27-Jul-15 31-Aug-16 27-Jul-15 31-Aug-16
250.1.3.4 Electricity room Milestones 5-Aug-15 17-Sep-16 5-Aug-15 17-Sep-16
250.1.3.5 Mosque Milestones 1-Aug-15 28-Sep-16 1-Aug-15 28-Sep-16
250.1.3.6 Ware house Milestones 16-Jul-15 31-Oct-16 16-Jul-15 31-Oct-16
250.1.3.9 Main Entrance Milestones 9-Aug-15 31-Oct-16 9-Aug-15 31-Oct-16
250.1.3.7 Kiosk Milestones 7-Aug-16 20-Sep-16 7-Aug-16 20-Sep-16
250.1.8 Testing & Commissioning Milestones 1-Nov-16 15-Feb-17 1-Nov-16 15-Feb-17
250.1.5 Handing Over & Project Close Out Milestones 26-Dec-16 29-Mar-17 26-Dec-16 29-Mar-17
250.2 Engineering Works 9-Apr-15 11-Jul-15 9-Apr-15 11-Jul-15
250.2.1 Design Work 9-Apr-15 11-Jul-15 9-Apr-15 11-Jul-15
250.2.1.1 Site Adaptation 9-Apr-15 8-May-15 9-Apr-15 8-May-15
250.2.1.2 Design Work 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.3 Main Building 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.3.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.3.2 Design Approval 19-May-15 11-Jul-15 19-May-15 11-Jul-15
250.2.1.2.1 Barracks 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.1.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.1.2 Design Approval 19-May-15 11-Jul-15 19-May-15 11-Jul-15

Page 1 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.2.1.2.2 Electricity room 9-May-15 9-Jul-15 9-May-15 9-Jul-15


250.2.1.2.2.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.2.2 Design Approval 19-May-15 9-Jul-15 19-May-15 9-Jul-15
250.2.1.2.4 Mosque 9-May-15 9-Jul-15 9-May-15 9-Jul-15
250.2.1.2.4.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.4.2 Design Approval 19-May-15 9-Jul-15 19-May-15 9-Jul-15
250.2.1.2.5 Ware house 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.5.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.5.2 Design Approval 19-May-15 11-Jul-15 19-May-15 11-Jul-15
250.2.1.2.8 Main Entrance 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.8.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.8.2 Design Approval 19-May-15 11-Jul-15 19-May-15 11-Jul-15
250.2.1.2.6 Kiosk 9-May-15 11-Jul-15 9-May-15 11-Jul-15
250.2.1.2.6.1 Design Submittal 9-May-15 29-Jun-15 9-May-15 29-Jun-15
250.2.1.2.6.2 Design Approval 19-May-15 11-Jul-15 19-May-15 11-Jul-15
250.20 Mobilization Works 9-May-15 7-Jul-15 9-May-15 7-Jul-15
250.20.1 Caravans 9-May-15 28-May-15 9-May-15 28-May-15
250.20.1.5 CONSTRUCTION OF CARAVANS 9-May-15 28-May-15 9-May-15 28-May-15
250.20.4 Intial Manpower and Equipment Mobilization 9-May-15 28-May-15 9-May-15 28-May-15
250.20.6 Outer Fence 29-May-15 17-Jun-15 29-May-15 17-Jun-15
250.20.6.5 CONSTRUCTION OF FENCE 29-May-15 17-Jun-15 29-May-15 17-Jun-15
250.20.2 Sign Board 18-Jun-15 7-Jul-15 18-Jun-15 7-Jul-15
250.20.2.5 CONSTRUCTION OF SIGN BOARD 18-Jun-15 7-Jul-15 18-Jun-15 7-Jul-15
250.20.3 Soil Investigation 9-May-15 16-May-15 9-May-15 16-May-15
250.3 Shop Drawings 12-Jul-15 2-Apr-16 12-Jul-15 2-Apr-16
250.3.4 Shop Drawings Submittal 12-Jul-15 16-Mar-16 12-Jul-15 16-Mar-16
250.3.4.6 Site Plan 27-Oct-15 30-Nov-15 27-Oct-15 30-Nov-15
250.3.4.6.2 SURVEY & SITE LEVELLING 27-Oct-15 2-Nov-15 27-Oct-15 2-Nov-15
250.3.4.6.3 INFRASTRUCTURES & NEWWORKS 3-Nov-15 9-Nov-15 3-Nov-15 9-Nov-15

Page 2 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.4.6.4 PAVEMENT & ROAD WORKS 10-Nov-15 16-Nov-15 10-Nov-15 16-Nov-15


250.3.4.6.5 BOUNDARY WALL 17-Nov-15 23-Nov-15 17-Nov-15 23-Nov-15
250.3.4.6.6 LANDSCAPE 24-Nov-15 30-Nov-15 24-Nov-15 30-Nov-15
250.3.4.7 Architectural 12-Jul-15 12-Mar-16 12-Jul-15 12-Mar-16
250.3.4.7.1 Main Building 12-Jul-15 26-Oct-15 12-Jul-15 26-Oct-15
250.3.4.7.1.2 Ground floor 12-Jul-15 18-Aug-15 12-Jul-15 18-Aug-15
250.3.4.7.1.3 First floor 19-Aug-15 22-Sep-15 19-Aug-15 22-Sep-15
250.3.4.7.1.5 Roof 24-Sep-15 12-Oct-15 24-Sep-15 12-Oct-15
250.3.4.7.1.4 Elevation 13-Oct-15 26-Oct-15 13-Oct-15 26-Oct-15
250.3.4.7.2 Barracks 27-Oct-15 6-Dec-15 27-Oct-15 6-Dec-15
250.3.4.7.2.2 Ground floor 27-Oct-15 24-Nov-15 27-Oct-15 24-Nov-15
250.3.4.7.2.7 Roof 25-Nov-15 30-Nov-15 25-Nov-15 30-Nov-15
250.3.4.7.2.4 Elevation 1-Dec-15 6-Dec-15 1-Dec-15 6-Dec-15
250.3.4.7.3 Electricity room 25-Jan-16 10-Feb-16 25-Jan-16 10-Feb-16
250.3.4.7.3.2 Ground floor 25-Jan-16 7-Feb-16 25-Jan-16 7-Feb-16
250.3.4.7.3.4 Elevation 8-Feb-16 10-Feb-16 8-Feb-16 10-Feb-16
250.3.4.7.4 Mosque 7-Dec-15 30-Dec-15 7-Dec-15 30-Dec-15
250.3.4.7.4.2 Ground floor 7-Dec-15 23-Dec-15 7-Dec-15 23-Dec-15
250.3.4.7.4.3 Roof 24-Dec-15 27-Dec-15 24-Dec-15 27-Dec-15
250.3.4.7.4.4 Elevation 28-Dec-15 30-Dec-15 28-Dec-15 30-Dec-15
250.3.4.7.5 Ware house 31-Dec-15 24-Jan-16 31-Dec-15 24-Jan-16
250.3.4.7.5.2 Ground floor 31-Dec-15 17-Jan-16 31-Dec-15 17-Jan-16
250.3.4.7.5.3 Roof 18-Jan-16 20-Jan-16 18-Jan-16 20-Jan-16
250.3.4.7.5.4 Elevation 21-Jan-16 24-Jan-16 21-Jan-16 24-Jan-16
250.3.4.7.8 Main Entrance 11-Feb-16 9-Mar-16 11-Feb-16 9-Mar-16
250.3.4.7.8.2 Ground floor 11-Feb-16 28-Feb-16 11-Feb-16 28-Feb-16
250.3.4.7.8.3 Roof 29-Feb-16 2-Mar-16 29-Feb-16 2-Mar-16
250.3.4.7.8.4 Elevation 3-Mar-16 9-Mar-16 3-Mar-16 9-Mar-16
250.3.4.7.6 Kiosk 10-Mar-16 12-Mar-16 10-Mar-16 12-Mar-16

Page 3 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.4.7.6.2 Ground floor 10-Mar-16 12-Mar-16 10-Mar-16 12-Mar-16


250.3.4.1 Structural 12-Jul-15 1-Sep-15 12-Jul-15 1-Sep-15
250.3.4.1.1 Main Building 12-Jul-15 1-Sep-15 12-Jul-15 1-Sep-15
250.3.4.1.1.1 Foundation 12-Jul-15 18-Jul-15 12-Jul-15 18-Jul-15
250.3.4.1.1.2 Ground floor 22-Jul-15 4-Aug-15 22-Jul-15 4-Aug-15
250.3.4.1.1.3 First floor 5-Aug-15 18-Aug-15 5-Aug-15 18-Aug-15
250.3.4.1.1.5 Roof 19-Aug-15 1-Sep-15 19-Aug-15 1-Sep-15
250.3.4.1.2 Barracks 22-Jul-15 8-Aug-15 22-Jul-15 8-Aug-15
250.3.4.1.2.1 Foundation 22-Jul-15 27-Jul-15 22-Jul-15 27-Jul-15
250.3.4.1.2.2 Ground floor 28-Jul-15 8-Aug-15 28-Jul-15 8-Aug-15
250.3.4.1.3 Electricity room 22-Jul-15 1-Aug-15 22-Jul-15 1-Aug-15
250.3.4.1.3.1 Foundation 22-Jul-15 25-Jul-15 22-Jul-15 25-Jul-15
250.3.4.1.3.2 Ground floor 26-Jul-15 1-Aug-15 26-Jul-15 1-Aug-15
250.3.4.1.4 Mosque 12-Jul-15 25-Jul-15 12-Jul-15 25-Jul-15
250.3.4.1.4.1 Foundation 12-Jul-15 14-Jul-15 12-Jul-15 14-Jul-15
250.3.4.1.4.2 Ground floor 15-Jul-15 25-Jul-15 15-Jul-15 25-Jul-15
250.3.4.1.5 Ware house 22-Jul-15 1-Aug-15 22-Jul-15 1-Aug-15
250.3.4.1.5.1 Foundation 22-Jul-15 25-Jul-15 22-Jul-15 25-Jul-15
250.3.4.1.5.2 Ground floor 26-Jul-15 1-Aug-15 26-Jul-15 1-Aug-15
250.3.4.1.8 Main Entrance 22-Jul-15 1-Aug-15 22-Jul-15 1-Aug-15
250.3.4.1.8.1 Foundation 22-Jul-15 25-Jul-15 22-Jul-15 25-Jul-15
250.3.4.1.8.2 Ground floor 26-Jul-15 1-Aug-15 26-Jul-15 1-Aug-15
250.3.4.1.6 Kiosk 2-Aug-15 8-Aug-15 2-Aug-15 8-Aug-15
250.3.4.1.6.1 Foundation 2-Aug-15 5-Aug-15 2-Aug-15 5-Aug-15
250.3.4.1.6.2 Ground floor 6-Aug-15 8-Aug-15 6-Aug-15 8-Aug-15
250.3.4.2 Electrical 2-Sep-15 14-Mar-16 2-Sep-15 14-Mar-16
250.3.4.2.1 Main Building 2-Sep-15 15-Sep-15 2-Sep-15 15-Sep-15
250.3.4.2.1.2 Ground floor 2-Sep-15 8-Sep-15 2-Sep-15 8-Sep-15
250.3.4.2.1.3 First floor 9-Sep-15 15-Sep-15 9-Sep-15 15-Sep-15

Page 4 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.4.2.2 Barracks 16-Sep-15 21-Sep-15 16-Sep-15 21-Sep-15


250.3.4.2.2.2 Ground floor 16-Sep-15 21-Sep-15 16-Sep-15 21-Sep-15
250.3.4.2.3 Electricity room 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.2.3.2 Ground floor 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.2.4 Mosque 22-Sep-15 1-Oct-15 22-Sep-15 1-Oct-15
250.3.4.2.4.2 Ground floor 22-Sep-15 1-Oct-15 22-Sep-15 1-Oct-15
250.3.4.2.5 Ware house 3-Oct-15 6-Oct-15 3-Oct-15 6-Oct-15
250.3.4.2.5.2 Ground floor 3-Oct-15 6-Oct-15 3-Oct-15 6-Oct-15
250.3.4.2.8 Main Enrance 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.2.8.2 Ground floor 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.2.6 Kiosk 13-Mar-16 14-Mar-16 13-Mar-16 14-Mar-16
250.3.4.2.6.2 Ground floor 13-Mar-16 14-Mar-16 13-Mar-16 14-Mar-16
250.3.4.8 Mechanical 9-Sep-15 16-Mar-16 9-Sep-15 16-Mar-16
250.3.4.8.4 Plumbing 9-Sep-15 20-Oct-15 9-Sep-15 20-Oct-15
250.3.4.8.4.1 Main Building 9-Sep-15 22-Sep-15 9-Sep-15 22-Sep-15
250.3.4.8.4.1.2 Ground floor 9-Sep-15 15-Sep-15 9-Sep-15 15-Sep-15
250.3.4.8.4.1.3 First floor 16-Sep-15 22-Sep-15 16-Sep-15 22-Sep-15
250.3.4.8.4.2 Barracks 22-Sep-15 3-Oct-15 22-Sep-15 3-Oct-15
250.3.4.8.4.2.2 Ground floor 22-Sep-15 3-Oct-15 22-Sep-15 3-Oct-15
250.3.4.8.4.4 Mosque 3-Oct-15 6-Oct-15 3-Oct-15 6-Oct-15
250.3.4.8.4.4.2 Ground floor 3-Oct-15 6-Oct-15 3-Oct-15 6-Oct-15
250.3.4.8.4.5 Ware house 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.8.4.5.2 Ground floor 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.8.4.7 Main entrance 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.4.7.2 Ground floor 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.3 Fire fighting 16-Sep-15 25-Oct-15 16-Sep-15 25-Oct-15
250.3.4.8.3.1 Main Building 16-Sep-15 5-Oct-15 16-Sep-15 5-Oct-15
250.3.4.8.3.1.2 Ground floor 16-Sep-15 22-Sep-15 16-Sep-15 22-Sep-15
250.3.4.8.3.1.3 First floor 24-Sep-15 5-Oct-15 24-Sep-15 5-Oct-15

Page 5 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.4.8.3.2 Barracks 4-Oct-15 8-Oct-15 4-Oct-15 8-Oct-15


250.3.4.8.3.2.2 Ground floor 4-Oct-15 8-Oct-15 4-Oct-15 8-Oct-15
250.3.4.8.3.3 Electricity room 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.3.3.2 Ground floor 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.3.4 Mosque 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.8.3.4.2 Ground floor 7-Oct-15 11-Oct-15 7-Oct-15 11-Oct-15
250.3.4.8.3.5 Ware house 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.3.5.2 Ground floor 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.3.7 Main Entrance 21-Oct-15 25-Oct-15 21-Oct-15 25-Oct-15
250.3.4.8.3.7.2 Ground floor 21-Oct-15 25-Oct-15 21-Oct-15 25-Oct-15
250.3.4.8.5 HVAC 24-Sep-15 16-Mar-16 24-Sep-15 16-Mar-16
250.3.4.8.5.1 Main Building 24-Sep-15 12-Oct-15 24-Sep-15 12-Oct-15
250.3.4.8.5.1.2 Ground floor 24-Sep-15 5-Oct-15 24-Sep-15 5-Oct-15
250.3.4.8.5.1.3 First floor 6-Oct-15 12-Oct-15 6-Oct-15 12-Oct-15
250.3.4.8.5.2 Barracks 10-Oct-15 14-Oct-15 10-Oct-15 14-Oct-15
250.3.4.8.5.2.2 Ground floor 10-Oct-15 14-Oct-15 10-Oct-15 14-Oct-15
250.3.4.8.5.3 Electricity room 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.5.3.2 Ground floor 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.5.4 Mosque 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.5.4.2 Ground floor 12-Oct-15 15-Oct-15 12-Oct-15 15-Oct-15
250.3.4.8.5.5 Ware house 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.5.5.2 Ground floor 17-Oct-15 20-Oct-15 17-Oct-15 20-Oct-15
250.3.4.8.5.8 Main Entrance 26-Oct-15 29-Oct-15 26-Oct-15 29-Oct-15
250.3.4.8.5.8.2 Ground floor 26-Oct-15 29-Oct-15 26-Oct-15 29-Oct-15
250.3.4.8.5.6 Kiosk 15-Mar-16 16-Mar-16 15-Mar-16 16-Mar-16
250.3.4.8.5.6.2 Ground floor 15-Mar-16 16-Mar-16 15-Mar-16 16-Mar-16
250.3.1 Shop Drawings Approval 15-Jul-15 2-Apr-16 15-Jul-15 2-Apr-16
250.3.1.6 Site Plan 3-Nov-15 16-Dec-15 3-Nov-15 16-Dec-15
250.3.1.6.2 SURVEY & SITE LEVELLING 3-Nov-15 18-Nov-15 3-Nov-15 18-Nov-15

Page 6 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.1.6.3 INFRASTRUCTURES & NEWWORKS 10-Nov-15 25-Nov-15 10-Nov-15 25-Nov-15


250.3.1.6.4 PAVEMENT & ROAD WORKS 17-Nov-15 2-Dec-15 17-Nov-15 2-Dec-15
250.3.1.6.5 BOUNDARY WALL 24-Nov-15 9-Dec-15 24-Nov-15 9-Dec-15
250.3.1.6.6 LANDSCAPE 1-Dec-15 16-Dec-15 1-Dec-15 16-Dec-15
250.3.1.7 Architectural 22-Jul-15 28-Mar-16 22-Jul-15 28-Mar-16
250.3.1.7.1 Main Building 22-Jul-15 11-Nov-15 22-Jul-15 11-Nov-15
250.3.1.7.1.2 Ground floor 22-Jul-15 3-Sep-15 22-Jul-15 3-Sep-15
250.3.1.7.1.3 First floor 26-Aug-15 14-Oct-15 26-Aug-15 14-Oct-15
250.3.1.7.1.5 Roof 6-Oct-15 28-Oct-15 6-Oct-15 28-Oct-15
250.3.1.7.1.4 Elevation 20-Oct-15 11-Nov-15 20-Oct-15 11-Nov-15
250.3.1.7.2 Barracks 2-Nov-15 22-Dec-15 2-Nov-15 22-Dec-15
250.3.1.7.2.2 Ground floor 2-Nov-15 10-Dec-15 2-Nov-15 10-Dec-15
250.3.1.7.2.7 Roof 1-Dec-15 16-Dec-15 1-Dec-15 16-Dec-15
250.3.1.7.2.4 Elevation 7-Dec-15 22-Dec-15 7-Dec-15 22-Dec-15
250.3.1.7.3 Electricity room 28-Jan-16 27-Feb-16 28-Jan-16 27-Feb-16
250.3.1.7.3.2 Ground floor 28-Jan-16 23-Feb-16 28-Jan-16 23-Feb-16
250.3.1.7.3.4 Elevation 11-Feb-16 27-Feb-16 11-Feb-16 27-Feb-16
250.3.1.7.4 Mosque 10-Dec-15 16-Jan-16 10-Dec-15 16-Jan-16
250.3.1.7.4.2 Ground floor 10-Dec-15 9-Jan-16 10-Dec-15 9-Jan-16
250.3.1.7.4.3 Roof 28-Dec-15 12-Jan-16 28-Dec-15 12-Jan-16
250.3.1.7.4.4 Elevation 31-Dec-15 16-Jan-16 31-Dec-15 16-Jan-16
250.3.1.7.5 Ware house 4-Jan-16 9-Feb-16 4-Jan-16 9-Feb-16
250.3.1.7.5.2 Ground floor 4-Jan-16 2-Feb-16 4-Jan-16 2-Feb-16
250.3.1.7.5.3 Roof 21-Jan-16 6-Feb-16 21-Jan-16 6-Feb-16
250.3.1.7.5.4 Elevation 25-Jan-16 9-Feb-16 25-Jan-16 9-Feb-16
250.3.1.7.8 Main Entrance 15-Feb-16 26-Mar-16 15-Feb-16 26-Mar-16
250.3.1.7.8.2 Ground floor 15-Feb-16 15-Mar-16 15-Feb-16 15-Mar-16
250.3.1.7.8.3 Roof 3-Mar-16 19-Mar-16 3-Mar-16 19-Mar-16
250.3.1.7.8.4 Elevation 7-Mar-16 26-Mar-16 7-Mar-16 26-Mar-16

Page 7 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.1.7.6 Kiosk 13-Mar-16 28-Mar-16 13-Mar-16 28-Mar-16


250.3.1.7.6.2 Ground floor 13-Mar-16 28-Mar-16 13-Mar-16 28-Mar-16
250.3.1.1 Structural 15-Jul-15 17-Sep-15 15-Jul-15 17-Sep-15
250.3.1.1.1 Main Building 22-Jul-15 17-Sep-15 22-Jul-15 17-Sep-15
250.3.1.1.1.1 Foundation 22-Jul-15 6-Aug-15 22-Jul-15 6-Aug-15
250.3.1.1.1.2 Ground floor 29-Jul-15 20-Aug-15 29-Jul-15 20-Aug-15
250.3.1.1.1.3 First floor 12-Aug-15 3-Sep-15 12-Aug-15 3-Sep-15
250.3.1.1.1.5 Roof 26-Aug-15 17-Sep-15 26-Aug-15 17-Sep-15
250.3.1.1.2 Barracks 28-Jul-15 24-Aug-15 28-Jul-15 24-Aug-15
250.3.1.1.2.1 Foundation 28-Jul-15 12-Aug-15 28-Jul-15 12-Aug-15
250.3.1.1.2.2 Ground floor 3-Aug-15 24-Aug-15 3-Aug-15 24-Aug-15
250.3.1.1.3 Electricity room 26-Jul-15 17-Aug-15 26-Jul-15 17-Aug-15
250.3.1.1.3.1 Foundation 26-Jul-15 10-Aug-15 26-Jul-15 10-Aug-15
250.3.1.1.3.2 Ground floor 29-Jul-15 17-Aug-15 29-Jul-15 17-Aug-15
250.3.1.1.4 Mosque 15-Jul-15 10-Aug-15 15-Jul-15 10-Aug-15
250.3.1.1.4.1 Foundation 15-Jul-15 3-Aug-15 15-Jul-15 3-Aug-15
250.3.1.1.4.2 Ground floor 22-Jul-15 10-Aug-15 22-Jul-15 10-Aug-15
250.3.1.1.5 Ware house 26-Jul-15 17-Aug-15 26-Jul-15 17-Aug-15
250.3.1.1.5.1 Foundation 26-Jul-15 10-Aug-15 26-Jul-15 10-Aug-15
250.3.1.1.5.2 Ground floor 29-Jul-15 17-Aug-15 29-Jul-15 17-Aug-15
250.3.1.1.8 Main Entrance 26-Jul-15 17-Aug-15 26-Jul-15 17-Aug-15
250.3.1.1.8.1 Foundation 26-Jul-15 10-Aug-15 26-Jul-15 10-Aug-15
250.3.1.1.8.2 Ground floor 29-Jul-15 17-Aug-15 29-Jul-15 17-Aug-15
250.3.1.1.6 Kiosk 4-Aug-15 24-Aug-15 4-Aug-15 24-Aug-15
250.3.1.1.6.1 Foundation 4-Aug-15 22-Aug-15 4-Aug-15 22-Aug-15
250.3.1.1.6.2 Ground floor 9-Aug-15 24-Aug-15 9-Aug-15 24-Aug-15
250.3.1.2 Electrical 9-Sep-15 30-Mar-16 9-Sep-15 30-Mar-16
250.3.1.2.1 Main Building 9-Sep-15 7-Oct-15 9-Sep-15 7-Oct-15
250.3.1.2.1.2 Ground floor 9-Sep-15 30-Sep-15 9-Sep-15 30-Sep-15

Page 8 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.1.2.1.3 First floor 16-Sep-15 7-Oct-15 16-Sep-15 7-Oct-15


250.3.1.2.2 Barracks 22-Sep-15 13-Oct-15 22-Sep-15 13-Oct-15
250.3.1.2.2.2 Ground floor 22-Sep-15 13-Oct-15 22-Sep-15 13-Oct-15
250.3.1.2.3 Electricity room 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.2.3.2 Ground floor 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.2.4 Mosque 3-Oct-15 18-Oct-15 3-Oct-15 18-Oct-15
250.3.1.2.4.2 Ground floor 3-Oct-15 18-Oct-15 3-Oct-15 18-Oct-15
250.3.1.2.5 Ware house 7-Oct-15 22-Oct-15 7-Oct-15 22-Oct-15
250.3.1.2.5.2 Ground floor 7-Oct-15 22-Oct-15 7-Oct-15 22-Oct-15
250.3.1.2.8 Main Entrance 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.2.8.2 Ground floor 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.2.6 Kiosk 15-Mar-16 30-Mar-16 15-Mar-16 30-Mar-16
250.3.1.2.6.2 Ground floor 15-Mar-16 30-Mar-16 15-Mar-16 30-Mar-16
250.3.1.8 Mechanical 16-Sep-15 2-Apr-16 16-Sep-15 2-Apr-16
250.3.1.8.4 Plumbing 16-Sep-15 5-Nov-15 16-Sep-15 5-Nov-15
250.3.1.8.4.1 Main Building 16-Sep-15 14-Oct-15 16-Sep-15 14-Oct-15
250.3.1.8.4.1.2 Ground floor 16-Sep-15 7-Oct-15 16-Sep-15 7-Oct-15
250.3.1.8.4.1.3 First floor 24-Sep-15 14-Oct-15 24-Sep-15 14-Oct-15
250.3.1.8.4.2 Barracks 4-Oct-15 19-Oct-15 4-Oct-15 19-Oct-15
250.3.1.8.4.2.2 Ground floor 4-Oct-15 19-Oct-15 4-Oct-15 19-Oct-15
250.3.1.8.4.4 Mosque 7-Oct-15 22-Oct-15 7-Oct-15 22-Oct-15
250.3.1.8.4.4.2 Ground floor 7-Oct-15 22-Oct-15 7-Oct-15 22-Oct-15
250.3.1.8.4.5 Ware house 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.8.4.5.2 Ground floor 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.8.4.7 Main Entrance 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.4.7.2 Ground floor 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.3 Fire fighting 24-Sep-15 10-Nov-15 24-Sep-15 10-Nov-15
250.3.1.8.3.1 Main Building 24-Sep-15 21-Oct-15 24-Sep-15 21-Oct-15
250.3.1.8.3.1.2 Ground floor 24-Sep-15 14-Oct-15 24-Sep-15 14-Oct-15

Page 9 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.3.1.8.3.1.3 First floor 6-Oct-15 21-Oct-15 6-Oct-15 21-Oct-15


250.3.1.8.3.2 Barracks 10-Oct-15 25-Oct-15 10-Oct-15 25-Oct-15
250.3.1.8.3.2.2 Ground floor 10-Oct-15 25-Oct-15 10-Oct-15 25-Oct-15
250.3.1.8.3.3 Electricity room 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.3.3.2 Ground floor 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.3.4 Mosque 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.8.3.4.2 Ground floor 12-Oct-15 27-Oct-15 12-Oct-15 27-Oct-15
250.3.1.8.3.5 Ware house 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.3.5.2 Ground floor 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.3.7 Main Entrance 26-Oct-15 10-Nov-15 26-Oct-15 10-Nov-15
250.3.1.8.3.7.2 Ground floor 26-Oct-15 10-Nov-15 26-Oct-15 10-Nov-15
250.3.1.8.5 HVAC 6-Oct-15 2-Apr-16 6-Oct-15 2-Apr-16
250.3.1.8.5.1 Main Building 6-Oct-15 28-Oct-15 6-Oct-15 28-Oct-15
250.3.1.8.5.1.2 Ground floor 6-Oct-15 21-Oct-15 6-Oct-15 21-Oct-15
250.3.1.8.5.1.3 First floor 13-Oct-15 28-Oct-15 13-Oct-15 28-Oct-15
250.3.1.8.5.2 Barracks 15-Oct-15 31-Oct-15 15-Oct-15 31-Oct-15
250.3.1.8.5.2.2 Ground floor 15-Oct-15 31-Oct-15 15-Oct-15 31-Oct-15
250.3.1.8.5.3 Electricity room 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.5.3.2 Ground floor 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.5.4 Mosque 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.5.4.2 Ground floor 17-Oct-15 1-Nov-15 17-Oct-15 1-Nov-15
250.3.1.8.5.5 Ware house 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.5.5.2 Ground floor 21-Oct-15 5-Nov-15 21-Oct-15 5-Nov-15
250.3.1.8.5.8 Main Entrance 31-Oct-15 15-Nov-15 31-Oct-15 15-Nov-15
250.3.1.8.5.8.2 Ground floor 31-Oct-15 15-Nov-15 31-Oct-15 15-Nov-15
250.3.1.8.5.6 Kiosk 17-Mar-16 2-Apr-16 17-Mar-16 2-Apr-16
250.3.1.8.5.6.2 Ground floor 17-Mar-16 2-Apr-16 17-Mar-16 2-Apr-16
250.4 Procurement 9-May-15 23-Jun-16 9-May-15 23-Jun-16
250.4.2 P.O. 9-May-15 3-Apr-16 9-May-15 3-Apr-16

Page 10 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.4.2.7 Site Plan Materials 26-May-15 3-Apr-16 26-May-15 3-Apr-16


250.4.2.7.10 EARTH MATERIALS 26-May-15 19-Mar-16 26-May-15 19-Mar-16
250.4.2.7.20 DRAINAGE SYSTEM MATERIALS 31-Aug-15 24-Feb-16 31-Aug-15 24-Feb-16
250.4.2.7.60 BOUNDARY WALL MATERIALS 15-Aug-15 30-Aug-15 15-Aug-15 30-Aug-15
250.4.2.7.30 ELECTRICAL MATERIALS 18-Jan-16 22-Mar-16 18-Jan-16 22-Mar-16
250.4.2.7.40 PORTABEL & IRRIGATION SYSTEM MATERIALS 20-Sep-15 31-Dec-15 20-Sep-15 31-Dec-15
250.4.2.7.50 FIRE FIGHTING SYSTEM MATERIALS 19-Dec-15 16-Feb-16 19-Dec-15 16-Feb-16
250.4.2.7.70 PAVEMENT & ROADS MATERIALS 20-Jan-16 22-Mar-16 20-Jan-16 22-Mar-16
250.4.2.7.80 LAND SCAPE MATERIALS 20-Jan-16 3-Apr-16 20-Jan-16 3-Apr-16
250.4.2.1 Buildings Materials 9-May-15 13-Feb-16 9-May-15 13-Feb-16
250.4.2.1.1 CONCRETE MATERIALS 9-May-15 4-Jun-15 9-May-15 4-Jun-15
250.4.2.1.7 Block Works 29-Jul-15 13-Aug-15 29-Jul-15 13-Aug-15
250.4.2.1.8 Metal Fabrications Works 10-Nov-15 9-Feb-16 10-Nov-15 9-Feb-16
250.4.2.1.9 Proofing and insulation Works 16-May-15 2-Jan-16 16-May-15 2-Jan-16
250.4.2.1.2 FINISH MATERIALS 18-Oct-15 13-Feb-16 18-Oct-15 13-Feb-16
250.4.2.1.3 ELECTRICAL MATERIALS 23-Jun-15 7-Jan-16 23-Jun-15 7-Jan-16
250.4.2.1.4 HVAC MATERIALS 18-Oct-15 7-Dec-15 18-Oct-15 7-Dec-15
250.4.2.1.5 PLUMBING MATERIALS 12-Oct-15 6-Dec-15 12-Oct-15 6-Dec-15
250.4.2.1.6 FIRE FIGHTING MATERIALS 27-Jul-15 12-Oct-15 27-Jul-15 12-Oct-15
250.4.3 Start of Delivery 25-May-15 23-Jun-16 25-May-15 23-Jun-16
250.4.3.7 Site Plan Materials 11-Jun-15 23-Jun-16 11-Jun-15 23-Jun-16
250.4.3.7.10 EARTH MATERIALS 11-Jun-15 30-Mar-16 11-Jun-15 30-Mar-16
250.4.3.7.20 DRAINAGE SYSTEM MATERIALS 31-Aug-15 30-Mar-16 31-Aug-15 30-Mar-16
250.4.3.7.60 BOUNDARY WALL MATERIALS 31-Aug-15 27-Oct-15 31-Aug-15 27-Oct-15
250.4.3.7.30 ELECTRICAL MATERIALS 3-Feb-16 31-May-16 3-Feb-16 31-May-16
250.4.3.7.40 PORTABEL & IRRIGATION SYSTEM MATERIALS 12-Oct-15 14-Apr-16 12-Oct-15 14-Apr-16
250.4.3.7.50 FIRE FIGHTING SYSTEM MATERIALS 4-Jan-16 17-Apr-16 4-Jan-16 17-Apr-16
250.4.3.7.70 PAVEMENT & ROADS MATERIALS 6-Feb-16 26-Apr-16 6-Feb-16 26-Apr-16
250.4.3.7.80 LAND SCAPE MATERIALS 6-Feb-16 23-Jun-16 6-Feb-16 23-Jun-16

Page 11 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.4.3.1 Buildings Materials 25-May-15 13-Apr-16 25-May-15 13-Apr-16


250.4.3.1.1 CONCRETE MATERIALS 25-May-15 16-Jun-15 25-May-15 16-Jun-15
250.4.3.1.7 Block Works 15-Aug-15 17-Sep-15 15-Aug-15 17-Sep-15
250.4.3.1.8 Metal Fabrications Works 26-Nov-15 2-Apr-16 26-Nov-15 2-Apr-16
250.4.3.1.9 Proofing and insulation Works 1-Jun-15 19-Jan-16 1-Jun-15 19-Jan-16
250.4.3.1.2 FINISH MATERIALS 3-Nov-15 13-Apr-16 3-Nov-15 13-Apr-16
250.4.3.1.3 ELECTRICAL MATERIALS 9-Jul-15 14-Mar-16 9-Jul-15 14-Mar-16
250.4.3.1.4 HVAC MATERIALS 28-Oct-15 13-Jan-16 28-Oct-15 13-Jan-16
250.4.3.1.5 PLUMBING MATERIALS 28-Oct-15 10-Feb-16 28-Oct-15 10-Feb-16
250.4.3.1.6 FIRE FIGHTING MATERIALS 12-Aug-15 3-Dec-15 12-Aug-15 3-Dec-15
250.5 Construction 9-May-15 12-Feb-17 9-May-15 12-Feb-17
250.5.02 Division2-Site Works 12-Jul-15 30-Aug-16 12-Jul-15 30-Aug-16
250.5.02.1 Main Building 12-Jul-15 10-Oct-15 12-Jul-15 10-Oct-15
250.5.02.5 Barracks 27-Jul-15 30-Sep-15 27-Jul-15 30-Sep-15
250.5.02.2 Electricity room 5-Aug-15 3-Oct-15 5-Aug-15 3-Oct-15
250.5.02.3 Mosque 1-Aug-15 3-Oct-15 1-Aug-15 3-Oct-15
250.5.02.4 Ware house 16-Jul-15 31-Oct-15 16-Jul-15 31-Oct-15
250.5.02.8 Main Entrance 9-Aug-15 7-Oct-15 9-Aug-15 7-Oct-15
250.5.02.6 Kiosk 7-Aug-16 30-Aug-16 7-Aug-16 30-Aug-16
250.5.03 Division3-Concrete 22-Jul-15 18-Sep-16 22-Jul-15 18-Sep-16
250.5.03.1 Main Building 22-Jul-15 14-Mar-16 22-Jul-15 14-Mar-16
250.5.03.1.3 Sub structure 22-Jul-15 18-Nov-15 22-Jul-15 18-Nov-15
250.5.03.1.3.1 Foundation 22-Jul-15 18-Nov-15 22-Jul-15 18-Nov-15
250.5.03.1.2 Super structure 19-Nov-15 14-Mar-16 19-Nov-15 14-Mar-16
250.5.03.1.2.1 Ground floor 19-Nov-15 14-Dec-15 19-Nov-15 14-Dec-15
250.5.03.1.2.2 First floor 15-Dec-15 24-Jan-16 15-Dec-15 24-Jan-16
250.5.03.1.2.3 Roof 25-Jan-16 14-Mar-16 25-Jan-16 14-Mar-16
250.5.03.5 Barracks 2-Aug-15 22-Jun-16 2-Aug-15 22-Jun-16
250.5.03.5.1 Sub structure 2-Aug-15 12-Oct-15 2-Aug-15 12-Oct-15

Page 12 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.03.5.1.1 Foundation 2-Aug-15 12-Oct-15 2-Aug-15 12-Oct-15


250.5.03.5.2 Super structure 2-Apr-16 22-Jun-16 2-Apr-16 22-Jun-16
250.5.03.5.2.1 Ground floor 2-Apr-16 18-Apr-16 2-Apr-16 18-Apr-16
250.5.03.5.2.2 Roof 18-Jun-16 22-Jun-16 18-Jun-16 22-Jun-16
250.5.03.2 Electricity room 10-Aug-15 23-Jul-16 10-Aug-15 23-Jul-16
250.5.03.2.1 Sub structure 10-Aug-15 13-Oct-15 10-Aug-15 13-Oct-15
250.5.03.2.1.1 Foundation 10-Aug-15 13-Oct-15 10-Aug-15 13-Oct-15
250.5.03.2.2 Super structure 7-Jun-16 23-Jul-16 7-Jun-16 23-Jul-16
250.5.03.2.2.1 Ground floor 7-Jun-16 19-Jun-16 7-Jun-16 19-Jun-16
250.5.03.2.2.2 Roof 18-Jul-16 23-Jul-16 18-Jul-16 23-Jul-16
250.5.03.3 Mosque 6-Aug-15 23-Jul-16 6-Aug-15 23-Jul-16
250.5.03.3.1 Sub structure 6-Aug-15 12-Oct-15 6-Aug-15 12-Oct-15
250.5.03.3.1.1 Foundation 6-Aug-15 12-Oct-15 6-Aug-15 12-Oct-15
250.5.03.3.2 Super structure 5-May-16 23-Jul-16 5-May-16 23-Jul-16
250.5.03.3.2.1 Ground floor 5-May-16 21-May-16 5-May-16 21-May-16
250.5.03.3.2.2 Roof 18-Jul-16 23-Jul-16 18-Jul-16 23-Jul-16
250.5.03.4 Ware house 29-Jul-15 22-Jun-16 29-Jul-15 22-Jun-16
250.5.03.4.1 Sub structure 29-Jul-15 18-Nov-15 29-Jul-15 18-Nov-15
250.5.03.4.1.1 Foundation 29-Jul-15 18-Nov-15 29-Jul-15 18-Nov-15
250.5.03.4.2 Super structure 24-Feb-16 22-Jun-16 24-Feb-16 22-Jun-16
250.5.03.4.2.1 Ground floor 24-Feb-16 31-Mar-16 24-Feb-16 31-Mar-16
250.5.03.4.2.2 Roof 18-Jun-16 22-Jun-16 18-Jun-16 22-Jun-16
250.5.03.8 Main Entrance 13-Aug-15 18-Sep-16 13-Aug-15 18-Sep-16
250.5.03.8.1 Sub structure 13-Aug-15 15-Oct-15 13-Aug-15 15-Oct-15
250.5.03.8.1.1 Foundation 13-Aug-15 15-Oct-15 13-Aug-15 15-Oct-15
250.5.03.8.2 Super structure 6-Jul-16 18-Sep-16 6-Jul-16 18-Sep-16
250.5.03.8.2.1 Ground floor 6-Jul-16 18-Jul-16 6-Jul-16 18-Jul-16
250.5.03.8.2.2 Roof 13-Sep-16 18-Sep-16 13-Sep-16 18-Sep-16
250.5.03.6 Kiosk 10-Aug-16 7-Sep-16 10-Aug-16 7-Sep-16

Page 13 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.03.6.1 Sub structure 10-Aug-16 21-Aug-16 10-Aug-16 21-Aug-16


250.5.03.6.1.1 Foundation 10-Aug-16 21-Aug-16 10-Aug-16 21-Aug-16
250.5.03.6.2 Super structure 1-Sep-16 7-Sep-16 1-Sep-16 7-Sep-16
250.5.03.6.2.1 Ground floor 1-Sep-16 7-Sep-16 1-Sep-16 7-Sep-16
250.5.04 Division4-Masonry 9-Jan-16 12-Sep-16 9-Jan-16 12-Sep-16
250.5.04.1 Main Building 9-Jan-16 8-Mar-16 9-Jan-16 8-Mar-16
250.5.04.1.2 Super structure 9-Jan-16 8-Mar-16 9-Jan-16 8-Mar-16
250.5.04.1.2.1 Ground floor 9-Jan-16 17-Jan-16 9-Jan-16 17-Jan-16
250.5.04.1.2.2 First floor 18-Feb-16 27-Feb-16 18-Feb-16 27-Feb-16
250.5.04.1.2.3 Roof 3-Mar-16 8-Mar-16 3-Mar-16 8-Mar-16
250.5.04.5 Barracks 14-May-16 16-Jun-16 14-May-16 16-Jun-16
250.5.04.5.2 Super structure 14-May-16 16-Jun-16 14-May-16 16-Jun-16
250.5.04.5.2.1 Ground floor 14-May-16 19-May-16 14-May-16 19-May-16
250.5.04.5.2.2 Roof 14-Jun-16 16-Jun-16 14-Jun-16 16-Jun-16
250.5.04.2 Electricity room 14-Jul-16 17-Jul-16 14-Jul-16 17-Jul-16
250.5.04.2.2 Super structure 14-Jul-16 17-Jul-16 14-Jul-16 17-Jul-16
250.5.04.2.2.1 Ground floor 14-Jul-16 17-Jul-16 14-Jul-16 17-Jul-16
250.5.04.3 Mosque 15-Jun-16 17-Jul-16 15-Jun-16 17-Jul-16
250.5.04.3.2 Super structure 15-Jun-16 17-Jul-16 15-Jun-16 17-Jul-16
250.5.04.3.2.1 Ground floor 15-Jun-16 19-Jun-16 15-Jun-16 19-Jun-16
250.5.04.3.2.2 Roof 14-Jul-16 17-Jul-16 14-Jul-16 17-Jul-16
250.5.04.4 Ware house 26-Apr-16 16-Jun-16 26-Apr-16 16-Jun-16
250.5.04.4.2 Super structure 26-Apr-16 16-Jun-16 26-Apr-16 16-Jun-16
250.5.04.4.2.1 Ground floor 26-Apr-16 16-May-16 26-Apr-16 16-May-16
250.5.04.4.2.2 Roof 11-Jun-16 16-Jun-16 11-Jun-16 16-Jun-16
250.5.04.7 Main Entrance 13-Aug-16 12-Sep-16 13-Aug-16 12-Sep-16
250.5.04.7.2 Super structure 13-Aug-16 12-Sep-16 13-Aug-16 12-Sep-16
250.5.04.7.2.1 Ground floor 13-Aug-16 16-Aug-16 13-Aug-16 16-Aug-16
250.5.04.7.2.2 Roof 11-Sep-16 12-Sep-16 11-Sep-16 12-Sep-16

Page 14 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.05 Division5-Metals 10-Mar-16 5-Oct-16 10-Mar-16 5-Oct-16


250.5.05.1 Main Building 10-Mar-16 15-May-16 10-Mar-16 15-May-16
250.5.05.1.2 Super structure 10-Mar-16 15-May-16 10-Mar-16 15-May-16
250.5.05.1.2.1 Ground floor 10-Mar-16 3-Apr-16 10-Mar-16 3-Apr-16
250.5.05.1.2.2 First floor 20-Apr-16 15-May-16 20-Apr-16 15-May-16
250.5.05.1.2.3 Roof 16-Apr-16 18-Apr-16 16-Apr-16 18-Apr-16
250.5.05.5 Barracks 3-Jul-16 27-Jul-16 3-Jul-16 27-Jul-16
250.5.05.5.2 Super structure 3-Jul-16 27-Jul-16 3-Jul-16 27-Jul-16
250.5.05.5.2.1 Ground floor 3-Jul-16 21-Jul-16 3-Jul-16 21-Jul-16
250.5.05.5.2.2 Roof 25-Jul-16 27-Jul-16 25-Jul-16 27-Jul-16
250.5.05.2 Electricity room 20-Aug-16 24-Aug-16 20-Aug-16 24-Aug-16
250.5.05.2.2 Super structure 20-Aug-16 24-Aug-16 20-Aug-16 24-Aug-16
250.5.05.2.2.1 Ground Floor 20-Aug-16 24-Aug-16 20-Aug-16 24-Aug-16
250.5.05.3 Mosque 27-Jul-16 9-Aug-16 27-Jul-16 9-Aug-16
250.5.05.3.2 Super structure 27-Jul-16 9-Aug-16 27-Jul-16 9-Aug-16
250.5.05.3.2.1 Ground floor 27-Jul-16 9-Aug-16 27-Jul-16 9-Aug-16
250.5.05.3.2.2 Roof 7-Aug-16 9-Aug-16 7-Aug-16 9-Aug-16
250.5.05.4 Ware house 31-Jul-16 10-Sep-16 31-Jul-16 10-Sep-16
250.5.05.4.2 Super structure 31-Jul-16 10-Sep-16 31-Jul-16 10-Sep-16
250.5.05.4.2.1 Ground floor 4-Sep-16 10-Sep-16 4-Sep-16 10-Sep-16
250.5.05.4.2.2 Roof 31-Jul-16 2-Aug-16 31-Jul-16 2-Aug-16
250.5.05.7 Main Entrance 7-Sep-16 5-Oct-16 7-Sep-16 5-Oct-16
250.5.05.7.2 Super structure 7-Sep-16 5-Oct-16 7-Sep-16 5-Oct-16
250.5.05.7.2.1 Ground floor 7-Sep-16 8-Sep-16 7-Sep-16 8-Sep-16
250.5.05.7.2.2 Roof 3-Oct-16 5-Oct-16 3-Oct-16 5-Oct-16
250.5.07 Division7-Thermal & Moisture Protection 20-Aug-15 2-Oct-16 20-Aug-15 2-Oct-16
250.5.07.1 Main Building 20-Aug-15 11-Apr-16 20-Aug-15 11-Apr-16
250.5.07.1.3 Sub structure 20-Aug-15 14-Oct-15 20-Aug-15 14-Oct-15
250.5.07.1.3.1 Foundation 20-Aug-15 14-Oct-15 20-Aug-15 14-Oct-15

Page 15 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.07.1.2 Super structure 12-Jan-16 11-Apr-16 12-Jan-16 11-Apr-16


250.5.07.1.2.1 Ground floor 12-Jan-16 24-Feb-16 12-Jan-16 24-Feb-16
250.5.07.1.2.2 First floor 22-Feb-16 5-Apr-16 22-Feb-16 5-Apr-16
250.5.07.1.2.3 Roof 15-Mar-16 11-Apr-16 15-Mar-16 11-Apr-16
250.5.07.5 Barracks 25-Aug-15 20-Jul-16 25-Aug-15 20-Jul-16
250.5.07.5.1 Sub structure 25-Aug-15 3-Oct-15 25-Aug-15 3-Oct-15
250.5.07.5.1.1 Foundation 25-Aug-15 3-Oct-15 25-Aug-15 3-Oct-15
250.5.07.5.2 Super structure 19-May-16 20-Jul-16 19-May-16 20-Jul-16
250.5.07.5.2.1 Ground floor 19-May-16 16-Jun-16 19-May-16 16-Jun-16
250.5.07.5.2.2 Roof 23-Jun-16 20-Jul-16 23-Jun-16 20-Jul-16
250.5.07.2 Electricity room 3-Sep-15 7-Aug-16 3-Sep-15 7-Aug-16
250.5.07.2.1 Sub structure 3-Sep-15 5-Oct-15 3-Sep-15 5-Oct-15
250.5.07.2.1.1 Foundation 3-Sep-15 5-Oct-15 3-Sep-15 5-Oct-15
250.5.07.2.2 Super structure 18-Jul-16 7-Aug-16 18-Jul-16 7-Aug-16
250.5.07.2.2.1 Ground floor 18-Jul-16 7-Aug-16 18-Jul-16 7-Aug-16
250.5.07.2.2.2 Roof 24-Jul-16 6-Aug-16 24-Jul-16 6-Aug-16
250.5.07.3 Mosque 31-Aug-15 6-Aug-16 31-Aug-15 6-Aug-16
250.5.07.3.1 Sub structure 31-Aug-15 5-Oct-15 31-Aug-15 5-Oct-15
250.5.07.3.1.1 Foundation 31-Aug-15 5-Oct-15 31-Aug-15 5-Oct-15
250.5.07.3.2 Super structure 18-Jun-16 6-Aug-16 18-Jun-16 6-Aug-16
250.5.07.3.2.1 Ground floor 18-Jun-16 20-Jun-16 18-Jun-16 20-Jun-16
250.5.07.3.2.2 Roof 24-Jul-16 6-Aug-16 24-Jul-16 6-Aug-16
250.5.07.4 Ware house 2-Sep-15 30-Jul-16 2-Sep-15 30-Jul-16
250.5.07.4.1 Sub structure 2-Sep-15 4-Nov-15 2-Sep-15 4-Nov-15
250.5.07.4.1.1 Foundation 2-Sep-15 4-Nov-15 2-Sep-15 4-Nov-15
250.5.07.4.2 Super structure 30-Apr-16 30-Jul-16 30-Apr-16 30-Jul-16
250.5.07.4.2.1 Ground floor 30-Apr-16 29-Jun-16 30-Apr-16 29-Jun-16
250.5.07.4.2.2 Roof 23-Jun-16 30-Jul-16 23-Jun-16 30-Jul-16
250.5.07.8 Main Entrance 7-Sep-15 2-Oct-16 7-Sep-15 2-Oct-16

Page 16 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.07.8.1 Sub structure 7-Sep-15 8-Oct-15 7-Sep-15 8-Oct-15


250.5.07.8.1.1 Foundation 7-Sep-15 8-Oct-15 7-Sep-15 8-Oct-15
250.5.07.8.2 Super structure 17-Aug-16 2-Oct-16 17-Aug-16 2-Oct-16
250.5.07.8.2.1 Ground floor 17-Aug-16 31-Aug-16 17-Aug-16 31-Aug-16
250.5.07.8.2.2 Roof 19-Sep-16 2-Oct-16 19-Sep-16 2-Oct-16
250.5.07.6 Kiosk 24-Aug-16 31-Aug-16 24-Aug-16 31-Aug-16
250.5.07.6.1 Substructure 24-Aug-16 31-Aug-16 24-Aug-16 31-Aug-16
250.5.07.6.1.1 Foundation 24-Aug-16 31-Aug-16 24-Aug-16 31-Aug-16
250.5.08 Division8-Doors & Windows 16-Jan-16 26-Sep-16 16-Jan-16 26-Sep-16
250.5.08.1 Main Building 16-Jan-16 26-Jun-16 16-Jan-16 26-Jun-16
250.5.08.1.2 Super structure 16-Jan-16 26-Jun-16 16-Jan-16 26-Jun-16
250.5.08.1.2.1 Ground floor 16-Jan-16 16-Jun-16 16-Jan-16 16-Jun-16
250.5.08.1.2.2 First floor 25-Feb-16 26-Jun-16 25-Feb-16 26-Jun-16
250.5.08.5 Barracks 21-May-16 25-Jul-16 21-May-16 25-Jul-16
250.5.08.5.2 Super structure 21-May-16 25-Jul-16 21-May-16 25-Jul-16
250.5.08.5.2.1 Ground floor 21-May-16 25-Jul-16 21-May-16 25-Jul-16
250.5.08.2 Electricity room 18-Jul-16 30-Aug-16 18-Jul-16 30-Aug-16
250.5.08.2.2 Super structure 18-Jul-16 30-Aug-16 18-Jul-16 30-Aug-16
250.5.08.2.2.1 Ground floor 18-Jul-16 30-Aug-16 18-Jul-16 30-Aug-16
250.5.08.3 Mosque 20-Jun-16 13-Aug-16 20-Jun-16 13-Aug-16
250.5.08.3.2 Super structure 20-Jun-16 13-Aug-16 20-Jun-16 13-Aug-16
250.5.08.3.2.1 Ground floor 20-Jun-16 13-Aug-16 20-Jun-16 13-Aug-16
250.5.08.4 Ware house 12-May-16 26-Sep-16 12-May-16 26-Sep-16
250.5.08.4.2 Super structure 12-May-16 26-Sep-16 12-May-16 26-Sep-16
250.5.08.4.2.1 Ground floor 12-May-16 26-Sep-16 12-May-16 26-Sep-16
250.5.08.7 Main Entrance 17-Aug-16 18-Sep-16 17-Aug-16 18-Sep-16
250.5.08.7.2 Super structure 17-Aug-16 18-Sep-16 17-Aug-16 18-Sep-16
250.5.08.7.2.1 Ground floor 17-Aug-16 18-Sep-16 17-Aug-16 18-Sep-16
250.5.09 Division9-Finishes 1-Feb-16 24-Oct-16 1-Feb-16 24-Oct-16

Page 17 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.09.1 Main Building 1-Feb-16 21-Jun-16 1-Feb-16 21-Jun-16


250.5.09.1.2 Super structure 1-Feb-16 21-Jun-16 1-Feb-16 21-Jun-16
250.5.09.1.2.1 Ground floor 1-Feb-16 26-May-16 1-Feb-16 26-May-16
250.5.09.1.2.2 First floor 13-Mar-16 7-Jun-16 13-Mar-16 7-Jun-16
250.5.09.1.2.3 Roof 19-Apr-16 24-Apr-16 19-Apr-16 24-Apr-16
250.5.09.1.2.4 Elevation 25-Apr-16 21-Jun-16 25-Apr-16 21-Jun-16
250.5.09.5 Barracks 1-Jun-16 20-Aug-16 1-Jun-16 20-Aug-16
250.5.09.5.2 Super structure 1-Jun-16 20-Aug-16 1-Jun-16 20-Aug-16
250.5.09.5.2.1 Ground floor 1-Jun-16 4-Aug-16 1-Jun-16 4-Aug-16
250.5.09.5.2.4 Elevation 28-Jul-16 20-Aug-16 28-Jul-16 20-Aug-16
250.5.09.2 Electricity room 30-Jul-16 17-Sep-16 30-Jul-16 17-Sep-16
250.5.09.2.2 Super structure 30-Jul-16 17-Sep-16 30-Jul-16 17-Sep-16
250.5.09.2.2.1 Ground floor 30-Jul-16 17-Sep-16 30-Jul-16 17-Sep-16
250.5.09.2.2.3 Roof 10-Aug-16 11-Aug-16 10-Aug-16 11-Aug-16
250.5.09.2.2.4 Elevation 13-Aug-16 31-Aug-16 13-Aug-16 31-Aug-16
250.5.09.3 Mosque 27-Jun-16 20-Sep-16 27-Jun-16 20-Sep-16
250.5.09.3.2 Super structure 27-Jun-16 20-Sep-16 27-Jun-16 20-Sep-16
250.5.09.3.2.1 Ground floor 27-Jun-16 16-Aug-16 27-Jun-16 16-Aug-16
250.5.09.3.2.3 Roof 10-Aug-16 10-Aug-16 10-Aug-16 10-Aug-16
250.5.09.3.2.4 Elevation 11-Aug-16 20-Sep-16 11-Aug-16 20-Sep-16
250.5.09.4 Ware house 31-May-16 8-Oct-16 31-May-16 8-Oct-16
250.5.09.4.2 Super structure 31-May-16 8-Oct-16 31-May-16 8-Oct-16
250.5.09.4.2.1 Ground floor 31-May-16 8-Oct-16 31-May-16 8-Oct-16
250.5.09.4.2.3 Roof 3-Aug-16 8-Aug-16 3-Aug-16 8-Aug-16
250.5.09.4.2.4 Elevation 9-Aug-16 25-Sep-16 9-Aug-16 25-Sep-16
250.5.09.8 Main Entrance 24-Aug-16 24-Oct-16 24-Aug-16 24-Oct-16
250.5.09.8.2 Super structure 24-Aug-16 24-Oct-16 24-Aug-16 24-Oct-16
250.5.09.8.2.1 Ground floor 24-Aug-16 24-Sep-16 24-Aug-16 24-Sep-16
250.5.09.8.2.3 Roof 6-Oct-16 8-Oct-16 6-Oct-16 8-Oct-16

Page 18 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.09.8.2.4 Elevation 9-Oct-16 24-Oct-16 9-Oct-16 24-Oct-16


250.5.09.6 Kiosk 20-Sep-16 20-Sep-16 20-Sep-16 20-Sep-16
250.5.09.6.2 Super structure 20-Sep-16 20-Sep-16 20-Sep-16 20-Sep-16
250.5.09.6.2.3 Roof 20-Sep-16 20-Sep-16 20-Sep-16 20-Sep-16
250.5.10 Division10-Specialties 8-Jun-16 19-Oct-16 8-Jun-16 19-Oct-16
250.5.10.1 Main Building 8-Jun-16 21-Jun-16 8-Jun-16 21-Jun-16
250.5.10.1.2 Super structure 8-Jun-16 21-Jun-16 8-Jun-16 21-Jun-16
250.5.10.1.2.1 Ground floor 8-Jun-16 14-Jun-16 8-Jun-16 14-Jun-16
250.5.10.1.2.2 First floor 15-Jun-16 21-Jun-16 15-Jun-16 21-Jun-16
250.5.10.3 Barracks 10-Aug-16 18-Aug-16 10-Aug-16 18-Aug-16
250.5.10.3.2 Super structure 10-Aug-16 18-Aug-16 10-Aug-16 18-Aug-16
250.5.10.3.2.1 Ground floor 10-Aug-16 18-Aug-16 10-Aug-16 18-Aug-16
250.5.10.2 Ware house 13-Oct-16 19-Oct-16 13-Oct-16 19-Oct-16
250.5.10.2.2 Super structure 13-Oct-16 19-Oct-16 13-Oct-16 19-Oct-16
250.5.10.2.2.1 Ground floor 13-Oct-16 19-Oct-16 13-Oct-16 19-Oct-16
250.5.10.6 Main Entrance 28-Sep-16 2-Oct-16 28-Sep-16 2-Oct-16
250.5.10.6.2 Super structure 28-Sep-16 2-Oct-16 28-Sep-16 2-Oct-16
250.5.10.6.2.1 Ground floor 28-Sep-16 2-Oct-16 28-Sep-16 2-Oct-16
250.5.11 Division11-Equipment 8-Jun-16 1-Oct-16 8-Jun-16 1-Oct-16
250.5.11.1 Main Building 8-Jun-16 26-Jun-16 8-Jun-16 26-Jun-16
250.5.11.1.2 Super structure 8-Jun-16 26-Jun-16 8-Jun-16 26-Jun-16
250.5.11.1.2.1 Ground floor 8-Jun-16 16-Jun-16 8-Jun-16 16-Jun-16
250.5.11.1.2.2 First floor 18-Jun-16 26-Jun-16 18-Jun-16 26-Jun-16
250.5.11.5 Barracks 6-Aug-16 16-Aug-16 6-Aug-16 16-Aug-16
250.5.11.5.2 Super structure 6-Aug-16 16-Aug-16 6-Aug-16 16-Aug-16
250.5.11.5.2.1 Ground floor 6-Aug-16 16-Aug-16 6-Aug-16 16-Aug-16
250.5.11.6 Main Entrance 25-Sep-16 1-Oct-16 25-Sep-16 1-Oct-16
250.5.11.6.2 Super structure 25-Sep-16 1-Oct-16 25-Sep-16 1-Oct-16
250.5.11.6.2.1 Ground floor 25-Sep-16 1-Oct-16 25-Sep-16 1-Oct-16

Page 19 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.1 Division12-Furniture 27-Jun-16 31-Oct-16 27-Jun-16 31-Oct-16


250.5.1.1 Main Building 27-Jun-16 31-Jul-16 27-Jun-16 31-Jul-16
250.5.1.1.2 Super structure 27-Jun-16 31-Jul-16 27-Jun-16 31-Jul-16
250.5.1.1.2.1 Ground floor 27-Jun-16 7-Jul-16 27-Jun-16 7-Jul-16
250.5.1.1.2.2 First floor 20-Jul-16 31-Jul-16 20-Jul-16 31-Jul-16
250.5.1.5 Barracks 21-Aug-16 31-Aug-16 21-Aug-16 31-Aug-16
250.5.1.5.2 Super structure 21-Aug-16 31-Aug-16 21-Aug-16 31-Aug-16
250.5.1.5.2.1 Ground floor 21-Aug-16 31-Aug-16 21-Aug-16 31-Aug-16
250.5.1.3 Mosque 21-Sep-16 27-Sep-16 21-Sep-16 27-Sep-16
250.5.1.3.2 Super structure 21-Sep-16 27-Sep-16 21-Sep-16 27-Sep-16
250.5.1.3.2.1 Ground floor 21-Sep-16 27-Sep-16 21-Sep-16 27-Sep-16
250.5.1.4 Ware house 20-Oct-16 31-Oct-16 20-Oct-16 31-Oct-16
250.5.1.4.2 Super structure 20-Oct-16 31-Oct-16 20-Oct-16 31-Oct-16
250.5.1.4.2.1 Ground floor 20-Oct-16 31-Oct-16 20-Oct-16 31-Oct-16
250.5.1.6 Main Entrance 25-Oct-16 31-Oct-16 25-Oct-16 31-Oct-16
250.5.1.6.2 Super structure 25-Oct-16 31-Oct-16 25-Oct-16 31-Oct-16
250.5.1.6.2.1 Ground floor 25-Oct-16 31-Oct-16 25-Oct-16 31-Oct-16
250.5.15 Division15-External Works and Landscaping 9-May-15 12-Feb-17 9-May-15 12-Feb-17
250.5.15.1 Survey & Site Levelling 9-May-15 24-Dec-15 9-May-15 24-Dec-15
250.5.15.2 Infrastructure & Networks 26-Dec-15 12-Feb-17 26-Dec-15 12-Feb-17
250.5.15.2.1 Drainage Networks 6-Jun-16 26-Jul-16 6-Jun-16 26-Jul-16
250.5.15.2.2 Water Supply Networks 6-Jun-16 3-Jul-16 6-Jun-16 3-Jul-16
250.5.15.2.3 Water Wells 26-Dec-15 17-Jan-16 26-Dec-15 17-Jan-16
250.5.15.2.4 Drainage Tank 26-Dec-15 10-Feb-16 26-Dec-15 10-Feb-16
250.5.15.2.5 Water Tank 11-Feb-16 3-Apr-16 11-Feb-16 3-Apr-16
250.5.15.2.8 Water Supply Pumps 27-Jul-16 10-Aug-16 27-Jul-16 10-Aug-16
250.5.15.2.9 RO 4-Apr-16 5-Jun-16 4-Apr-16 5-Jun-16
250.5.15.2.10 Fire Fighting Networks 6-Jun-16 19-Jul-16 6-Jun-16 19-Jul-16
250.5.15.2.10.11 Fire pumps (Electrical) 4-Jul-16 19-Jul-16 4-Jul-16 19-Jul-16

Page 20 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.15.2.14 NOVEC System 6-Jun-16 3-Jul-16 6-Jun-16 3-Jul-16


250.5.15.2.16 Diesel Fuel Tank 4-Apr-16 18-Apr-16 4-Apr-16 18-Apr-16
250.5.15.2.17 GAS-Fuel Sytem 7-Apr-16 23-Apr-16 7-Apr-16 23-Apr-16
250.5.15.2.18 Electrical 16-Jul-16 21-Nov-16 16-Jul-16 21-Nov-16
250.5.15.2.18.2 Power Layout 16-Jul-16 19-Nov-16 16-Jul-16 19-Nov-16
250.5.15.2.18.6 Distribution Board 6-Aug-16 19-Nov-16 6-Aug-16 19-Nov-16
250.5.15.2.18.3 Earthing Layout 6-Aug-16 28-Aug-16 6-Aug-16 28-Aug-16
250.5.15.2.18.5 Lighting Layout 30-Jul-16 21-Nov-16 30-Jul-16 21-Nov-16
250.5.15.2.18.1 Data & Telephone / CCTV / NIC / IPTV,Fire Alarm) 30-Jul-16 19-Nov-16 30-Jul-16 19-Nov-16
250.5.15.2.11 Firing of Electric Current 12-Feb-17 12-Feb-17 12-Feb-17 12-Feb-17
250.5.15.3 Boundary Works 1-Aug-16 31-Dec-16 1-Aug-16 31-Dec-16
250.5.15.3.1 Precast Fence 1-Aug-16 31-Dec-16 1-Aug-16 31-Dec-16
250.5.15.4 Pavement & Road Works 29-Aug-16 1-Jan-17 29-Aug-16 1-Jan-17
250.5.15.5 Landscape Works 15-Oct-16 11-Feb-17 15-Oct-16 11-Feb-17
250.5.16 Division16-Mechanical 30-Jul-15 16-Oct-16 30-Jul-15 16-Oct-16
250.5.16.1 Main Building 30-Jul-15 14-Jun-16 30-Jul-15 14-Jun-16
250.5.16.1.1 Sub Structure 30-Jul-15 4-Aug-15 30-Jul-15 4-Aug-15
250.5.16.1.1.1 Drainage 30-Jul-15 4-Aug-15 30-Jul-15 4-Aug-15
250.5.16.1.7 Super Structure 9-Jan-16 14-Jun-16 9-Jan-16 14-Jun-16
250.5.16.1.7.1 Ground Floor 18-Jan-16 2-Jun-16 18-Jan-16 2-Jun-16
250.5.16.1.7.1.1 Plumbing 18-Jan-16 2-Jun-16 18-Jan-16 2-Jun-16
250.5.16.1.7.1.1.1 Drainage 18-Jan-16 2-Jun-16 18-Jan-16 2-Jun-16
250.5.16.1.7.1.1.2 Water Supply 18-Jan-16 2-Jun-16 18-Jan-16 2-Jun-16
250.5.16.1.7.1.3 HVAC 18-Jan-16 1-Jun-16 18-Jan-16 1-Jun-16
250.5.16.1.7.1.3.1 Concealed A/C Unit 18-Jan-16 1-Jun-16 18-Jan-16 1-Jun-16
250.5.16.1.7.1.3.2 Split Unit 18-Jan-16 31-May-16 18-Jan-16 31-May-16
250.5.16.1.7.1.3.3 Precision Type Unit 18-Jan-16 1-Jun-16 18-Jan-16 1-Jun-16
250.5.16.1.7.1.3.4 Ventlization System 18-Jan-16 17-Apr-16 18-Jan-16 17-Apr-16
250.5.16.1.7.1.2 Fire Fighting 18-Jan-16 6-Apr-16 18-Jan-16 6-Apr-16

Page 21 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.16.1.7.1.2.1 Fire Fighting System 18-Jan-16 6-Apr-16 18-Jan-16 6-Apr-16


250.5.16.1.7.1.2.2 NOVEC System 18-Jan-16 6-Apr-16 18-Jan-16 6-Apr-16
250.5.16.1.7.2 First Floor 28-Feb-16 14-Jun-16 28-Feb-16 14-Jun-16
250.5.16.1.7.2.1 Plumbing 28-Feb-16 14-Jun-16 28-Feb-16 14-Jun-16
250.5.16.1.7.2.1.1 Drainage 28-Feb-16 14-Jun-16 28-Feb-16 14-Jun-16
250.5.16.1.7.2.1.2 Water Supply 28-Feb-16 14-Jun-16 28-Feb-16 14-Jun-16
250.5.16.1.7.2.3 HVAC 28-Feb-16 13-Jun-16 28-Feb-16 13-Jun-16
250.5.16.1.7.2.3.1 Concealed A/C Unit 28-Feb-16 13-Jun-16 28-Feb-16 13-Jun-16
250.5.16.1.7.2.3.2 Split Unit 28-Feb-16 12-Jun-16 28-Feb-16 12-Jun-16
250.5.16.1.7.2.3.3 Precision Type Unit 28-Feb-16 13-Jun-16 28-Feb-16 13-Jun-16
250.5.16.1.7.2.3.4 Ventlization System 28-Feb-16 29-May-16 28-Feb-16 29-May-16
250.5.16.1.7.2.2 Fire Fighting 28-Feb-16 18-May-16 28-Feb-16 18-May-16
250.5.16.1.7.2.2.1 Fire Fighting System 28-Feb-16 18-May-16 28-Feb-16 18-May-16
250.5.16.1.7.2.2.2 NOVEC System 28-Feb-16 18-May-16 28-Feb-16 18-May-16
250.5.16.1.7.3 Roof 9-Jan-16 22-May-16 9-Jan-16 22-May-16
250.5.16.1.7.3.1 Drainage 9-Jan-16 14-Apr-16 9-Jan-16 14-Apr-16
250.5.16.1.7.3.2 HVAC Eqip 22-Mar-16 22-May-16 22-Mar-16 22-May-16
250.5.16.5 Barracks 11-Aug-15 9-Aug-16 11-Aug-15 9-Aug-16
250.5.16.5.1 Sub Structure 11-Aug-15 13-Aug-15 11-Aug-15 13-Aug-15
250.5.16.5.1.1 Drainage 11-Aug-15 13-Aug-15 11-Aug-15 13-Aug-15
250.5.16.5.2 Super structure 7-Apr-16 9-Aug-16 7-Apr-16 9-Aug-16
250.5.16.5.2.1 Ground floor 19-May-16 9-Aug-16 19-May-16 9-Aug-16
250.5.16.5.2.1.1 Plumbing 19-May-16 9-Aug-16 19-May-16 9-Aug-16
250.5.16.5.2.1.1.1 Drainage 19-May-16 9-Aug-16 19-May-16 9-Aug-16
250.5.16.5.2.1.1.2 Water Supply 19-May-16 9-Aug-16 19-May-16 9-Aug-16
250.5.16.5.2.1.3 HVAC 24-May-16 9-Aug-16 24-May-16 9-Aug-16
250.5.16.5.2.1.3.1 Concealed A/C Unit 24-May-16 9-Aug-16 24-May-16 9-Aug-16
250.5.16.5.2.1.3.4 Ventlization System 24-May-16 31-Jul-16 24-May-16 31-Jul-16
250.5.16.5.2.1.2 Fire Fighting 21-May-16 23-Jul-16 21-May-16 23-Jul-16

Page 22 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.16.5.2.1.2.1 Fire Fighting System 21-May-16 23-Jul-16 21-May-16 23-Jul-16


250.5.16.5.2.2 Roof 7-Apr-16 7-Aug-16 7-Apr-16 7-Aug-16
250.5.16.5.2.2.1 Drainage 7-Apr-16 24-Jul-16 7-Apr-16 24-Jul-16
250.5.16.5.2.2.2 HVAC Eqip 30-Jun-16 7-Aug-16 30-Jun-16 7-Aug-16
250.5.16.2 Electricity room 12-Jun-16 11-Sep-16 12-Jun-16 11-Sep-16
250.5.16.2.2 Super structure 12-Jun-16 11-Sep-16 12-Jun-16 11-Sep-16
250.5.16.2.2.1 Ground floor 18-Jul-16 11-Sep-16 18-Jul-16 11-Sep-16
250.5.16.2.2.1.3 Fire Fighting 18-Jul-16 3-Sep-16 18-Jul-16 3-Sep-16
250.5.16.2.2.1.3.1 Fire Fighting System 18-Jul-16 3-Sep-16 18-Jul-16 3-Sep-16
250.5.16.2.2.1.3.2 NOVEC System 18-Jul-16 3-Sep-16 18-Jul-16 3-Sep-16
250.5.16.2.2.1.2 HVAC 18-Jul-16 11-Sep-16 18-Jul-16 11-Sep-16
250.5.16.2.2.1.2.2 Split Unit 18-Jul-16 31-Aug-16 18-Jul-16 31-Aug-16
250.5.16.2.2.1.2.4 Ventlization System 18-Jul-16 11-Sep-16 18-Jul-16 11-Sep-16
250.5.16.2.2.2 Roof 12-Jun-16 22-Aug-16 12-Jun-16 22-Aug-16
250.5.16.2.2.2.1 Drainage 12-Jun-16 9-Aug-16 12-Jun-16 9-Aug-16
250.5.16.2.2.2.2 HVAC Eqip 27-Jul-16 22-Aug-16 27-Jul-16 22-Aug-16
250.5.16.3 Mosque 17-Aug-15 30-Aug-16 17-Aug-15 30-Aug-16
250.5.16.3.1 Sub Structure 17-Aug-15 18-Aug-15 17-Aug-15 18-Aug-15
250.5.16.3.1.1 Drainage 17-Aug-15 18-Aug-15 17-Aug-15 18-Aug-15
250.5.16.3.2 Super structure 11-May-16 30-Aug-16 11-May-16 30-Aug-16
250.5.16.3.2.1 Ground floor 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.16.3.2.1.1 Plumbing 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.16.3.2.1.1.1 Drainage 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.16.3.2.1.3 HVAC 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.16.3.2.1.3.2 Split Unit 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.16.3.2.1.2 Fire Fighting 20-Jun-16 8-Aug-16 20-Jun-16 8-Aug-16
250.5.16.3.2.1.2.1 Fire Fighting System 20-Jun-16 8-Aug-16 20-Jun-16 8-Aug-16
250.5.16.3.2.2 Roof 11-May-16 30-Aug-16 11-May-16 30-Aug-16
250.5.16.3.2.2.1 Drainage 11-May-16 30-Aug-16 11-May-16 30-Aug-16

Page 23 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.16.4 Ware house 9-Aug-15 13-Oct-16 9-Aug-15 13-Oct-16


250.5.16.4.1 Sub Structure 9-Aug-15 10-Aug-15 9-Aug-15 10-Aug-15
250.5.16.4.1.1 Drainage 9-Aug-15 10-Aug-15 9-Aug-15 10-Aug-15
250.5.16.4.2 Super structure 5-Mar-16 13-Oct-16 5-Mar-16 13-Oct-16
250.5.16.4.2.1 Ground floor 30-Apr-16 13-Oct-16 30-Apr-16 13-Oct-16
250.5.16.4.2.1.1 Plumbing 30-Apr-16 12-Oct-16 30-Apr-16 12-Oct-16
250.5.16.4.2.1.1.1 Drainage 30-Apr-16 12-Oct-16 30-Apr-16 12-Oct-16
250.5.16.4.2.1.1.2 Water Supply 17-May-16 12-Oct-16 17-May-16 12-Oct-16
250.5.16.4.2.1.3 HVAC 17-May-16 13-Oct-16 17-May-16 13-Oct-16
250.5.16.4.2.1.3.2 Split Unit 17-May-16 13-Oct-16 17-May-16 13-Oct-16
250.5.16.4.2.1.3.4 Ventlization System 17-May-16 21-Sep-16 17-May-16 21-Sep-16
250.5.16.4.2.1.2 Fire Fighting 17-May-16 10-Sep-16 17-May-16 10-Sep-16
250.5.16.4.2.1.2.1 Fire Fighting System 17-May-16 10-Sep-16 17-May-16 10-Sep-16
250.5.16.4.2.2 Roof 5-Mar-16 25-Aug-16 5-Mar-16 25-Aug-16
250.5.16.4.2.2.1 Drainage 5-Mar-16 25-Aug-16 5-Mar-16 25-Aug-16
250.5.16.8 Main Entrance 27-Aug-15 16-Oct-16 27-Aug-15 16-Oct-16
250.5.16.8.1 Sub Structure 27-Aug-15 29-Aug-15 27-Aug-15 29-Aug-15
250.5.16.8.1.1 Drainage 27-Aug-15 29-Aug-15 27-Aug-15 29-Aug-15
250.5.16.8.2 Super structure 19-Jul-16 16-Oct-16 19-Jul-16 16-Oct-16
250.5.16.8.2.1 Ground floor 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.1 Plumbing 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.1.1 Drainage 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.1.2 Water Supply 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.3 HVAC 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.3.2 Split Unit 17-Aug-16 27-Sep-16 17-Aug-16 27-Sep-16
250.5.16.8.2.1.2 Fire Fighting 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.16.8.2.1.2.1 Fire Fighting System 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.16.8.2.2 Roof 19-Jul-16 16-Oct-16 19-Jul-16 16-Oct-16
250.5.16.8.2.2.1 Drainage 19-Jul-16 16-Oct-16 19-Jul-16 16-Oct-16

Page 24 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.16.6 Kiosk 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16


250.5.16.6.2 Super structure 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.16.6.2.1 Ground floor 8-Sep-16 17-Sep-16 8-Sep-16 17-Sep-16
250.5.16.6.2.1.1 HVAC 8-Sep-16 17-Sep-16 8-Sep-16 17-Sep-16
250.5.16.6.2.1.1.2 Split Unit 8-Sep-16 17-Sep-16 8-Sep-16 17-Sep-16
250.5.16.6.2.2 Roof 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.16.6.2.2.1 Drainage 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.17 Division17-Electrical 10-Aug-15 15-Oct-16 10-Aug-15 15-Oct-16
250.5.17.1 Main Building 10-Aug-15 14-Jun-16 10-Aug-15 14-Jun-16
250.5.17.1.2 Super structure 10-Aug-15 14-Jun-16 10-Aug-15 14-Jun-16
250.5.17.1.2.1 Ground floor 10-Aug-15 5-Jun-16 10-Aug-15 5-Jun-16
250.5.17.1.2.1.2 Power Layout 29-Nov-15 6-Apr-16 29-Nov-15 6-Apr-16
250.5.17.1.2.1.6 Distribution Board 24-Jan-16 2-Jun-16 24-Jan-16 2-Jun-16
250.5.17.1.2.1.4 Lightining Layout 10-Aug-15 24-Feb-16 10-Aug-15 24-Feb-16
250.5.17.1.2.1.3 Earthing Layout 10-Aug-15 24-Feb-16 10-Aug-15 24-Feb-16
250.5.17.1.2.1.5 Lighting Layout 29-Nov-15 5-Jun-16 29-Nov-15 5-Jun-16
250.5.17.1.2.1.1 Data & Telephone / CCTV / NIC / IPTV,Fire Alarm,Security
18-Jan-16
Doors) 2-Jun-16 18-Jan-16 2-Jun-16
250.5.17.1.2.2 First floor 29-Nov-15 14-Jun-16 29-Nov-15 14-Jun-16
250.5.17.1.2.2.2 Power Layout 9-Jan-16 18-May-16 9-Jan-16 18-May-16
250.5.17.1.2.2.6 Distribution Board 5-Mar-16 14-Jun-16 5-Mar-16 14-Jun-16
250.5.17.1.2.2.4 Lightining Layout 29-Nov-15 19-Apr-16 29-Nov-15 19-Apr-16
250.5.17.1.2.2.3 Earthing Layout 29-Nov-15 19-Apr-16 29-Nov-15 19-Apr-16
250.5.17.1.2.2.5 Lighting Layout 9-Jan-16 14-Jun-16 9-Jan-16 14-Jun-16
250.5.17.1.2.2.1 Data & Telephone / CCTV / NIC / IPTV,Fire Alarm,Security
28-Feb-16
Doors) 14-Jun-16 28-Feb-16 14-Jun-16
250.5.17.5 Barracks 17-Aug-15 9-Aug-16 17-Aug-15 9-Aug-16
250.5.17.5.2 Super structure 17-Aug-15 9-Aug-16 17-Aug-15 9-Aug-16
250.5.17.5.2.1 Ground floor 17-Aug-15 9-Aug-16 17-Aug-15 9-Aug-16
250.5.17.5.2.1.2 Power Layout 7-Apr-16 21-Jul-16 7-Apr-16 21-Jul-16
250.5.17.5.2.1.6 Distribution Board 25-May-16 27-Jul-16 25-May-16 27-Jul-16

Page 25 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.17.5.2.1.4 Lightining Layout 17-Aug-15 26-Jun-16 17-Aug-15 26-Jun-16


250.5.17.5.2.1.3 Earthing Layout 17-Aug-15 26-Jun-16 17-Aug-15 26-Jun-16
250.5.17.5.2.1.5 Lighting Layout 7-Apr-16 9-Aug-16 7-Apr-16 9-Aug-16
250.5.17.5.2.1.1 Data & Telephone / CCTV / NIC / IPTV,Fire Alarm) 21-May-16 9-Aug-16 21-May-16 9-Aug-16
250.5.17.2 Electricity room 26-Aug-15 13-Sep-16 26-Aug-15 13-Sep-16
250.5.17.2.2 Super structure 26-Aug-15 13-Sep-16 26-Aug-15 13-Sep-16
250.5.17.2.2.1 Ground floor 26-Aug-15 13-Sep-16 26-Aug-15 13-Sep-16
250.5.17.2.2.1.2 Power Layout 12-Jun-16 3-Sep-16 12-Jun-16 3-Sep-16
250.5.17.2.2.1.6 Distribution Board 25-Jul-16 10-Sep-16 25-Jul-16 10-Sep-16
250.5.17.2.2.1.4 Lightining Layout 26-Aug-15 15-Aug-16 26-Aug-15 15-Aug-16
250.5.17.2.2.1.3 Earthing Layout 26-Aug-15 15-Aug-16 26-Aug-15 15-Aug-16
250.5.17.2.2.1.7 Lighting Layout 12-Jun-16 1-Sep-16 12-Jun-16 1-Sep-16
250.5.17.2.2.1.1 Data & Telephone / CCTV /Fire Alarm) 18-Jul-16 13-Sep-16 18-Jul-16 13-Sep-16
250.5.17.2.2.1.5 Eqipment( Generators) 18-Jul-16 29-Aug-16 18-Jul-16 29-Aug-16
250.5.17.3 Mosque 23-Aug-15 20-Aug-16 23-Aug-15 20-Aug-16
250.5.17.3.2 Super structure 23-Aug-15 20-Aug-16 23-Aug-15 20-Aug-16
250.5.17.3.2.1 Ground floor 23-Aug-15 20-Aug-16 23-Aug-15 20-Aug-16
250.5.17.3.2.1.2 Power Layout 11-May-16 9-Aug-16 11-May-16 9-Aug-16
250.5.17.3.2.1.6 Distribution Board 25-Jun-16 13-Aug-16 25-Jun-16 13-Aug-16
250.5.17.3.2.1.3 Earthing Layout 23-Aug-15 10-Jul-16 23-Aug-15 10-Jul-16
250.5.17.3.2.1.5 Lighting Layout 11-May-16 20-Aug-16 11-May-16 20-Aug-16
250.5.17.3.2.1.1 Data & Telephone / CCTV /Fire Alarm) 20-Jun-16 20-Aug-16 20-Jun-16 20-Aug-16
250.5.17.4 Ware house 22-Aug-15 15-Oct-16 22-Aug-15 15-Oct-16
250.5.17.4.2 Super structure 22-Aug-15 15-Oct-16 22-Aug-15 15-Oct-16
250.5.17.4.2.1 Ground floor 22-Aug-15 15-Oct-16 22-Aug-15 15-Oct-16
250.5.17.4.2.1.2 Power Layout 5-Mar-16 10-Sep-16 5-Mar-16 10-Sep-16
250.5.17.4.2.1.6 Distribution Board 23-May-16 17-Sep-16 23-May-16 17-Sep-16
250.5.17.4.2.1.4 Lightining Layout 22-Aug-15 13-Jul-16 22-Aug-15 13-Jul-16
250.5.17.4.2.1.3 Earthing Layout 22-Aug-15 13-Jul-16 22-Aug-15 13-Jul-16

Page 26 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.5.17.4.2.1.5 Lighting Layout 5-Mar-16 15-Oct-16 5-Mar-16 15-Oct-16


250.5.17.4.2.1.1 Data & Telephone / CCTV /Fire Alarm) 17-May-16 15-Oct-16 17-May-16 15-Oct-16
250.5.17.8 Main Entrance 30-Aug-15 29-Sep-16 30-Aug-15 29-Sep-16
250.5.17.8.2 Super structure 30-Aug-15 29-Sep-16 30-Aug-15 29-Sep-16
250.5.17.8.2.1 Ground floor 30-Aug-15 29-Sep-16 30-Aug-15 29-Sep-16
250.5.17.8.2.1.2 Power Layout 11-Jul-16 20-Sep-16 11-Jul-16 20-Sep-16
250.5.17.8.2.1.6 Distribution Board 22-Aug-16 25-Sep-16 22-Aug-16 25-Sep-16
250.5.17.8.2.1.4 Lightining Layout 30-Aug-15 5-Sep-16 30-Aug-15 5-Sep-16
250.5.17.8.2.1.3 Earthing Layout 30-Aug-15 5-Sep-16 30-Aug-15 5-Sep-16
250.5.17.8.2.1.5 Lighting Layout 11-Jul-16 27-Sep-16 11-Jul-16 27-Sep-16
250.5.17.8.2.1.1 Data & Telephone / CCTV /Fire Alarm) 17-Aug-16 29-Sep-16 17-Aug-16 29-Sep-16
250.5.17.6 Kiosk 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.17.6.2 Super structure 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.17.6.2.1 Ground floor 17-Aug-16 19-Sep-16 17-Aug-16 19-Sep-16
250.5.17.6.2.1.2 Power Layout 1-Sep-16 14-Sep-16 1-Sep-16 14-Sep-16
250.5.17.6.2.1.6 Distribution Board 11-Sep-16 17-Sep-16 11-Sep-16 17-Sep-16
250.5.17.6.2.1.3 Earthing Layout 17-Aug-16 23-Aug-16 17-Aug-16 23-Aug-16
250.5.17.6.2.1.5 Lighting Layout 1-Sep-16 19-Sep-16 1-Sep-16 19-Sep-16
250.5.17.6.2.1.1 ( Telephone System) 8-Sep-16 14-Sep-16 8-Sep-16 14-Sep-16
250.6 Testing & Commissioning 25-Feb-16 15-Feb-17 25-Feb-16 15-Feb-17
250.6.1 Main Building 25-Feb-16 25-Dec-16 25-Feb-16 25-Dec-16
250.6.1.2 Water Supply 8-Mar-16 7-Nov-16 8-Mar-16 7-Nov-16
250.6.1.3 Drainage 8-Mar-16 9-Nov-16 8-Mar-16 9-Nov-16
250.6.1.4 Fire Protection 25-Feb-16 23-Nov-16 25-Feb-16 23-Nov-16
250.6.1.7 Electrical 10-Mar-16 13-Dec-16 10-Mar-16 13-Dec-16
250.6.1.10 HVAC 18-Apr-16 25-Dec-16 18-Apr-16 25-Dec-16
250.6.11 Barracks 26-Dec-16 11-Jan-17 26-Dec-16 11-Jan-17
250.6.11.2 Water Supply 26-Dec-16 28-Dec-16 26-Dec-16 28-Dec-16
250.6.11.3 Drainage 29-Dec-16 1-Jan-17 29-Dec-16 1-Jan-17

Page 27 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.6.11.4 Fire Protection 2-Jan-17 4-Jan-17 2-Jan-17 4-Jan-17


250.6.11.7 Electrical 5-Jan-17 8-Jan-17 5-Jan-17 8-Jan-17
250.6.11.10 HVAC 9-Jan-17 11-Jan-17 9-Jan-17 11-Jan-17
250.6.2 Electricity room 26-Dec-16 8-Jan-17 26-Dec-16 8-Jan-17
250.6.2.4 Fire Protection 5-Jan-17 8-Jan-17 5-Jan-17 8-Jan-17
250.6.2.7 LPG 2-Jan-17 4-Jan-17 2-Jan-17 4-Jan-17
250.6.2.1 Electrical 26-Dec-16 28-Dec-16 26-Dec-16 28-Dec-16
250.6.2.10 HVAC 29-Dec-16 1-Jan-17 29-Dec-16 1-Jan-17
250.6.3 Mosque 26-Dec-16 11-Jan-17 26-Dec-16 11-Jan-17
250.6.3.2 Water Supply 26-Dec-16 28-Dec-16 26-Dec-16 28-Dec-16
250.6.3.3 Drainage 29-Dec-16 1-Jan-17 29-Dec-16 1-Jan-17
250.6.3.4 Fire Protection 2-Jan-17 4-Jan-17 2-Jan-17 4-Jan-17
250.6.3.7 Electrical 5-Jan-17 8-Jan-17 5-Jan-17 8-Jan-17
250.6.3.10 HVAC 9-Jan-17 11-Jan-17 9-Jan-17 11-Jan-17
250.6.4 Ware house 12-Jan-17 4-Feb-17 12-Jan-17 4-Feb-17
250.6.4.2 Water Supply 12-Jan-17 16-Jan-17 12-Jan-17 16-Jan-17
250.6.4.3 Drainage 17-Jan-17 21-Jan-17 17-Jan-17 21-Jan-17
250.6.4.4 Fire Protection 22-Jan-17 25-Jan-17 22-Jan-17 25-Jan-17
250.6.4.7 Electrical 26-Jan-17 30-Jan-17 26-Jan-17 30-Jan-17
250.6.4.10 HVAC 31-Jan-17 4-Feb-17 31-Jan-17 4-Feb-17
250.6.7 Main Entrance 12-Jan-17 29-Jan-17 12-Jan-17 29-Jan-17
250.6.7.2 Water Supply 12-Jan-17 15-Jan-17 12-Jan-17 15-Jan-17
250.6.7.3 Drainage 16-Jan-17 18-Jan-17 16-Jan-17 18-Jan-17
250.6.7.4 Fire Protection 19-Jan-17 22-Jan-17 19-Jan-17 22-Jan-17
250.6.7.7 Electrical 23-Jan-17 25-Jan-17 23-Jan-17 25-Jan-17
250.6.7.10 HVAC 26-Jan-17 29-Jan-17 26-Jan-17 29-Jan-17
250.6.5 Kiosk 26-Jan-17 30-Jan-17 26-Jan-17 30-Jan-17
250.6.5.7 Electrical 26-Jan-17 28-Jan-17 26-Jan-17 28-Jan-17
250.6.5.10 HVAC 29-Jan-17 30-Jan-17 29-Jan-17 30-Jan-17

Page 28 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.6.8 Site Plan 12-Feb-17 15-Feb-17 12-Feb-17 15-Feb-17


250.6.8.5 Irrigation 12-Feb-17 13-Feb-17 12-Feb-17 13-Feb-17
250.6.8.6 Fuel Supply 14-Feb-17 15-Feb-17 14-Feb-17 15-Feb-17
250.7 Handing Over & Project Close Out 26-Dec-16 29-Mar-17 26-Dec-16 29-Mar-17
250.7.1 As Built 26-Dec-16 29-Mar-17 26-Dec-16 29-Mar-17
250.7.1.6 Site Plan 16-Feb-17 6-Mar-17 16-Feb-17 6-Mar-17
250.7.1.6.2 SURVEY & SITE LEVELLING 16-Feb-17 18-Feb-17 16-Feb-17 18-Feb-17
250.7.1.6.3 INFRASTRUCTURES & NEWWORKS 19-Feb-17 27-Feb-17 19-Feb-17 27-Feb-17
250.7.1.6.4 PAVEMENT & ROAD WORKS 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.6.5 BOUNDARY WALL 2-Mar-17 4-Mar-17 2-Mar-17 4-Mar-17
250.7.1.6.6 LANDSCAPE 5-Mar-17 6-Mar-17 5-Mar-17 6-Mar-17
250.7.1.1 Structural 26-Dec-16 6-Feb-17 26-Dec-16 6-Feb-17
250.7.1.1.1 Main Building 26-Dec-16 1-Jan-17 26-Dec-16 1-Jan-17
250.7.1.1.1.1 Foundation 26-Dec-16 28-Dec-16 26-Dec-16 28-Dec-16
250.7.1.1.1.2 Ground floor 26-Dec-16 28-Dec-16 26-Dec-16 28-Dec-16
250.7.1.1.1.3 First floor 26-Dec-16 1-Jan-17 26-Dec-16 1-Jan-17
250.7.1.1.1.5 Roof 29-Dec-16 1-Jan-17 29-Dec-16 1-Jan-17
250.7.1.1.2 Barracks 12-Jan-17 15-Jan-17 12-Jan-17 15-Jan-17
250.7.1.1.2.1 Foundation 12-Jan-17 15-Jan-17 12-Jan-17 15-Jan-17
250.7.1.1.2.2 Ground floor 12-Jan-17 15-Jan-17 12-Jan-17 15-Jan-17
250.7.1.1.3 Electricity rooms 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.3.1 Foundation 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.3.2 Ground floor 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.4 Mosque 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.4.1 Foundation 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.4.2 Ground floor 12-Jan-17 14-Jan-17 12-Jan-17 14-Jan-17
250.7.1.1.5 Ware house 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.1.5.1 Foundation 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.1.5.2 Ground floor 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17

Page 29 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.7.1.1.8 Main Entrance 30-Jan-17 31-Jan-17 30-Jan-17 31-Jan-17


250.7.1.1.8.1 Foundation 30-Jan-17 31-Jan-17 30-Jan-17 31-Jan-17
250.7.1.1.8.2 Ground floor 30-Jan-17 31-Jan-17 30-Jan-17 31-Jan-17
250.7.1.1.6 Kiosk 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.1.6.1 Foundation 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.1.6.2 Ground floor 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.7 Architectural 2-Jan-17 2-Mar-17 2-Jan-17 2-Mar-17
250.7.1.7.1 Main Building 2-Jan-17 20-Feb-17 2-Jan-17 20-Feb-17
250.7.1.7.1.2 Ground floor 2-Jan-17 18-Jan-17 2-Jan-17 18-Jan-17
250.7.1.7.1.3 First floor 19-Jan-17 5-Feb-17 19-Jan-17 5-Feb-17
250.7.1.7.1.5 Roof 6-Feb-17 12-Feb-17 6-Feb-17 12-Feb-17
250.7.1.7.1.4 Elevation 13-Feb-17 20-Feb-17 13-Feb-17 20-Feb-17
250.7.1.7.2 Barracks 16-Jan-17 24-Jan-17 16-Jan-17 24-Jan-17
250.7.1.7.2.2 Ground floor 16-Jan-17 22-Jan-17 16-Jan-17 22-Jan-17
250.7.1.7.2.7 Roof 23-Jan-17 24-Jan-17 23-Jan-17 24-Jan-17
250.7.1.7.2.4 Elevation 23-Jan-17 24-Jan-17 23-Jan-17 24-Jan-17
250.7.1.7.3 Electricity room 15-Jan-17 1-Feb-17 15-Jan-17 1-Feb-17
250.7.1.7.3.2 Ground floor 15-Jan-17 25-Jan-17 15-Jan-17 25-Jan-17
250.7.1.7.3.3 Roof 26-Jan-17 30-Jan-17 26-Jan-17 30-Jan-17
250.7.1.7.3.4 Elevation 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.7.4 Mosque 15-Jan-17 30-Jan-17 15-Jan-17 30-Jan-17
250.7.1.7.4.2 Ground floor 15-Jan-17 25-Jan-17 15-Jan-17 25-Jan-17
250.7.1.7.4.3 Roof 26-Jan-17 30-Jan-17 26-Jan-17 30-Jan-17
250.7.1.7.4.4 Elevation 29-Jan-17 30-Jan-17 29-Jan-17 30-Jan-17
250.7.1.7.5 Ware house 7-Feb-17 2-Mar-17 7-Feb-17 2-Mar-17
250.7.1.7.5.2 Ground floor 7-Feb-17 21-Feb-17 7-Feb-17 21-Feb-17
250.7.1.7.5.3 Roof 22-Feb-17 26-Feb-17 22-Feb-17 26-Feb-17
250.7.1.7.5.4 Elevation 27-Feb-17 2-Mar-17 27-Feb-17 2-Mar-17
250.7.1.7.8 Main Entrance 1-Feb-17 25-Feb-17 1-Feb-17 25-Feb-17

Page 30 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.7.1.7.8.2 Ground floor 1-Feb-17 15-Feb-17 1-Feb-17 15-Feb-17


250.7.1.7.8.3 Roof 16-Feb-17 20-Feb-17 16-Feb-17 20-Feb-17
250.7.1.7.8.4 Elevation 21-Feb-17 25-Feb-17 21-Feb-17 25-Feb-17
250.7.1.7.6 Kiosk 2-Feb-17 6-Feb-17 2-Feb-17 6-Feb-17
250.7.1.7.6.2 Ground floor 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.7.6.3 Roof 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.2 Electrical 25-Jan-17 5-Mar-17 25-Jan-17 5-Mar-17
250.7.1.2.1 Main Building 21-Feb-17 1-Mar-17 21-Feb-17 1-Mar-17
250.7.1.2.1.2 Ground floor 21-Feb-17 25-Feb-17 21-Feb-17 25-Feb-17
250.7.1.2.1.3 First floor 26-Feb-17 1-Mar-17 26-Feb-17 1-Mar-17
250.7.1.2.2 Barracks 25-Jan-17 26-Jan-17 25-Jan-17 26-Jan-17
250.7.1.2.2.2 Ground floor 25-Jan-17 26-Jan-17 25-Jan-17 26-Jan-17
250.7.1.2.3 Electricity room 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.2.3.2 Ground floor 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.2.4 Mosque 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.2.4.2 Ground floor 31-Jan-17 1-Feb-17 31-Jan-17 1-Feb-17
250.7.1.2.5 Ware house 4-Mar-17 5-Mar-17 4-Mar-17 5-Mar-17
250.7.1.2.5.2 Ground floor 4-Mar-17 5-Mar-17 4-Mar-17 5-Mar-17
250.7.1.2.8 Main Entrance 26-Feb-17 27-Feb-17 26-Feb-17 27-Feb-17
250.7.1.2.8.2 Ground floor 26-Feb-17 27-Feb-17 26-Feb-17 27-Feb-17
250.7.1.2.6 Kiosk 7-Feb-17 8-Feb-17 7-Feb-17 8-Feb-17
250.7.1.2.6.2 Ground floor 7-Feb-17 8-Feb-17 7-Feb-17 8-Feb-17
250.7.1.8 Mechanical 28-Jan-17 29-Mar-17 28-Jan-17 29-Mar-17
250.7.1.8.4 Plumbing 28-Jan-17 11-Mar-17 28-Jan-17 11-Mar-17
250.7.1.8.4.1 Main Building 2-Mar-17 11-Mar-17 2-Mar-17 11-Mar-17
250.7.1.8.4.1.2 Ground floor 2-Mar-17 6-Mar-17 2-Mar-17 6-Mar-17
250.7.1.8.4.1.3 First floor 7-Mar-17 11-Mar-17 7-Mar-17 11-Mar-17
250.7.1.8.4.2 Barracks 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17
250.7.1.8.4.2.2 Ground floor 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17

Page 31 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.7.1.8.4.3 Electricity room 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17


250.7.1.8.4.3.2 Ground floor 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.8.4.4 Mosque 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.4.4.2 Ground floor 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.4.5 Ware house 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.4.5.2 Ground floor 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.4.7 Main Entrance 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.4.7.2 Ground floor 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.3 Fire fighting 28-Jan-17 20-Mar-17 28-Jan-17 20-Mar-17
250.7.1.8.3.1 Main Building 12-Mar-17 20-Mar-17 12-Mar-17 20-Mar-17
250.7.1.8.3.1.2 Ground floor 12-Mar-17 15-Mar-17 12-Mar-17 15-Mar-17
250.7.1.8.3.1.3 First floor 16-Mar-17 20-Mar-17 16-Mar-17 20-Mar-17
250.7.1.8.3.2 Barracks 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17
250.7.1.8.3.2.2 Ground floor 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17
250.7.1.8.3.3 Electricity room 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.8.3.3.2 Ground floor 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17
250.7.1.8.3.4 Mosque 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.3.4.2 Ground floor 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.3.5 Ware house 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.3.5.2 Ground floor 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.3.7 Main Entrance 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.3.7.2 Ground floor 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.5 HVAC 28-Jan-17 29-Mar-17 28-Jan-17 29-Mar-17
250.7.1.8.5.1 Main Building 21-Mar-17 29-Mar-17 21-Mar-17 29-Mar-17
250.7.1.8.5.1.2 Ground floor 21-Mar-17 25-Mar-17 21-Mar-17 25-Mar-17
250.7.1.8.5.1.3 First floor 26-Mar-17 29-Mar-17 26-Mar-17 29-Mar-17
250.7.1.8.5.2 Barracks 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17
250.7.1.8.5.2.2 Ground floor 28-Jan-17 29-Jan-17 28-Jan-17 29-Jan-17
250.7.1.8.5.3 Electricity room 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17

Page 32 of 33 Date Revision Checked Approved


All Projects
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
WBS Elements below Project
Summary
Site no.250-Prototype no.48-Al Mujahidin Departement Branch Completion

ABHA-ASIR Zone

WBS

WBS Code WBS Name Start Finish 2014 2015 2016 2017 2018 2019 2020

250.7.1.8.5.3.2 Ground floor 5-Feb-17 6-Feb-17 5-Feb-17 6-Feb-17


250.7.1.8.5.4 Mosque 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.5.4.2 Ground floor 2-Feb-17 4-Feb-17 2-Feb-17 4-Feb-17
250.7.1.8.5.5 Ware house 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.5.5.2 Ground floor 6-Mar-17 9-Mar-17 6-Mar-17 9-Mar-17
250.7.1.8.5.8 Main Entrance 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.5.8.2 Ground floor 28-Feb-17 1-Mar-17 28-Feb-17 1-Mar-17
250.7.1.8.5.6 Kiosk 9-Feb-17 11-Feb-17 9-Feb-17 11-Feb-17
250.7.1.8.5.6.2 Ground floor 9-Feb-17 11-Feb-17 9-Feb-17 11-Feb-17
250.7.2 Operation & Manual Maintenance 16-Feb-17 7-Mar-17 16-Feb-17 7-Mar-17
250.7.3 Demobilization 8-Mar-17 27-Mar-17 8-Mar-17 27-Mar-17

Page 33 of 33 Date Revision Checked Approved