Problem 1:
Draw the current state drawing along with the time line for the following data
(Table -1) of a Peanut butter manufacturing unit. Also calculate lead time, value
added time and takt time. Assume any missing data appropriately.
Table - 1
Customer demand 700 pieces per day
Company working time 1 shifts of 8 hours duration with 30 min break for each shift and
5 days/week
1: Peanut butter CT = 25 s with 1 operator and 700 pcs in inventory
application
2: Jelly Application CT = 30 s with 1 operator and 359 pcs in inventory
Problem 2:
Draw the current state drawing along with the Time line for the following data
(Table -1&2).Also calculate Lead time, processing time and Takt time. Assume any
missing data appropriately and mention in the current state drawing.
Table - 1
Customer demand 10,000 pieces per month
Company working time 2 shifts of 8 hours duration with 45 min break for each shift and 22
days/month
Packaging 20 items in a tray
2000
1300
3 Welding 28 325 80
4000
1600
5 Assembly 40 0 100
2800
6 Shipping - - -
Problem 3:
Draw the current state drawing along with the Time line for the following data
(Table -1&2).Also calculate Lead time, processing time and Takt time. Assume any
missing data appropriately and mention in the current state drawing.
Table - 1
Customer demand 22,000 pieces per month
Company working time 2 shifts of 8 hours duration with 40 min break for each shift and
26 days/month
Packaging 50 items in a tray
Shipment Once in a day
Worker One operator per machine
Raw material will have to wait 5 days for the first process to
start
3000
1400
3 Drilling 30 325 80
3000
5 Assembly 40 0 100
2800
6 Shipping - - -