Method Statement For Construction of An Additional Column To Support The Existing Ground)

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 7

TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No.

TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 1 of 7
basement raft slab

METHOD STATEMENT FOR CONSTRUCTION OF AN


ADDITIONAL COLUMN TO SUPPORT THE EXISTING
GROUND FLOOR SLAB FROM BASEMENT RAFT SLAB

PROJECT : (Replace with the project’s name, at location , city name)

CLIENT : (Replace with the client’s name)

MASTER DEVELOPER : (Replace with the master developer’s name)

PMC : (Replace with the PMC’s name)

LEAD CONSULTANT : (Replace with the lead consultant’s name)

SUB-CONSULTANT : (Replace with the sub-consultant’s name)

MAIN CONTRACTOR : (Replace with the main contractor’s name)

SUB-CONTRACTOR : (Replace with the sub-contractor’s name)

TABLE OF CONTENTS
1. REVISION RECORD...............................................................................................................................3
2. PURPOSE...............................................................................................................................................4
3. SCOPE OF WORKS...............................................................................................................................4
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 2 of 7
basement raft slab

4. REFERENCES........................................................................................................................................4
5. DEFINITIONS / ABBREVIATIONS..........................................................................................................4
5.1. Definition.............................................................................................................................................4
5.2. Abbreviations......................................................................................................................................4
6. RESPONSIBILITIES................................................................................................................................4
7. EQUIPMENTS/ TOOLS/ MANPOWER...................................................................................................5
7.1. Equipments / Tools.............................................................................................................................5
7.2. List of Manpower................................................................................................................................5
7.3. MATERIALS.......................................................................................................................................5
8. PROCEDURE..........................................................................................................................................5
8.1. Back propping.....................................................................................................................................5
8.2. Survey and Marking............................................................................................................................5
8.3. Chipping / removal of concrete...........................................................................................................6
8.4. Inserting for starter bars......................................................................................................................6
8.5. Steel reiforcement fixing.....................................................................................................................6
8.6. Formwork shutter................................................................................................................................6
8.7. Concete pouring.................................................................................................................................6
8.8. Curing.................................................................................................................................................6
8.9. GRP Lining.........................................................................................................................................7
9. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS.............................................................................7
10. ATTACHMENTS......................................................................................................................................7
10.1. Inspection Checklists..........................................................................................................................7
10.2. Inspection Test Plan...........................................................................................................................7
10.3. Risk Assessment................................................................................................................................7
10.4. Technical Data sheet (TDS)...............................................................................................................7
10.5. Material Safety Data Sheet (MSDS)...................................................................................................7
10.6. Taransmittals......................................................................................................................................7

1. REVISION RECORD
This page is a record of all revisions of the document identified below by number and title. All previous revisions
are hereby superseded and are to be destroyed.
Rev Date By Chkd. Approved Description of Revisions
0 First issue
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 3 of 7
basement raft slab

Signature field
Revision
Revision
Number
Date
Prepared by Checked by

Reviewed
By Construction Technical QA/QC MEP Co-
Manager Manager Engineer HSE Officer ordinator Sub-contractor

Approved
By Project
Manager

2. PURPOSE
1. The purpose of this method statement is to define the procedure for the sequence of construction of an additional
column to support the existing ground floor slab of the pump room from the basement raft considering all safety
and quality requirements.
3. SCOPE OF WORKS
1. Chipping, concrete removal, inserting starter bars using approved chemical anchoring system, fixing steel
reinforcement, pouring of concrete and GRP lining for one central column for the pump room ground floor slab in
accordance with the approved shop drawings and in compliance with contract specifications.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 4 of 7
basement raft slab

4. REFERENCES
1. XXXX transmittal ref. GG2_TRA_TCI_PIV_0429 dated 24 May 2011
2. XXXX transmittal ref. GG2_TRA_TCI_PIV_0444 dated 14 June 2011
5. DEFINITIONS / ABBREVIATIONS
5.1.Definition
1. Client -(Replace with clients name)
2. Developer -(Replace with developers name)
3. Consultant -(Replace with consultants name)
4. PMC -(Replace with PMC name)
5. Contractor -(Replace with contractors name)
5.2.Abbreviations
1. Engineer- Representative of “Name of engineering consultancy”
2. ICL - Inspection Check List
3. IR - Inspection Request
4. ITL -Independent Testing Laboratory
5. ITP - Inspection and Test Plan
6. ITR -Inspection & Test Requests
7. MET - Method Statement
8. MIR - Material Inspection Request
9. MSDS - Material Safety Data Sheet
10. PPE -Personal Protective Equipment
11. PQP -Project Quality Plan
12. PTW -Permit To Work ( Working at Height or enclosed spaces)
13. RA -Hazard Identification and Risk Assessment
14. RFIA - Request for Inspection and Approval
15. TBM - Temporary Bench Mark
6. RESPONSIBILITIES
1. The Construction Manager is overall responsible for the implementation of the method statement, to ensure that
the team of Engineers and foremen are aware of this MS and, to ensure that all resources (labour, material and
equipment) are available to carry out the work as planned.
2. The Project Engineer/ Site Engineer are responsible to carry out the work as per the approved MS. He is also
responsible to ensure adequate equipment for mobilization works are in place prior to the starting of work.
3. QA/QC Engineer is responsible to ensure work has been done as per the specification and drawings, inspections
are done as per Quality Control Procedure and the Inspection and Test plan, and all work are offered to
client/consultant for inspection.
4. The Safety Engineer is responsible to ensure that all Safety precautions are in place, and that all personnel on site
are using the required Personal Protective Equipment (helmet, gloves, shoes, coveralls, etc.). He must also ensure
that all relevant permissions are available for the works.
7. EQUIPMENTS/ TOOLS/ MANPOWER
7.1.Equipments / Tools
1. Drill machine
2. Saw cut grinder
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 5 of 7
basement raft slab

3. Electric chipping hammer (Hilti)


4. Jack hammer
5. Masonry tools
6. Cleaning tools
7.2.List of Manpower
1. Project Manager
2. Safety Engineer/ Officer
3. Construction Manager
4. Foremen / Work Supervisors
5. Site Engineer
6. Skilled and unskilled labourers & scaffolders
7. QA/ QC Engineer/ Inspector
7.3.MATERIALS
1. GRP lining 5 mm GRP lining GG2_MD_07110_2415
2. Bonding agent PVA LATEX REPRESA GG2_MD_03210_2502
3. Anchoring system Hilti HIT RE 500 GG2_MD_03210_1689
4. Nonshrink concrete C40/10 GG2_MD_03310_5352
5. Concrete Repair CONREP 301 GA GG2_MD_03310_0400
8. PROCEDURE
8.1.Back propping
Prior to the commencement of the work the ground floor slab of the pump room shall be supported using back propping
system (cup lock + decking + infill beam)as per the attached layout ref GG2_PV_SD_D_SF_01_10_00 on the basement
raft.
Care shall be taken to protect the completed GRP work inside the water tank by covering it with polyethylene sheet followed
by18 mm plywood.
8.2.Survey and Marking
Mark the concrete area outline for the 2400*2400 mm to be chipped at the pump room ground floor as shown in the
attached lay outs.
Mark the concrete out line for the column 400*400 mm at the basement floor slab (raft) as per the attached layouts.
8.3.Chipping / removal of concrete
After marking the area of concrete that to be removed (2.4*2.4 m) at the pump floor slab, this marking will be saw cut using
grinder to a depth of 10 mm for proper termination of the chipping works.
Use an electric chipping hammer, a width of 100-150 mm of concrete at the perimeter of the marking to be chipped to the
full depth of the pump floor slab.
The remaining entire area within the 2.4*2.4 m area will be demolished using jack hammer.
Do chipping for the top surface of basement raft to the dimension of the column (400x400) mm to be done.
The existing steel reinforcement bars will be properly cleaned using wire steel brush to remove any laitance or foreign
materials.
8.4.Inserting for starter bars
Using the drill, 25 mm diameter holes will be prepared with 200 mm depth at the spacing specified at the drawing with total
no of 8 no. of main column reinforcement rebar.
The holes will be cleaned well by compressed air or blower.
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 6 of 7
basement raft slab

Approved anchoring system, Hilti HIT RE 500, will be used for the anchoring of steel bars.
Place the Hilti hit Re 500 foil pack into the holder of the dispenser.
Screw the mixer assembly onto the foil pack.
Put this assembly into the dispenser.
Inject the Hilti HIT RE 500 starting from the hole.
The volume required of Hilti HIT RE 500 can be calculated as follow
V ml= L x (D12-D22)/ 1000= 200x ((25)2-(20)2)/1000=45 ml for each hole
This means that 8 no of holes will take 8*45=360 ml (i.e. approx. 1 foil pack will be used for the total no. of holes).
Injection of epoxy shall be start from bottom of the hole and slowly withdrawn upward in order to avoid air pockets.
Push the rebar into the epoxy giving it slight twisting motion to allow flow of the epoxy around the deformation of the bar.
The same will be repeated for the eight no of rebar.
The inserted rebar shall be left undisturbed for min. 4 hours until complete curing of the epoxy.
RFIA will be raised to the Engineer for checking the installation of steel rebar.
8.5.Steel reinforcement fixing
As per the transmittal from M/s. XXXX ref. GG2_TRA_TCI_PIV_0429, 8 T 20 main reinforcement of the column will be
installed with T8 @ 150 mm stirrups as per the attached shop drawing reinforcement details.
Additional top reinforcement bars 6T25 with length (L=3500 mm) will be added in both directions.
Shear links T10@20 cm, each direction, will be fixed within the area 2.4*2.44 m
8.6.Formwork shutter
Formwork shutter will be erected as per the attached concrete out line at the shop drawing.
The same will be checked before casting by QA/QC and RFIA will be raised to the Engineer for concrete pouring.
Application of bonding Agent:
Approved bonding agent, PVA LATEX REPRESA, will be applied to the chipped area at the pump room ground floor slab,
manufacturer instructions for mixing and application will be followed as per the attached data sheet.
8.7.Concrete pouring
Approved C40/10 non shrinkage concrete (GGBS + OPC + Cebex 100) will be poured to the prepared shutter of column.
8.8.Curing
After 24 hours, column shutter can be removed while the slab shutter shall be kept for at least 14 days and the curing shall
continue for min. 7 days using wet purl lab clothes.
8.9.GRP Lining
After the curing time elapsed, the supporting scaffolding shall be dismantled tacking care not to damage the internal GRP
lining.
Prepare the column and ceiling concrete surface, corner edges to be chamfered and floor column angles shall be provided
with mortar angle fillet prior to GRP application.
The approved 5mm GRP lining will be applied to the column and ceiling with required lamination to the floor and ceiling
existing GRP lining.
The GRP lining work for the column and ceiling will be applied in accordance to the approved method statement of GRP
lining via our approved submittal ref. GG2_MD_07110_2415 rev. (0)
Openings enlargement.
1. As per the MEP requirements the existing openings 250*250 mm are required to be enlarged to be 500*500 mm,
the following procedure shall be followed:
The new openings (500*500 mm) shall be marked by the MEP engineer.
The marking shall be saw cut to terminate the chipping of concrete.
Chipping shall start using Electric chipping hammer (Hilti) till the required clear dim obtained
TECHNICAL DEPARTMENT-CIVIL (Replace by the Doc. No. TEC-CSInnn-MET-DoR-
Project Name) (Rev No.) 001
Insert Main METHOD STATEMENT Issue Date 02 January 2013
Contractors Logo Method statement for construction of an additional Rev. Date NA
column to support the existing ground floor slab from
Pages 7 of 7
basement raft slab

The chipped surface of concrete shall be repaired using the approved material concrete repair CONREP 301 GA.
Manufacturer’s instructions regarding the CONREP 301GA mixing, application and curing shall be strictly followed (copy
attached for your reference).
9. EQUIPMENTS/ TOOLS / MANPOWER/MATERIALS
10. ATTACHMENTS
10.1. Inspection Checklists
10.2. Inspection Test Plan
10.3. Risk Assessment
10.4. Technical Data sheet (TDS)
1. PVA latex represa data sheet
2. Approved mix design for C40/10 non shrinkage concrete
3. Approved submittal for GRP lining.
4. CONREP 301 GA data sheet
5. Hilti HIT RE 500 epoxy data sheet
10.5. Material Safety Data Sheet (MSDS)
10.6. Transmittals
6. Building Type F pump room column location & sec. A-A for column details.
7. Building Type E pump room column location & sec. A-A for column details.
8. Layout sketch for the GG2_PV_SD_D_SF_01_10_00