DMC Wood Floor
DMC Wood Floor
DMC Wood Floor
2 Masonry/Concreting
Cement bags 45.00 235.00 10,575.00
Fine Sand cu.m 2.00 1,450.00 2,900.00
Screened Sand cu.m 2.00 1,700.00 3,400.00
CHB #4 pcs 550.00 17.00 9,350.00
RSB 16mm dia. X 6m pcs 8.00 385.00 3,080.00
RSB 10mm dia. X 6m pcs 20.00 138.00 2,760.00
Material Cost 32,065.00
Labor Cost 16,032.50
Total Cost 48,097.50
3 Tile Works
Tiles 60cm x 60cm pcs 177.00 165.00 29,205.00
Tiles 30cm x 30cm pcs 268.00 35.00 9,380.00
Tiles 20cm x 20cm pcs 72.00 15.00 1,080.00
Cement bags 50.00 235.00 11,750.00
Fine Sand cu.m 5.00 1,450.00 7,250.00
Material Cost 58,665.00
Labor Cost 23,466.00
Total Cost 82,131.00
1 Embankment 12,660.00
2 Masonry/Concreting 48,097.50
3 Tile Works 82,131.00
4 Steel Works (2nd Floor Flooring and Roofing) 50,558.20
5 Carpentry Works (Second Floor Walls) 38,422.50
6 Painting Works ( Finishing Works) 29,460.00
7 Doors and Windows 110,012.00
8 Plumbing Works 87,720.00
9 Electrical Works 30,000.00
Total Cost 489,061.20