Professional Documents
Culture Documents
KHRI-Webinar (04-05-2020) - Pumping of Concrete - Challenges & Way Forward - DR Prakash Nandagopalan (IITB)
KHRI-Webinar (04-05-2020) - Pumping of Concrete - Challenges & Way Forward - DR Prakash Nandagopalan (IITB)
KHRI-Webinar (04-05-2020) - Pumping of Concrete - Challenges & Way Forward - DR Prakash Nandagopalan (IITB)
Way forward
Prakash Nanthagopalan
Associate Professor
Construction Technology and Management Specialisation
Department of Civil Engineering
Indian Institute of Technology Bombay
Mumbai
4th May 2020
Outline
• Case studies
Courtesy:
3
Google Images
Why concrete needs to be pumped ?
• Concreting - inaccessible areas
• Speed of placement
4
Components involved in pumping
– Concrete pump
– Placing boom
– Cleaning accessories
5
Pumping mechanisms
• Screw
• Squeeze/peristaltic
6
Placing Booms
Truck mounted booms Tower mounted booms
Courtesy: http://www.pumppartners.com/documents/schwing31htreach.pdf
Concrete pump - Switching valves
https://schwing-stetter.com/en/technology/rock-valve.html
S-transfer tube 8
Schematic of the piston side and rod side
9
https://www.putzmeister.com/documents/58410/62433/Putzmeister-Concrete+Technology-BSA+702D.zip/9afd9e4f-6aae-0e53-13e5-c5c28dc3c725
Piston pump
11
Burj Khalifa
Pump Putzmeister BSA 14000 HP-D with
max 310 bar pressure
Pipe diameter Horizontal - 125 mm, vertical - 150 mm
Grade of concrete C80, C60, C50
Test on fresh concrete Flow (> 550 mm for tower and 150±25
mm for podium), setting time,
Temperature.
Concrete properties Flow loss – up to 10%,
(per 100m pumping) Temp. increment - 2 to 3ºC.
Expected concrete C80A (250 m) – 151
pressure (in bars) C80 (450 m) – 170
C60 (600 m) – 290
C50 (600 m) – 199
• w/b ratio = 0.30-0.36
• Fine agg. content for tower was maintained 50%. Coarse agg. used (20, 14, 10 mm)
• Pulverised fuel ash (F class - up to 20 %) used for tower.
• Silica fume used between 5 – 10%.
• Specially modified superplasticiser used to meet site requirements.
12
Courtesy: https://en.wikipedia.org/wiki/Burj_Khalifa, burjkhalifa.ae, baker et al., 2007, Ghorbanzadeh, 2017)
Mock test
Pumping trails were conducted with a 310 bar stationary pump.
Pressure transducers were fixed at 250, 450 and 600 m to measure the concrete pressure.
15
Mixture details and challenges
Materials Quantity (kg/m3) Maintaining the consistency concrete properties
at batching point, pumping point, pouring point
Cement 340 is a challenge.
Fly ash 135
Water 200 Temperature ranges = 15 - 35°C
RH ranges = 30 - 100 %
Coarse agg. 948
Fine agg. 766 Priming Grout : Cement + Fly ash (645 kg/m3),
w/b ratio = 0.38, SP = 7.1 kg/m3, retarder 2.5
SP 2.4 – 5.2 kg/m3.
?
17
Factors affecting pumpability
Pipe diameter
Discharge requirements
Pump capacity
Ambient conditions/Seasonal variations
• Segregation resistance
• Pressurized Bleeding test
• Segregation Cylinder test
19
Rheology
• Rheology - a science of deformation and flow of matter (BS 5168)
20
Concrete flow in pipes - CVC Vs SCC
• Lubrication layer (LL)
• Shearing zone (SZ)
• Plug zone (PZ)
21
Courtesy: Revanth Kumar
Role of lubrication layer
• Improves the efficiency of pumping
• It acts as a ‘lubricant’
• Does priming through grout/slurry is suffice for
lubrication throughout the pumping?
• Bleeding
• Wall effect
24
Dhanapal and Nanthagopalan, 2020; Kwon et al. 2013
Prediction of concrete pressure
25
Pressure prediction using interface rheometer
(Tribometer)
HFC/SCC CVC
26
Khatib (2013)
Testing parameters and their significance
Khatib (2013)
29
Rheometer
Shear Profile
Rheological parameters
30
Pressure Prediction
• When the shear stress at the concrete pipe wall interface is lower than the
yield stress of the concrete, the concrete flow as slip flow.
2𝐿 𝑄.µ𝑖
𝑃= + 𝜏𝑜𝑖 Equation 1
𝑅 𝜋.𝑅2 .𝑘
• When the shear stress at the concrete pipe interface exceeds the yield stress
of concrete, the concrete will experience the slip plus shear flow of concrete.
𝑄 𝑅 𝑅
2𝐿 2 − 4.µ𝜏0𝑖 +3.µ𝜏0
𝜋.𝑅 .𝑘
𝑃= 𝑅 . µ𝑖 + 𝜏0𝑖 Equation 2
𝑅 1+4.µ.µ𝑖
32
T Pipe Pressure transducer Data logger Pressure gauge
Mock test – Results
33
Pressure prediction using sliding pipe rheometer
i = Area ratio
• i=3
• Predicted concrete pressure = 60 bar
• Hydraulic pressure required = 180 bar (i.e 60 ×3)
• Pump capacity > 180 bar
35
Decision making
Pump capacity “less than” or “greater than” hydraulic pressure required
36
Points to be pondered
37
Minimum horizontal clearance
L o n g- r a d i u s r iser b e n d S b end
39
s e c ur e d in c o n crete
Concrete Pumping – Pipeline anchorages
40
Pipe line anchoring
The pipe lines must be supported on firm platform with proper mounting of
the couplings* and adequate attention shall be given for alignment.
Replacement of pipes
43
Shut off valve – Pumping upwards Shut off valve – Pumping downwards
Concreting pumping - downwards
Cleaning accessories
• Sponge ball
• Cleaning pigs
Improper cleaning Reduces pipe c/s area increases pressure requirements
46
Courtesy: Putzmeister
Pipe related considerations
• Minimum bends in pipes, avoid sharp bends. Each 10o bend is
equivalent to an extra length of pipe of 1 m.
47
Requirements for pumped concrete
• Concrete mixture should neither be too harsh nor too sticky.
Thank you
50