A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY REMARKS
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT REMARKS
Prepared by : Checked by :
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
7/11/2019 RSB 12mm x 6m, PNS 415 161 pcs
### RSB 12mm x 7.5m, PNS 415 365 pcs
### RSB 12mm x 9m, PNS 415 968 pcs
### RSB 12mm x 10.5m, PNS 415 352 pcs
### RSB 12mm x 12m, PNS 415 870 pcs
### RSB 20mm x 9m, PNS 415 16 pcs
### RSB 25mm x 10.5m, PNS 415 149 pcs
### RSB 25mm X 12m, PNS 415 68 pcs
### RSB 28mm x 6m, PNS 415 18 pcs
### RSB 28mm x 7.5m, PNS 415 36 pcs
### RSB 28mm x 9m, PNS 415 233 pcs
### RSB 28mm x 10.5m, PNS 415 76 pcs
### RSB 28mm x 12m, PNS 415 18 pcs
TOTAL
REMARKS
- rsb arrived in right number of quantity with Delivery Receipts & Mill Certificates
- no adverse finding prior to unloading
C. TESTING
Concrete Compressive Strength Test Results
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
4/11/2019 34 DAYS FTG 6K 3/4 PCD 28D 1/10/2019 9770 PSI
4/11/2019 33 DAYS TANKWALL 5K 3/4 PCD 28D 2/10/2019 5710 PSI
4/11/2019 28 DAYS COLUMN 8K 3/4 PCD 28D 7/10/2019 8410 PSI
4/11/2019 19 DAYS COLUMN 8K 3/4 PCD 28D 10/16/2019 6030 PSI
4/11/2019 19 DAYS FOOTING 5K 3/4 PCD 28D 10/16/2019 5710 PSI
4/11/2019 16 DAYS RTW 5K 3/4 PCD 28D 10/19/2019 4830 PSI
4/11/2019 15 DAYS FOOTING 5K 3/4 PCD 28D 10/20/2019 4610 PSI
4/11/2019 14 DAYS FOOTING 5K 3/4 PCD 28D 10/21/2019 5920 PSI
4/11/2019 8 DAYS COLUMN 8K 3/4 PCD 28D 10/27/2019 7990 PSI
4/11/2019 8 DAYS RTW 5K 3/4 PCD 28D 10/27/2019 3280 PSI
4/11/2019 7 DAYS GF SLAB 6K 3/4 PCD 28D 10/28/2019 8250 PSI
5/11/2019 31 DAYS FOOTING 5K 3/4 PCD 28D 5/10/2019 7370 PSI
5/11/2019 36 DAYS COLUMN 8K 3/4 PCD 28D 9/30/2019 8400 PSI
5/11/2019 12 DAYS TANKSLAB 6K 3/4 PCD 28D 10/24/2019 6510 PSI
5/11/2019 7 DAYS COLUMN 8K 3/4 PCD 28D 10/29/2019 7290 PSI
7/11/2019 8 DAYS FOOTING F4 5K 3/4 PCD 28D 10/30/2019 3940 PSI
7/11/2019 7 DAYS RTW ZONE 1 5K 3/4 PCD 28D 10/31/2019 5000 PSI
7/11/2019 29 DAYS FTG 6K 3/4 PCD 28D 9/10/2019 9410 PSI
7/11/2019 14 DAYS TANKSLAB 6K 3/4 PCD 28D 10/24/2019 6870 PSI
Prepared by : Checked by :
WEIGHT (KG)
858.13
2430.9
7734.32
3282.64
9265.5
355.2
6028.54
3144.32
522
1305
10135.5
3857
1044
49963.05
REMARKS
PASSED
PASSED
PASSED
75% AT 19 DAYS
PASSED
PASSED
PASSED
PASSED
PASSED
66% AT 8 DAYS
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
rnie De Torres
oject Manager
PROJECT TITLE : UMA RESIDENCES
PROPRIETOR : QUEENSTOWN REALTY & DEVELOPMENT
CONSTRUCTION MANAGERS : NQRDI
CONTRACTOR : Scheirman Construction Consolidation Inc.
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
### 12mm x 7.5m, PNS 415 1768
### 12mm x 9m, PNS 415 300
### 12mm x 10.5m, PNS 415 523
### 12mm x 12m, PNS 415 2389
### 28mm x 7.5m, PNS 415 150
TOTAL
REMARKS
- no adverse finding prior to unloading
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
### 16 DAYS RTW 5K 3/4 PCD 28D 10/27/2019 4090 PSI
### 12 DAYS GF SLAB 6K 3/4 PCD 28D 10/31/2019 5230 PSI
### 7 DAYS RTW 5K 3/4 PCD 28D 5/10/2019 4290 PSI
### 16 DAYS COLUMN 8K 3/4 PCD 28D 10/27/2019 8770 PSI
### 15 DAYS GF SLAB 6K 3/4 PCD 28D 10/28/2019 9410 PSI
### 14 DAYS COLUMN 8K 3/4 PCD 28D 10/29/2019 7380 PSI
11/15/2019 30 DAYS COLUMN 8K 3/4 PCD 28D 10/16/2019 15470 PSI
11/15/2019 27 DAYS FOOTING 5K 3/4 PCD 28D 10/19/2019 7210 PSI
11/15/2019 16 DAYS FOOTING 5K 3/4 PCD 28D 10/30/2019 4350 PSI
11/15/2019 15 DAYS RTW 5K 3/4 PCD 28D 10/31/2019 5960 PSI
11/15/2019 15 DAYS GF SLAB 6K 3/4 PCD 28D 10/31/2019 5060 PSI
11/15/2019 8 DAYS RTW 6K 3/4 PCD 28D 7/11/2019 4800 PSI
11/15/2019 7 DAYS RTW 5K 3/4 PCD 28D 8/11/2019 4000 PSI
Prepared by : Checked by :
WEIGHT (KG)
11774.68
2397.8
4876.452
25457.184
5438.25
49944.366
REMARKS
82% AT 16 DAYS
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
84% AT 15 DAYS
PASSED
PASSED
nie De Torres
oject Manager
PROJECT TITLE : UMA RESIDENCES
PROPRIETOR : QUEENSTOWN REALTY & DEVELOPMENT
CONSTRUCTION MANAGERS : NQRDI
CONTRACTOR : Scheirman Construction Consolidation Inc.
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
NO DELIVERIES
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
11/20/2019 11D RTW GL E'/1'-3' 5K 3/4 PCD 28D 9/11/2019 4580 PSI
11/20/2019 9D RTW GL A-B/3 5K 3/4 PCD 28D 11/11/2019 3600 PSI
11/20/2019 8D FTG GL C-D/1-2 6K 3/4 PCD 28D 12/11/2019 6080 PSI
11/20/2019 32 DAYS RTW 5K 3/4 PCD 28D 10/19/2019 5960 PSI
11/20/2019 31 DAYS FOOTING 5K 3/4 PCD 28D 10/20/2019 6680 PSI
11/20/2019 30 DAYS FOOTING 5K 3/4 PCD 28D 10/21/2019 6240 PSI
11/22/2019 29 DAYS TANK SLAB 6K 3/4 PCD 28D 10/24/2019 8120 PSI
11/22/2019 15D RTW GL A/1-3 5K 3/4 PCD 28D 7/11/2019 6080 PSI
11/22/2019 14D RTW D-E' C-E' 5K 3/4 PCD 28D 8/11/2019 5510 PSI
11/22/2019 7D COL GL C-E'/0 8K 3/4 PCD 28D 11/15/2019 7480 PSI
11/22/2019 7D S&B PROP-GL 1' 6K 3/4 PCD 28D 11/15/2019 7210 PSI
Prepared by : Checked by :
REMARKS
REMARKS
PASSED
72% AT 9 DAYS
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
rnie De Torres
oject Manager
PROJECT TITLE : UMA RESIDENCES
PROPRIETOR : QUEENSTOWN REALTY & DEVELOPMENT
CONSTRUCTION MANAGERS : NQRDI
CONTRACTOR : Scheirman Construction Consolidation Inc.
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
11/26/2019 17D RTW GL E/1'-3 5K 3/4 PCD 28D 9/11/2019 5420 PSI
11/26/2019 15D RTW GL A-B/3 5K 3/4 PCD 28D 11/11/2019 4000 PSI
11/26/2019 14D FTG C-D/1-2 6K 3/4 PCD 28D 12/11/2019 7190 PSI
11/26/2019 30 DAYS RTW 5K 3/4 PCD 28D 10/27/2019 5670 PSI
11/26/2019 30 DAYS COLUMN 8K 3/4 PCD 28D 10/27/2019 8770 PSI
11/26/2019 8D COL GL A-B/2-3 8K 3/4 PCD 28D 11/18/2019 7760 PSI
11/26/2019 7D FTG GL D-F/2-3 6K 3/4 PCD 28D 11/19/2019 6550 PSI
11/26/2019 29 DAYS COLUMN 8K 3/4 PCD 28D 10/28/2019 9140 PSI
11/27/2019 7D COL GL D-F/2-3 8K 3/4 PCD 28D 11/20/2019 5920 PSI
11/27/2019 7D FTG GL D-F/2-3 6K 3/4 PCD 28D 11/20/2019 6920 PSI
11/27/2019 22D RTW GL B-D/1' 5K 3/4 PCD 28D 5/11/2019 5870 PSI
11/27/2019 29 DAYS COLUMN 8K 3/4 PCD 28D 10/29/2019 9240 PSI
Prepared by : Checked by :
REMARKS
REMARKS
PASSED
80% AT 15 DAYS
PASSED
PASSED
PASSED
PASSED
PASSED
PASSED
74% AT 7 DAYS
PASSED
PASSED
PASSED
rnie De Torres
oject Manager
PROJECT TITLE : UMA RESIDENCES
PROPRIETOR : QUEENSTOWN REALTY & DEVELOPMENT
CONSTRUCTION MANAGERS : NQRDI
CONTRACTOR : Scheirman Construction Consolidation Inc.
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
6/12/2019 Column GF GL A-B/1-3 & GL E/1-2
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
5/12/2019 28mm x 10.5m, PNS 415 262 pcs
5/12/2019 28mm x 12m, PNS 415 271 pcs
5/12/2019 25mm x 6m, PNS 415 173 pcs
5/12/2019 25mm x 10.5m, PNS 415 267 pcs
5/12/2019 25mm x 12m, PNS 415 143 pcs
5/12/2019 28mm x 6m, PNS 415 7 pcs
TOTAL
REMARKS
- rebars arrived on December 2, 2019 but received by the warehouse on December 5, 2019 due to typhoon Tisoy
- no adverse finding prior to unloading
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
Prepared by : Checked by :
WEIGHT (KG)
13296.5
15718
3999.8
10802.8
6612.32
203
50632.42
to typhoon Tisoy
REMARKS
rnie De Torres
oject Manager
PROJECT TITLE : UMA RESIDENCES
PROPRIETOR : QUEENSTOWN REALTY & DEVELOPMENT
CONSTRUCTION MANAGERS : NQRDI
CONTRACTOR : Scheirman Construction Consolidation Inc.
A. CONCRETE
DATE CONCRETE POURED POST CONCRETE (after stripping)
B. DELIVERY OF MATERIALS
DATE ITEM DESCRIPTION QUANTITY
C. TESTING
DATE TESTED STRUCTURE/LOC DESIGN DATE SAMPLED TEST RESULT
Prepared by : Checked by :
REMARKS
REMARKS
rnie De Torres
oject Manager