Professional Documents
Culture Documents
Monitoreo de Bombas
Monitoreo de Bombas
Monitoreo de Bombas
Cover Story
Report
Condition Monitoring
Methods for Pumps
Applying condition monitoring tests
to pumps can save costs
by optimizing overhaul scheduling
Ray Beebe several condition-monitoring tests
MCM Consultants Pty Ltd. and for pumps, and discusses how to use
Monash University these predictive-maintenance meth-
ods to estimate the increased power
P
umps are among the most com- consumption that results from pump
monly used machines in the wear (Figures 1 and 2).
chemical process industries Experience in the field or with an
(CPI). Condition monitoring original equipment manufacturer
tests and predictive maintenance can (OEM) may help pump operators de-
help pump operators determine when termine when to undertake overhauls,
to overhaul pumps in a way that mini- but others may not have an idea of
FIGURE 1. Pump wear, such as that
mizes costs. Despite pumps’ ubiquity how to determine the optimal time, shown on this pump impeller, can lead
and large energy demands, however, because many pump textbooks, even to reduced pump performance
relatively little information is avail- excellent and widely used ones, have
able on how to apply predictive main- failed to cover the application of con-
tenance approaches and condition dition monitoring to pumps in detail,
monitoring to process pumps. and information in this area has been
Pump overhauls may occur on a fixed lacking until recently [1, 2].
time schedule or as a result of a specific It is hoped that the tools presented
breakdown, but neither case necessar- in this article will help asset managers
ily represents the most cost-effective and engineers improve management
policy. In cases where deterioration in of pump assets to provide capacity for
the performance of a centrifugal pump production, as well as improve energy
causes a drop in plant production, efficiency and minimize greenhouse-
pump overhaul is readily justified, be- gas emissions. Although the article
cause the cost of performing the over- focuses on pumps, the optimization
FIGURE 2. The degree of pump wear
haul is usually small compared to the approach described here can also be ap- is expressed as the percent reduction
losses from reduced production. How- plied to other plant equipment where in total head
ever, when pump performance deterio- deterioration results in efficiency loss,
rates due to wear and the only effect is and where energy consumption can be detect each of the pump degradation
increased power consumption (with no measured or estimated. modes that are either experienced or
discernable effect on production), the expected. Common pump-monitoring
question of when to perform an over- Choosing monitoring methods methods include the following:
haul becomes important. The extent and specific effects of in- • Vibration monitoring and analy-
The right time to overhaul that ternal wear in centrifugal pumps vary sis: probably the most widely ap-
minimizes cost can be calculated according to the characteristics of the plied method of condition monitor-
from predictive maintenance test re- liquid being pumped, as well as the ing for rotating machines in general,
sults. The use of condition monitoring type of pump and its operating duty. and suited to detect such faults as
methods ensures that pump over- Some pumps last for years, while oth- unbalance, misalignment, looseness
hauls aimed at restoring performance ers last for only months. • Sampling and analysis of lubri-
are executed when they are actu- Pump monitoring methods (where cants for deterioration and wear
ally necessary. This article describes justified) should be chosen that can debris: relevant for bearings and
34 CHEMICAL ENGINEERING WWW.CHE.COM SEPTEMBER 2012
18
16
Reduction in head, %
14
12
10
8 FIGURE 3. The A series of test readings at steady
degradation of conditions, at about 15-s intervals, is
6 pump perfor-
mance can be
sufficient. Average values are plot-
4
shown by the per- ted. Speed must also be measured for
2 cent decrease in variable-speed pumps, and the head-
0 total head at nor- flow data must be corrected to a stan-
0 500 1,000 1,500 mal-duty low, and dard speed using the affinity laws for
Days in service can be determined
by head-low test- pump performance.
12 Field tests sometimes yield results
ing (Top graph,
Reduction in head at normal flow, %
FIGURE 4.
20 Condition
L/S monitoring of a
High critical
high-energy mul-
tistage pump can
High alarm be accomplished
by measuring
the balance-
Leakoff flowrate
14.6
device leakoff
low. (Note:
lows shown are
Pump overhauled
corrected to a
standard pump
speed)
5
L/S
J J A S O N 1994 M A M J J A S O N 1995
Months
Thermodynamic method method would be more attractive eco- method is relatively inexpensive.
Another method of pump monitoring is nomically if no special tapping points Figure 4 shows an example of using
to measure the temperature rise of the were required. Research at Monash leakoff flow to schedule pump over-
liquid through the pump. This measure- University (Gippsland, Australia cam- hauls of boiler-feed pumps at a power
ment is a reflection of the inefficiency pus) on high-head pumps using special plant. Flows are read manually, and
of the pump. Because the differential semiconductor temperature probes on trends plotted using a database pro-
temperature is small, great care is re- the outside surface of the piping (even gram. Note that here the balance flow
quired to measure it. For example, ef- when covered with insulation) gave (15 L/s) corresponds to about 10% of
fects of recirculation at the pump inlet usable results, provided the pump was the regular duty flow, and consumes
and outlet must be eliminated and allowed to run at steady operating con- about 250 kW of extra power. When
thermodynamic tests are not possible ditions for 30 min to allow the piping added to the likely internal recircu-
at low or zero flow. Pump efficiency temperature to stabilize [4]. lation, this would mean that an even
can be calculated from the measured The empirical expression shown larger proportion of the power ab-
data of inlet temperature, the differen- below gives the percent efficiency for sorbed is being wasted.
tial temperature and the head. If the pumps at up to 54°C. The expression The boiler-feed pumps are variable-
efficiency changes over time, compari- includes a correction for the isentropic speed units, and other tests show that
sons can be made on plots of efficiency temperature rise. Total head is in kPa, the measured flows must be corrected
versus head. For high-head pumps, an and temperatures are in °C [5]. in direct proportion to the speed. On
allowance must be made for the isen- 100 a set of pumps of a different design at
tropic temperature rise, which occurs Temp rise another location, both head-flow and
as a result of pressure increase [2]. 1 − 0.003( InletTemp − 2 ) + 4,160 Total heead balance flow were measured for some
Commercially available devices are years, but no correlation was found be-
widely used for the thermodynamic tween the two.
method, especially in the water indus- Measurement of balance flow On still another pump type, of the
try [3]. For the installation of pressure Multistage pumps with their impellers 11 stages, the head-flow performance
and temperature probes, tappings facing in one direction usually have a was determined to be well below the
for measuring suction and discharge balance disc or drum arranged such datum curve. As the pump was dis-
must be two pipe diameters away from that the final-stage discharge pressure mantled, measurements showed that
pump flanges. Tong-type detectors are counteracts the axial thrust on the the interstage clearances were not
placed to measure motor power. Pump shaft line. Another method for pump worn. A condition-monitoring credibil-
efficiency is then found from the pre- condition monitoring is to measure the ity crisis was averted when the bal-
cise measurement of the head and leakoff from the balance device [6]. ance seat area was reached and found
temperature rise through the pump. The basis of the method is that if to be severely eroded from water leak-
By assessing motor losses, the power increased wear in the annular space ing past the valve seat. Balance flow
absorbed by the pump can be com- of the balance device is evident from had obviously been very high. For the
puted, and from these data, the pump increased leakoff flow, then the inter- best monitoring, it is therefore desir-
flow can be found. stage clearances must also be worn. able that both head-flow and balance
For condition monitoring, tests at Because the leakoff line is quite small flow should be measured, particularly
around the normal operating point are compared to the pump main flow pip- if the balance area can be separately
usually sufficient. The thermodynamic ing, a permanent flowmeter for this dismantled in the field.
36 CHEMICAL ENGINEERING WWW.CHE.COM SEPTEMBER 2012
900
Site test –
Head, m
800 n ew pum
p
A
700
Test points – worn pump C D
600
3,000 FIGURE 5. After some service, the data points
Head-low- marked on the diagram as “Test points
2,300 E power char-
acteristics of — worn pump” indicate that internal
Power, kW
2,000 2,150 B a new pump wear has occurred. When worn to this
differ from the extent, the operating point moves to
data points for Point C (the system resistance curve
a worn pump.
Point C to D
moves lower when the throttle valve
0 200 400 600 800 1,000
shows internal is opened further).
Flow, m3/h
leakage low The increased power required in the
worn condition can be estimated by
FIGURE 6.
The point that
extending from the head-flow curve at
Optimum time to overhaul
optimizes the constant head from the operating point
time to pump to Point D, and then dropping straight
Cost of overhaul/month overhaul can down to the point where the the power-
Total cost/month be shown flow curve intersects for the new con-
Cost per month, $
Head, m
A C 600
Head at 1,490 rpm (new) FIGURE 7
Power, kW
= $3,246/mo (using an average month 80
Head at 1,660 rpm (worn) For variable-
as 720 h). 500
speed pumps,
As the time that the pump has been 6 0 the effect of
operating now is 24 months, $3,246 ÷ rpm (new) 425 400 wear on power
t 1,490
24 gives the average monthly cost rate B Power a 325 required for
of deterioration as $135/mo. 300
operation is
more dramatic
The optimum time for overhaul (T) is than constant-
calculated [7] from Equation (1). 1,000 1,200 1,400 1,600 1,800 speed pumps
Flow, m3/h
2×O
T=
C (1) of delaying overhaul is thus the differ- no production will be lost. However,
where O = cost of overhaul and C = ence between the two ($10,811). power consumed will increase more
cost rate of deterioration. This calculation is only correct if the dramatically for a given wear state
This calculation yields an optimum wear progresses at a rate that increases than that for a constant-speed pump.
time to overhaul of the pump of 27.2 uniformly with time. As Figure 3 shows, To estimate the power required in
months. It is better to calculate and this is not unusual. Information may the worn state, the head-flow curve
plot the average total cost-per-month not be available to make any other as- must be drawn for the current higher
values for a range of times. Doing so sumption, but decision makers have to speed in the new condition. Select a
will allow the cost impact of undertak- start somewhere. Other formulas apply head-flow point on the original, new-
ing the repairs at another time (such for nonlinear rates of change [7]. condition curve, and correct it to the
as at a scheduled plant shutdown), to Some notes and additional points to higher speed by multiplying the flow
be seen clearly. consider regarding these calculations by the speed ratio and multiplying
are as follows: the head by the square of the speed
Average cost, month by month • Some relatively small pumps may ratio. Repeat this for several other
For an example, use the time period never fully justify an overhaul on points at flows above regular-duty
of 22 months. The average cost of con- savings in energy use alone, but the flow to draw the new condition head-
ducting the overhaul is now $50,000 ÷ overhaul may be justified on reduced flow curve.
22 = $2,273/mo. plant-production rate Follow the same method and calcula-
The average cost of extra energy con- • The method does not apply to pumps tions as in the previous section to find
sumed is then ($135 × 22) ÷ 2 = $1,485/ of high specific speed that show lit- the time for overhaul at minimum total
mo. Total average cost per month is the tle change, or even a reduction, in cost. The operating point is projected
sum of these two figures: $3,578/mo. power with increased flow from the worn curve to the new curve
Since pump wear progresses linearly, • If a pump varies in its duty, then the at the same speed as the worn curve.
the cost per month also is linear and the energy usage would be corrected in Figure 7 shows the performance of
average can be obtained by dividing by proportion a variable-speed pump. When new,
two (at the starting time, the value is • The cost of electricity to be used operation at 1,490 rpm meets the de-
zero, and the average over the time pe- here may vary with the power sup- sired duty flow, at operating Point A,
riod is given by the ending value minus plier’s tariff structure. The cost may requiring 325 kW of power (Point B).
the start value, divided by two). be less in stepped blocks with higher After some period of service, internal
Repeat this calculation for several consumption levels for the plant, or leakage has increased to the extent
months (the use of a spreadsheet can a peak-demand charge may apply that the pump must run at 1,660
be helpful) and look for the minimum Pump deterioration does not af- rpm to meet the required duty (still
total cost, which is at 27.2 months. If fect production (variable-speed Point A).
plotted as cost per month against time, control): In situations where a pump To estimate the power required now,
the resulting curves will show that the has variable-speed control, and perfor- the head-flow curve must be drawn for
cost per month of overhaul drops over mance deterioration does not (at least the higher speed in the new condition.
time, and the cost of extra energy in- initially) affect production, the follow- Several head-flow points are selected
creases with time. ing steps can be taken. For a pump and corrected to the higher speed.
The time value of money could also where the speed is varied to meet To do this, multiply each flow by the
be taken into account, if required. Usu- its desired duty, the effect of wear on speed ratio, and multiply each match-
ally the total cost curve is fairly flat power required is much more dramatic ing head by the speed ratio squared.
for ±20% or so. The calculations can be than for the case of a constant-speed, This will result in the head-flow curve
easily set up using a spreadsheet. throttle-controlled pump. This is be- at 1,660 rpm in the new condition.
If the overhaul was delayed until cause the power usage increases in pro- Project across from the head at the
the 30-month mark, for example, then portion to the cube of the speed ratio. duty flow (Point A) to meet the head-
the accumulated cost of lost energy Unless the pump output is limited flow curve at 1,660 rpm (new condition;
would have reached $135 × 0.5 × 30² by the pump reaching its maximum Line C in Figure 7). Projection down-
= $60,750. At 27.2 months, the cost is speed, or by its driver reaching its ward at a constant flow leads to the in-
$135 × 0.5 × 27.2² = $49,939. The cost highest allowable power output, then creased power required at 425 kW. The
38 CHEMICAL ENGINEERING WWW.CHE.COM SEPTEMBER 2012
extra power is 31% more. (This pump the optimization calculations as ex- shut-off head obtained on the test.
is driven by a steam turbine, so power plained in the above section. The trace is now in the position of
consumption cannot be measured). Head-power-flow characteristics the “worn” head-flow curve, which is
The same calculations as those pre- in the “new” state are needed as be- being experienced. Exactly the same
sented in the previous section are fol- fore, and the operating point must be process as that explained above can
lowed to find the time to an overhaul known. Note the power required at the be followed. ■
that minimizes total cost. operating point, as before. Edited by Scott Jenkins
Make an overlay trace of the head-
Using shut-off head test results flow curve in the new condition. Place Author
The shut-off head test information it over the “new” curve and move to Ray Beebe (Phone: +61-408-
178-261; Email: ray.beebe@
can also be used to estimate the power the left horizontally until the curve monash.edu) works part-time
since retiring after a 20-year
used in the worn state, and to perform cuts the head axis at the value of the tenure as a senior university
engineering lecturer at Mo-
rity and Maintenance), September 25–27, nash University (Gippsland
References 2002, Cairns, Australia. campus, Victoria, Australia)
1. American National Standards Institute. and an engineering consul-
American National Standard for Centrifugal 5. Whillier, A. Site testing of high-lift pumps in tant with 28 years of experi-
and Vertical Pumps for Condition Monitor- the South African mining industry. IMechE ence in the power generation
ing. ANSI/HI 9.6.5-2000. paper C155/72, Conference on Site testing of industry. His commitment
Pumps. London, pp. 209–217. to sharing knowledge and experience has led to
2. Beebe, R.S. “Predictive maintenance of
pumps using condition monitoring.” Elsevier, 6. Karassik, I.J. and others (Eds.). “Pump writing and presenting at many conferences and
London. 2004. Handbook” McGraw-Hill, New York, 2001. conducting training courses in condition moni-
toring around the world. His second book gained
3. Robertson, M. and others. Continuous Pump 7. Haynes, C.J., and Fitzgerald, M.A. Schedul- the George Julius Medal of Engineers Australia
Performance Monitoring and Scheduling. ing Power Plant Maintenance Using Perfor- for the best publication in mechanical engineer-
IMechE Symposium — Energy Savings in mance Data, ASME Paper 86-JPGC-Pwr-63, ing in 2004. His third book, on condition moni-
Pumps and Pumping, London, 2007. 1986. toring of steam turbines will be published later
4. Beebe, R.S. Thermometric testing of high- this year. He is an active volunteer in rotary and
8. Stepanoff, A.J. “Centrifugal And Axial Flow scouting. Beebe received a diploma of mechanical
energy pumps using pipe surface measure- Pumps.” John Wiley & Sons. Hoboken, N.J.
ments. Paper presented at the 3rd ACSIM engineering from the Caulfield Institute of Tech-
1957, and Figure 1-77A of the PDF figures nology, and an M.S. in engineering science from
(Asia-Pacific Conference on Systems Integ found at www.pumps.org. Monash University.
Multidechlorobac
Rapid and sustainable
decontamination of
soil and groundwater
The safe and validated bacterial
• Environmental Management: Air-Pollution Control
culture for the anaerobic degradation
• Environmental Management: Wastewater and of chlorinated ethanes and ethenes
Groundwater Treatment in soil and groundwater.
• Fluid Handling Degradation of 100 000 μg 1,2-DCA/L
in 10 days in the ield!
• Gas-Solid and Liquid-Solid Separation
• Liquid-Liquid and Gas-Liquid Separation
• Managing Bulk Solids
17792