Professional Documents
Culture Documents
GGPS Taparghai Rehabilitation Work
GGPS Taparghai Rehabilitation Work
Project
Project Short Title Description Project Sector
Electrification 80,311
Manholes 37,969
1 1 1 1
174 Cft
45 Cft
219 6.07 1329.33
58 cft
15.0 cft
100 cft
173.00 12.32 2131.36
35 cft
12.19 cft
59.38 cft
27.07 cft
133.635 191.4 25572.39
2.25 cft
8.00 cft
33.44 cft
43.6925 246.6 10776.32
27 cft
9.75 cft
19.5 cft
9.56 cft
27.56 cft
16.88 cft
110.25 210.5 23206.52
174.56 cft
106.88 cft
12.00 cft
293.44 218.11
26.25 cft
3.38 cft
29.63
263.81 218.11 57540.14
35 Sft
5 Sft
40 495.59 19575.81
50 sft
100 sft
100 sft
30 sft
280 Sft 158.21 44298.8
180 Sft
180 Sft
50 Sft
410 Sft 19.98
35 Sft
5 Sft
40 Sft
371 Sft 19.98 7402.59
231 Sft
122 Sft
353 Sft
Sft
35 Sft
5 Sft
40 Sft
313.75 Sft 23.45 7357.4375
180 Sft
180 Sft
50 Sft
410 Sft
Sft
35 Sft
5 Sft
40 Sft
370.5 Sft 7.37 2730.585
221 Sft
117 Sft
338 Sft
18 Sft
2 Sft
20 Sft
318 Sft 20.95 6656.8625
231,331.00
Rehabilitation of GGPS Taparghai, Ladha, South waziristan Agency
BOQ: Main Building Work (Rehab work)
Depth/
Length Width
S# Description Ref: MRS Height No Quantity Unit Unit Rate Total Cost Remarks
(ft) (ft)
(ft)
1 Removing of plaster from existing walls 04-48-b
Long wall 25 11 1 275.00 sft
Total 275.00 sft 2.25 618.75
Cement plastering 1:4 up to 20' height 3/4"
2 thick inner side 11-09-c
Long wall 25 11 1 275.00 sft
Net quantity of plaster 275.00 cft 26.92 7403.00
25-10 and
3 Heavy steel trusses
25-11
T/Beam 4 x 2 x 32 x 2.5 640 Kg
2 x 49 x 19 1862 Sft
2 x 28 x 2 112 Sft
2 x 48 x 1 96 Sft
13-06-b-1 &
8 Ceiling paint work
13-06-b-02
0.00 sft
Deduction -
Door D-1 for Class Room 3.75 7.00 2.00 52.50 sft 672.57 35,309.93
18
Provied & Fix GI wire gause 22SWG,mesh per
sq in fixed to steel window complete.
Total
Total
4 RCC in roof slab, beam, column, & other structural 14.75 9 0.42 1
members, insitu or precast (1:2:4) 06-06-a-03
P/F:Inpositiondeformedreinforcementbars,ofminimu
m40000PSIyieldstrength,ofanysizeanddiameteri/cstra
5 ightening,cutting,bending,placingandbindingandprovi
dingofspacersetc.Completeasperspecificationsand
instructions of Engineer
Grant Total
adha, South waziristan Agency
and kitchen (Rehab work)
49.50 sft
99.38 sft
148.88 cft 26.92 4007.72
5.28 cft
0 cft
33.00 sft
0.00 sft
55.76 cft
-
23.38 sft 672.57 15,721.32
108 sft
99 sft
33 sft
126 sft
99 sft
38.5 sft
503.5 sft
23.375 sft
25.5 sft
48.875 sft
454.625 sft 3.58 1627.5575
195.75 sft
195.75 sft
23.375 sft
25.5 sft
48.875 sft
146.875 sft 23.46 3445.6875
82,626
82,626
Rehabilitation of GGPS Taparghai, Ladha, South waziristan
BOQ: Quarter Main Building Work (Rehab w
Depth/
Length Width
S# Description Ref: MRS Height No
(ft) (ft)
(ft)
1 Removing of plaster from existing walls 04-48-b
Long wall 10 10 2
Short wall 16 12 0
Short wall 11 12 0
Total
Cement plastering 1:4 up to 20' height 3/4"
2 thick inner side 11-09-c
Long wall 10 10 2
Net quantity of plaster
Painting of old surface for Doors, Windows/Bathroom 13-05-c-01 &
3 13-05-c-02
Door and ceiling.
Windows 6 6 3
Room Ceiling 11 12 1
Room Ceiling 15 11 1
8
Provied & Fix GI wire gause 22SWG,mesh per
sq in fixed to steel window complete.
Grant Total
adha, South waziristan Agency
uilding Work (Rehab work)
200.00 sft
0.00 sft
0.00 sft
200.00 sft 2.25 450.00
200.00 sft
200.00 cft 26.92 5384.00
108.00 Cft
132.00 Cft
165.00 Cft
41.25 Cft -
0.00
108.00
0.00
264 sft
242 sft
0 sft
330 sft
242 sft
0 sft
206.25 sft
36 sft
0 sft
1320.25 sft
55.25 sft
108 sft
0 sft
163.25 sft
1157 sft 3.58 4142.06
639 sft
639 sft
0 sft
108 sft
108 sft
531 sft 23.46 12457.26
143,063
143,063
Rehabilitation of GGPS Taparghai, Ladha, South waziristan Agency
BOQ:Land Development
S# Description Ref: MRS Length (ft) Width (ft) Depth (ft) No Quantity Unit Unit Rate Total Cost Remarks
P/F Precast Concrete 7000 psi TUFF Tiles over bed of 2"
3 thick sand & 4" thick brick ballast comp or as per instruction 10-45 40 20 1 800 sft 0
engr.incharge
S# Description Ref: MRS Length (ft) Width (ft) Depth (ft) No Estimated Unit Unit Rate Estimated Cost Remarks
Quantity (PKR)
1 Supplying and fixing 18 SWG MS sheet gate with angle iron 25-47-b 7.00 8.00 1.00 56.00 sft
frame (2"x2"x3/16") with side window, lock, painting etc
672.57 37663.92
2 Cement plastering 1:4 up to 20' height 1/2" thick inner side 11-09-b 130.00 10.00 1.00 1300.00 sft
19.98 25974.00
3 White washing three coats external side 11-25-a-03 130.00 10.00 1.00 1300.00 sft
3.73 4851.73
4 Three coat of Weather sheet 13-38- 130.00 10.00 1.00 1300.00 sft
a+13-38-b
23.46 30498.00
S# Description Ref: MRS Estimated No. Unit Unit Rate Estimated Remarks
Quantity Cost (PKR)
Excavation in foundation of building, bridges etc complete : in
1 ordinary soil 03-23-b 108.00 2.00 Cft 6.070 1311.12 2.00
4 Cement plaster 1:4 upto 20' height 1/2" thick 11-09-b 60.00 2.00 Sft 19.980 2397.60 2.00
Providing and Fixing 'P' trap including GI grating & PCC chamber
2 4" of cast iron 14-32-a 3 Each 914.5 2743.50
10 Providing and Fixing brass ball float valve 1.25" dia 14-48-g 3 Each 665.1 1995.39
Providing and Fixing of poly dex high pressure PPR(green)
11 including testing ect complete 20 mm(including all special)etc 14-71-b 80 Rft 121.8 9744.80
12 Providing and Fixing CP bib-cock, heavy type : 1/2" 14-24-b 6 Each 567.5 3405.18
P/F polyethylene Water Tank 500 gallons (vertical) on existing
13 over head base. 14-69-b-03 1 Each 12553.8 12553.79
14 Soakage pit(6'dia x 15' deep) 23-11 2 Each 16376.3 32752.50
15 Septic Tank(int size: 7x2'x5') complete 23-10 2 Each 15957.2 31914.44
Wiring of light/fan/call-bell point in 3/0.029 PVC insulated bare cable in PVC pipe
1 15-50 30 30 Each 850.55 25516.5
recessed
Including quarter
Supply and Erection best quality AC ceiling fan complete with GI rod, canopy, asia, breeze, Climax, Millat, National
2 15-68-c 10 10 Each 3845.5 38455.3
blades & regulator : 56" sweep and pak fan are the approved makes
Supply and Erection fluorescent tube light fitting including 4' rod, choke, starter,
3 15-61-a 20 20 Each 211.05 4221
flexible wire etc. : Single / Energy sever
Supply and Erection MS sheet box of 16 SWG, 4"deep with 3/16" thick Bakelite
4 15-09-f 2 2 Each 395.63 791.26
sheet top etc. complete : 12"x14"
5 Supply and erection girder clamp hook, 5/8" dia for hanging ceiling fans 15-25 10 10 Each 318.11 3181.1 0
3600
6 Supplying and erection single phase imported auto circuit breaker 6 AMP 15-71-a 2 2 Each 536.49 1072.98
961
7 Supplying and erection single phase imported auto circuit breaker 30 AMP 15-71-d 2 2 Each 624.94 1249.88
Special earthling of iron/metal clade witches etc. with copper wire no 8 SWG in GI
8 15-41 1 1 Each 5822.66 5822.66
pipe 1/2" dia
2 NSI Gravel Filling 6" Thick Compacted Gravel Filling 6" Thick Compacted 7 5.67 0.5 1 19.85 Cft 35.00 694.58
3 NSI Gravel Filling 4" Thick (Open Area) Gravel Filling 4" Thick (Open Area) 7 5 0.33 1 11.55 Cft 35.00 404.25
Plain Cement Concrete including placing,
4 06-05-h compacting, finishing & Curing (Ratio PCC (1:3:6) 4" thick 7 5 0.33 1 11.55 Cft 165.98 1,917.07
1:3:6)
3 S/F Dust bin, 18 SWG GI Sheet 1.5' Dia 3' high Custom made NSI
Drum with 2'' Dia 18 SWG MS Pipe supports including delivery,
fixing, painting (each dustbin different color) and writing etc.. as
to specified for categorised wastes as per engineer direction
Total
5 Supply and fixing Sign Board 4'x3' size with 18gauge iron sheet, NSI
painting etc, Completed in all respect as shown in Drawing
4 4 Cft
4 Cft 6.07 24.28
4 2 cft
2 cft 191.4 382.7
2 2 No
38,407.00