CONSTRUCTION OF NEW DUAL GAUGE SINGLE RAILWAY LINE FROM DOHAZARI TO COX'S BAZAR VIA RAMU (LOT - 01)

DRAWING PREPARATION SCHEDULE


Toma Construction & Co. Ltd.
Project Start: Thu, 6/4/2020
Display Week: 1 Week - 01 Week - 02 Week - 03 Week - 04 Week - 05 Week - 06 Week - 07 Week - 08
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
ASSIGNED
TASK START END T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
TO

CULVERTS
Culvert No - 41 Moklas 6/4/20 6/4/20
Culvert No - 42 Moklas 6/7/20 6/9/20
Culvert No - 78 Jobayar 6/4/20 6/13/20
Culvert No - 50 Moklas 6/10/20 6/13/20
Culvert No - 51 Jobayar 6/14/20 6/16/20
Culvert No - 53 Jobayar 6/17/20 6/20/20

RIVER TRAINING WORK


Bridge - 03 Moklas 6/5/20 6/6/20
Bridge - 22 Moklas 6/14/20 6/20/20