Section VI.

F Equipment Requirment (ER)
Classification Requirment
For Tunnel For Road &  Maufacture Requirment‐1 Requirment‐2 Requirment‐3 Requirment‐4 Requirment‐5 Requirment‐6
Item
Work Item Equipment Type And Characterstics Certificate Exhuast Gas Exhuast Gas
 No. Finance Act 2017 Operational  Exhuast Gas
On‐Road Off‐Road On‐Road Off‐Road shall be (Minimum) Level Level
22 Miscellaneous Experance  Level (Euro 3)
provided (Table 1) (Table 2)
A. Equipment For Tunnel Excavation Works‐ Man Tunnel
1 Perforation Wheel Jumbo drill 2 or 3 booms with basket   2 N/A 3 projects N/A fulfill N/A
2 Finishing Hydrolic large range breaker 1,300kg dass  2 N/A N/A N/A N/A fulfill
3  Surface after Backhoe: Crawler‐type   2 N/A N/A N/A N/A fulfill
4 Loading loading machine   2 N/A N/A N/A N/A fulfill
5 Mucking drum truck   N/A N/A fulfill N/A N/A

Concrete spraying machine: Wet type sprayer 10 N/A 3 projects N/A fulfill N/A


6 Shot‐Concrete & robot integrated type  
7 Truck mixture  2 N/A N/A fulfill N/A N/A
8 Concrete plant   2 N/A N/A fulfill N/A N/A
9 Mortar injection machine  2 N/A N/A N/A N/A fulfill
Rock Bolt &
10 Truck for mountaining the mortar injector  2 N/A N/A fulfill N/A N/A
fore boring
11 Truck equiped with crain  1 N/A N/A fulfill N/A N/A
B. Equipment For Tunnel Excavation Works‐Evacuation Tunnel
12 Perforation Wheel Jumbo drill 2 booms with basket   2 N/A 3 projects N/A fulfill N/A
13 Loading loading machine   2 N/A N/A N/A N/A fulfill
14 Mucking drum truck   4 N/A N/A N/A N/A fulfill
Concrete spraying machine: Wet type sprayer 2 N/A 3 projects N/A fulfill N/A
15 Shot‐Concrete & robot integrated type  
16 Truck mixture  2 N/A N/A N/A N/A fulfill
17 Mortar injection machine  2 N/A N/A N/A N/A fulfill
Rock Bolt &
18 Truck for mountaining the mortar injector  2 N/A N/A fulfill N/A N/A
fore boring
19 Truck equiped with crain  1 N/A N/A fulfill N/A N/A
C. Equipment For Tunnel Construction Works
20 Bull dozer: 15 ton class  2 N/A N/A N/A N/A fulfill
21 bull dozer: 20 ton class  2 N/A N/A N/A N/A fulfill
22 tyre roll: 8‐20 ton class  2 N/A N/A N/A fulfill N/A

Mobile dust collector: Feeding & suction
2 N/A 3 projects N/A N/A fulfill
collection method, miniumum capicity 
23 Tunnel 2400 m³/min.  
24 Construction Concrete pump:    4 N/A N/A N/A N/A fulfill
25 High elivation work vehicles: basket type  2 N/A N/A fulfill N/A N/A
26 High elivation work vehicles: stage type  2 N/A N/A fulfill N/A N/A
27 Rough terrain cran:  1 N/A N/A N/A N/A fulfill
pump equipment for injection(with flow meter) 3 N/A N/A N/A N/A fulfill
28 for steel pipe forepilling system 
29 Sliding form for lining automatic scaling equipment   2 N/A N/A N/A N/A fulfill
D. Equipment For Earth Works And Structures Construction Works
30 crushing plant   1 N/A N/A N/A N/A fulfill
31 motor grader   2 N/A N/A N/A N/A fulfill
32 steel wheel vibratory/static roller 10‐20 ton class   2 N/A N/A N/A N/A fulfill
33 Road and pneumatic roller:8‐10 ton class  2 fulfill N/A N/A fulfill N/A
34 Structure asphalt mix plant   1 fulfill N/A N/A N/A fulfill
35 Construction asphalt concrete finisher  1 fulfill N/A N/A N/A fulfill
36 concrete paver    1 N/A N/A N/A N/A fulfill
37 drum truck  5 fulfill N/A fulfill N/A N/A
38 Road cutting machine for rumble strips   1 N/A 1 projects N/A N/A fulfill