PROJECT NAME: SOUTH PACIFIC INC

UPDATED AS OF: 6/18/2020


(ACTUAL JULY
CONCRETE PLAN PERIOD REMARKS
POURED) W1 W2 W3

3000 PSI - 8.25 Bags/m3

A. WAREHOUSE 1-2-3
Ground Slab 1946 cu.m.
Sub-total 1946 cu.m.
B. SITE DEVELOPMENT
Perimeter Fence
Footings 322 cu.m. 49 cu.m. 34.125
Retaining walls++Columns+CounterFort 389 cu.m. 51 cu.m. 42.25
ROADS AND ACCESS 1170 cu.m.
Curbs & Gutter 30 cu.m.
Pipe Trench 21 cu.m.
Pathways 16 cu.m.
Sub-total 1948 cu.m.
C. ELEVATED HELIPAD
2ND FLOOR
SUSPENDED SLAB 41 cu.m. 40.90
HELIPAD/ROOF DECK
SUSPENDED SLAB 37 cu.m.
Sub-total 78 cu.m.
C. BLASTING & PAINTING EQUIPMENT PAD
EQUIPMENT PADS
PLINTHS AND PEDESTALS 30 cu.m. 7.5
Sub-total 30 cu.m.
Total Volume 4002 cu.m. 34 cu.m. 0 cu.m. 42 cu.m.
Total Cement, T1 44019 Bags 375 Bags 0 Bags 465 Bags

Prepared by: Note:

Concrete Schedule is only tentative or it may change its schedule

Mark Roger R. Huberit II


PROJECT MANAGEMENT
2020
LY AUGUST SEPTEMBER
W4 W5 W6 W7 W8 W9 W10 W11 W12

34.125 34.125 34.125


42.25 42.25 42.25

37 cu.m.

7.5 7.5 7.5

34 cu.m. 0 cu.m. 42 cu.m. 34 cu.m. 0 cu.m. 42 cu.m. 34 cu.m. 0 cu.m. 42 cu.m.


375 Bags 0 Bags 465 Bags 375 Bags 0 Bags 465 Bags 375 Bags 0 Bags 465 Bags

ative or it may change its schedule of concrete casting; it is always dependable on weather conditions.