General Definitions: I I R L V I L I

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

12.

2
Cross references within the classification tables are given in the form:
14. General definitions
14.1
Work Number Number Number Number Where the rules require work to be described as curved with the radii stated
Section from first from second from third from fourth details shall be given of the curved work including if concave or convex,
number column column column column if con ical or spherical , if to more than one radius and shall state the radius
or radii.
Example:
020: 2. 2. 2. 1 14.2
Excavation and filling The radius stated shall be the mean radius measured to the centre line of
Excavating the material unless otherwise stated.
To reduce levels
Maximum depth ~ 1.00m
Commencing level stated where > 0.25m below existing
ground level.

12.3
An asterisk within a cross reference represents all entries in the column in
which it appears.
12.4
The digit 0 within a cross reference represents no entries in the column in
which it appears.

13. Work to existing buildings


13.1
Work to existing buildings shall be so described. Such work is defined as
work on, or in, or immediately under work existing before the current project.
13.2
The additional rules for work to existing buildings are to be read in conjunc-
tion with the preceding rules in the appropriate Work Sections.
13.3
A description of the additional Preliminaries/General conditions which are
pertinent to the work to the existing building shall be given, drawing
attention to any specific requirements due to the nature of the work.