Q1. A firm of landscape gardners is asked to quote for constructing a garden on a new site. The
activities involved are shown in the table.
*Note also that the patio can not begin to be laid until 2 days after the start of the building of
the retaining wall
1
Q2. Two different forecasting techniques (F1 and F2) were used to forecast demand for cases of bottled
water. Actual demand and the two sets of forecasts are as follows:
Q3. Eighty units of end item X are needed at the beginning of week 6, and another 30 units are needed
at the beginning of week 8. Prepare a material requirements plan for component D. D can only be
ordered in whole cases (50 units per case). One case of D is automatically received every other
week, beginning in week 1 (i.e., weeks 1, 3, 5, 7). Also, there are 30 units of B and 20 units of D now
on hand. Lead times for all items are a function of quantity: one week for up to 100 units, two
weeks for 101 to 200 units, three weeks for 201 to 300 units, and four weeks for 301 or more units.
2
Q4. The following table contains figures on the monthly volume and unit costs for a random sample of
16 items from a list of 2,000 inventory items at a health care facility: