Professional Documents
Culture Documents
ملاحظات هامة جدا من الاستاذ سمير سويلم
ملاحظات هامة جدا من الاستاذ سمير سويلم
ملاحظات هامة جدا من الاستاذ سمير سويلم
fee to get
3- If funding issues with the funding Bank occurred, funding limit reconciliation is recommended.
4- Involving negative stakeholders in decision making is an excellent way to behave with resistance.
5- Crashing after crashing results in more and more requirements of communication efforts . That is why PM
6- More departments have relations with your project, classify them into groups and collect each group
7- What are inputs for the following proccesses? 1) Develop project charter. 2) plan human resources
8- The stakeholders informed you that the previous project manager was fired as he was not communicating
9- Calculating communication channels objective is to indicate the complexity of the communication in the
project .then the communication plan limits who will communicate with who . This means not all the
10- If a supplier replaced, product verified, all deliverables met. PM shall perform procurement audit &
11- PM sent information to project team through Aconex but not all members received the information. To
%100 أما عند الحدوث فان االحتمال أصبح%100 عند حدوث خطر معرف مسبقا يزيد االحتياطي عن المخطط الن المخطط اقل من-12
الباقية و مقارنتها بالمطلوب بعد حدوث الخطر و في نفس الوقت تتغير حالة بعض منreserves و ذلك له دور كبير في إعادة حساب الـ
أوال ثمreserves مخاطر المشروع األخرى مثال مخاطر جديدة و مخاطر أخرى يقل االحتياطي المطلوب لها مما يستوجب عمل مراجعة للـ
هذا ما أقومstatus و كتابة ذلك في خانة الـissue Log باإلضافة إلى نقل الخطر إلى الـrisk register بعد ذلك تحديث هذه المعلومات بالـ
the execution process group. And while controlling we audit the effectiveness of the responses
implemented and reassess to identify new risks, close outdated risks and reassess the current risks.
16- Interactive communication is the best way for virtual team to communicate .
18- Update the change log after obtaining approval or rejection from CCB
20- Ishikawa diagram used for Root cause analysis which is part of process analysis.
21- When there is schedule delay PM shall identify alternatives for schedule compression.
22- Using Ishikawa to identify root cause for variance is part of variance analysis
23- Identify new risks, close outdated risks and reassess current risks means Risk reassessment.
24- Business case justifies why the project is being implemented. Project charter authorizes the project.
25- Procurement negotiation concluded when the contract terms are agreed by both buyer and seller &
26- Rejection of the product by key person at closing means neither he nor his requirements were identified at
initiation.
27- If your sponsor asked to terminate the project but you signed a contract with a supplier .
There is Contract already signed and it is binding. The contract terms include the procedure to be followed
if the project is terminated by Client. You should refer to contract terms first.
28- Project manager is a team member, the team leader. When you are managing a project that has 10 team
members. It means the project (not you ) has you plus another 9 When you have 10 team members it
29- Stakeholders complain the reports delay, you shall review communication plan
30- When an identified risk occurs, you should implement contingency plan, Perform reserve analysis first then
update risk register to update contingency reserves and in the status column you can write risk occurred
31- If some team members left the team you will update human resource management plan
5) when you feel that the project may not achieve its objectives.
........
33- Kick off meeting conducted at end of planning process group and the leader who explain the strategy plan
34- Prevention is by planning . Prevent any additional cost unless a change is approved first is the concept of
cost change management plan . Yes there is change management plan for each knowledge area.
35- When subcontractor wants to use his procedure but the PM insist to follow the project management plan
36- Plan quality means look for FUTURE to PREVENT quality problems.
Control quality means quality problem to your PRODUCT OCCURED and you need to repair it.
Assure quality. The problem occurred to the processes but the product still not completed, you make
quality audit, process analysis and continuous improvement to increase the effectiveness of the processes.
37- Once an identified risk occurs it means it will transfer from risk register to the issue log .
And the reserves shall be revised and updated as it became a fact which its probability is 100% Now and its
impact may be changed . A change will be requested to implement the contingency plan.
38- Lesson learned documented THROUHOUT THE PROJECT and collected AT CLOSURE to
39- Final project report shared based on COMMUNICATION MANAGEMENT PLAN to CONVEY
40- The last option to overcome a problem is asking sponsor help, PM shall do his best first.
42- The difference between a risk and an issue is that a risk has probability < 100% which means it may or may
not happen, But an issue is a fact that for sure has happened.
When a risk occurs it became a fact with 100% probability so it became an issue which will need more than
the planned reserves . So PM will need to revise the project status in respect to risks by revising reserves to
This is more important to do first then an update to the risk register and the issue log will be required.
43- When identified risk occurs reserve analysis shall be performed then issue log and risk register update.
44- It is not easy to reject the scope change requested by customer. But You can evaluate the impact of each
change, communicate this impact to the customer requesting approval for additional cost and time followed
by updating the cost and time baselines before implementing the changes. If you are implementing without
approval, then you still measure the variance against the 1st baseline which should be updated .
Cost inflation and/or fake schedule delay penalty occurs in these situations as there is no change
management.
When you are managing a project that has 10 team members. It means the project (not you ) has you plus
another 9 When you have 10 team members it means the project has you plus 10 ie the total number is 11
46- We plan responses for identified risks in the planning process group.
Then implement these responses in the execution process group ( direct and manage project work).
And while controlling we audit the effectiveness of the responses implemented and reassess to identify new
47- Corrective action in respect to schedule delay recovery " schedule compression " may result in some
activities negative schedule variance but at the same time all activities with positive total float. This may be
as a result of some activities duration crashing and some activities fast tracking.
Finally the project schedule variance required to be 0.0 and the negative project float became 0.0
The actions recommended shall be communicated to relevant stakeholders for approval then
implementation.
1) to recommend new contract terms with suppliers/ subcontracts early in the project.
Activity 1, Material / supplier approval delayed leading to negative variance - 7 d and negative total float -8d .
Activity 2, Fs relationship between 2 activities . Predecessor already delayed leading to negative variance -7d
Corrective actions .
1- crashing the duration for the successors, procurement, fabrication and delivery will lead to positive float for
activities while keeping the negative variance for the 1st activity "material approval"
2- fast tracking the 2 activities " SS with lag 5 d for example instead of FS" will change the negative variance and
float to Positive.
Risk id, category, risk description, identified by, date identified, probability, impact, score, trigger, planned
And attached to it Risk scoring document which includes probability definition, impact on schedule
definition, impact on cost definition, impact on quality definition and probability & impact Matrix
49- Corrective action chosen and why plus the variance reasons are part of lesson learned.
52- To confirm the achievement of project scope and deliverables, OBTAIN FINAL ACCEPTANCE OF
1) future use
2) future audit
54-To communicate formal project closure and confirm liability transfer, Obtain administrative, legal, and
financial closure.
55- Lessons learned and project records are part of the closure report.
اكبر منSPI و الـCPI من واقع الحياة العملية عندما يكون العميل غير مقتنع بان حالة المشروع جيدة على الرغم من معرفته ان قيم الـ-56
risk and issue و الـTrends و الـfloats و الـVariances و هى الـ. EV إلقناع العميل سوف نحتاج إلى وسائل أخرى مع الـ. 1
57- The best way to define scope is to allow the team who will do the project, specialists & experts to define
58- Kanban, Six sigma and LEAN are process analysis techniques
59- Important information When you conduct benefit analysis you justify the benefit of executing the project
that comply with the expected business case and company strategy.
Conduct benefit analysis to validate the alignment of the project with organization strategy and expected
businesses case.
60- Important information when you identify key deliverables and communicate them to customer then obtain
customer approval, at this time you transferred his expectations to key deliverables that will achieve project
goals.
That is why customer expectations and project goals achievement are managed by identifying key
deliverables.
61- Within given assumptions and constraints and based on meetings with relevant stakeholders, available
information and previous projects lessons learned project assessment is performed in order to
62- You have been assigned as a project manager when you meet experts, refer to historical data, current
environment and organizational factors. you want to propose an implementation strategy, therefore you
should
63- By compiling and analyzing gathered information and in order to ensure stakeholders agreement on the
C) Ensure that key deliverables and milestones are included in the charter.
64- You have been assigned as a project manager when you meet relevant stakeholders to validate project
65- You have participated in the project charter development, ensured stakeholders agreement on its elements,
obtained sponsor approval, gained commitment and acceptance of your project and formalized your
66- You have participated in the project charter development, ensured stakeholders agreement on its elements,
obtained sponsor approval, gained commitment and acceptance of your project and formalized your
authority.
Now you communicate the approved charter to stakeholders, what is your major objective in regard to
67- You have been assigned as a project manager when you refer to business requirements to direct the
achievement of project goals and manage customer expectations, therefore you should
analysis is
A) CMMI
B) IEEE
C) ISO
D) Kanban.
69- You identified , prioritized, qualitatively analyzed risks and planned risk responses in your project . The
risk register now includes description, probability, impact, score, contingencies, responses, action date and
status . You have 8 risks with the same highest score of 25, one risk of score of 20 and other 22 risks of
However the projects manager asked to include only the top 5 risks in the project dashboard. What should
you do next.
1) Combine each 2 risks together and report the 8 risks as 4 then add the risk no 9 as the 5th.
3) Prioritize risks based on the action date required for responses among the highest 8.
4) Report the 8 risks and inform the senior manager they are all high .
70- PM sent information to project team through Aconex but not all members received the information. What
71- You are at closure of your IT project when the PMO head called you asking to communicate formal
72- You are at closure of your construction project when the PMO head called you asking to ensure the
transfer of liability of the buildings to the operation department . What should you do to achieve PMO
request?
73- You are managing a project to collect and balance requirements of all stakeholders involved in the design
and construction of infrastructure and buildings of the new university at your City.
75- However the sponsor knows That the project CPI =1.15 and SPI=1.25, he still not convinced that the
project is ahead and under budget, in order to confirm the project status and persuade the sponsor, you
presented dashboard of tables and charts that includes Trends, variances, EV performance, risks status,
D) Variance Report.
76- Based on the project management plan, at closure, you are transferring the ownership of the deliverables to
77- You are at closure of your project when the PMO head called asking to confirm the completion of the
project scope and deliverables . What should you do to achieve PMO request?
78- Based on communication management plan, at closure, you prepare and share final project report , one of
79- You are at closure of your IT project when the PMO head called you asking your assistance in project
80- Based on stakeholder management plan, at closure, you are obtaining feedback from relevant stakeholders ,
C) A& B