Professional Documents
Culture Documents
Risk Analysis and Risk Allocation
Risk Analysis and Risk Allocation
Week 3
Index
LEGEND:
Additional content 1
CLIP 1
PROJECT FINANCE AS A BULK OF RISKS:
THE NEED OF RISK MANAGEMENT
Project Finance as a Bulk of Risks
2
CLIP 2
HOW TO MAP RISKS IN A PROJECT FINANCE DEAL:
RISK TAXONOMY
How to Map Risks in a Project Finance Deal
Tip #1
Mapping of project risks following project life-cycle:
Project absorbs cash: the The project first recovers the deficit
project is not able to generate of cash and then generates a cash
any cash flow and all the money surplus.
is committed to building the
infrastructure.
3
CLIP 3
PRE-COMPLETION RISK: TECHNOLOGY AND CONSTRUCTION
Pre-Completion Risks
Types
Planning
• The design of the project is not correct or the advancement of
the work is not properly scheduled.
Technology
• The technology for the project does not perform as originally
expected.
Construction
• The contractor delivers the infrastructure with a delay.
• The project is delivered but it performs below the agreed upon
standards.
• The final cost of construction far exceeds the original budget.
4
Pre-Completion Risks
Responsibilities & Solutions
The contractor takes on most of the responsibilities that arise in the
Responsibility
construction phase by entering a turnkey construction contract (TKCC) which includes
specific penalties.
1. The provision for a maximum cap which excludes extra cost for the SPV;
2. The provision for the refund by the contractor of damages to the SPV for
delay in construction (determined on a daily basis and proportional to the
damages to the SPV);
3. And the provision for the payment of damages if performance is not in line
with a originally agreed minimum standard (tested by an independent
technical engineer at completion).
If the supplier does not provide raw materials it is required to find alternative
sources of supply, and to bear the extra cost if the alternative source is more
expensive than the original one. 6
Post-Completion Risk
O&M Agreement
The SPV enters a contract with one O&M agent by which it commits to refund
damages to the SPV for the losses incurred due to any performance below the
pre-specified service level agreement (SLA).
7
Post-Completion Risk
8
Post-Completion Risk
Creditors require that all the counterparties of the vehicle can be substituted
if they are unable to perform as expected (Direct Agreements).
9
CLIP 5
RISKS COMMON TO BOTH PHASES
Risks Common to Both Phases
Risks that are common to both the pre-completion and post-completion phases and
cannot be allocated to any specific counterparty by means of a contractual obligation
are as follows:
• Natural disasters (or Acts of God, Force Majeure)
• Political risk: change in law, investment risk
• Environmental risk: public opposition, contamination risk
For the most part these are covered by insurance policies (in the case of investment
risk these are provided by Export Credit Agencies).
To safeguard the value of cash flows lenders typically require to hedge against all
fluctuations of macro variables (condition precedent)
• Interest rate risk
• Exchange rate risk
• Inflation risk (only for base risk: revenues and costs linked to different inflation
rates)
10
CLIP 6
WRAP UP: THE RISK MATRIX
Wrap Up: The Risk Matrix
TYPE OF RISKS
Technological, Planning or
Construction Risk
Design Risk
Technology
Penalties to be paid
Supplier
Operator
Buyers
Suppliers
Export Credit
Agency (ECAs)
Banks
Insurance
Insurance policies
Companies
Independent
Assessments on technological
Engineering validity 11
Firms
Wrap Up: The Risk Matrix
TYPE OF RISKS
Technological,
Environmental Regulatory Political Operational
Exchange Rate Risk Interst Rate Risk Inflation Risk Country Risk Planning or Design Construction Risk Suplly Risk Demand/Market
Risk Risk Risk Risk
Risk Risk
Limited to
Included in the Turnkey
obtaining Fixed price turnkey
Contractor construction Agreement
building agreement
agreement (first test)
permits
Penalty
payments and
Operator removal of
operator (later
tests)
Establishing pre-
Buyers agreed inflation
adjustments Take or Pay
Pur or Pay
Establishing pre-
Agreement or
Suppliers agreed inflation
through Pur
adjustments
Agreements
Credit
Export Credit credit insurance
insurance
Agency (ECAs) programs
programs