ACTIVITIES DURATION FOR 27.0M OF CONCRETE LINING,
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb‐Reinforcement binding (9.0m) 8.0 Hrs 8.0 Hrs 8.0 Hrs
3 Overhead reinforcement binding (9.0m)
Gantry de‐shuttering alignment fixing & bulk
4
heading (9.0m) 6.0 Hrs 6.0 Hrs 6.0 Hrs
Concrete Pouring ‐9.0m (During Concrete pouring of overhead after it,
5
the curb will be poured) 8.0 Hrs 8.0 Hrs 8.0 Hrs
6 Pump alignment & Placement of pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning 1.00 Hrs 1.00 Hrs 1.0 Hrs
Transport of materials (Rebars) 2.00 Hrs 2.00 Hrs 2.00 Hrs
8 Cleaning & Reinforcement binding of Invert
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9.0 Hrs
Thus, 27.0m (3Nos of gantry) completes in 5.00 Days
NOTE: REQUIREMENT OF MACHINARY
1. Small TM ‐(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine ‐ 3 Nos (1nos Spair) in proper working condition.
5. De‐watering Pumps ‐2 Nos (1 Nos Spair) in proper working condition.
: Manpower
1. A gang of labours should prepared required rebars outside the tunnel.
2. There should be 2nos gangs for rebar placement. ( 1 gangs will work curb rebar placement & other gangs will work for crown
overhead. Aprox. total numbers of labours should be 50 to 60 nos. ( including cleaning gangs, concreting gangs)
3. Days shift and Night Shift
3.1 Foreman / Supervisor ‐2Nos for each shift.
3.2 Electrician ‐2Nos for each shift.
4. Surveyor ‐1Nos (Call duty)
5. Mechanic & helper ‐1 Nos for each shift.
6. All drivers should be on call duty.
7. Face‐Incharge ‐ Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as mentioned
above.
2. It is assumed that labours shall be paid regularly.