Professional Documents
Culture Documents
Without Rebars-9m Gantry
Without Rebars-9m Gantry
00 m
ACTIVITIES DURATION FOR 27.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb‐Shuttering (9.0m)
Gantry de‐shuttering alignment fixing & bulk 6.0 Hrs 6.0 Hrs 6.0 Hrs
4
heading (9.0m)
5 Concrete Pouring ‐ 9.0m. (During Concrete pouring of overhead after
it, the curb will be poured) 8.0 Hrs 8.0 Hrs 8.0 Hrs
6 Pump alignment & Placement of pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning 1.0 Hrs 1.00 Hrs 1.0 Hrs
8 Invert Cleaning
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9 Hrs
Thus, 27.0m (3Nos of gantry) completes in 3.75 Days
NOTE: REQUIREMENT OF MACHINARY
1. Small TM ‐(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine ‐ 3 Nos (1nos Spair) in proper working condition.
5. De‐watering Pumps ‐2 Nos (1 Nos Spair) in proper working condition.
6.
: Manpower
1. There should be 4nos of gangs for cleaning, Gnatry Alignmnet, Concrete Pouring . Aprox. total numbers of labours should be
30 to 40 nos. ( including cleaning gangs, concreting gangs)
2. Days shift and Night Shift
2.1 Foreman / Supervisor ‐2Nos for each shift.
2.2 Electrician ‐2Nos for each shift.
3. Surveyor ‐1Nos (Call duty)
4. Mechanic & helper ‐1 Nos for each shift.
5. All drivers should be on call duty.
6. Face‐Incharge ‐ Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as
mentioned above.
2. It is assumed that labours shall be paid regularly.