Schedule-Concrete Linning - Tunnel

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

SCHEDULE OF 9.0M GANTRY FOR 30.0M STRECTH WITH REINFORCEMENT - MONTHLY PROGRESS AS PER THIS SCHEDULE= 162.

0 m
ACTIVITIES DURATION FOR 27.0M OF CONCRETE LINING,
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb-Reinforcement binding (9.0m) 8.0 Hrs 8.0 Hrs 8.0 Hrs
3 Overhead reinforcement binding (9.0m)
4 Gantry de-shuttering alignment fixing & bulk
heading (9.0m) 6.0 Hrs 6.0 Hrs 6.0 Hrs

5 Concrete Pouring -9.0m (During Concrete pouring of overhead after it,


the
Pump curb will be poured)
alignment & Placement of 8.0 Hrs 8.0 Hrs 8.0 Hrs
6 pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning 1.00 Hrs 1.00 Hrs 1.0 Hrs
Transport
Cleaning &ofReinforcement
materials (Rebars)
binding 2.00 Hrs 2.00 Hrs 2.00 Hrs
8 of Invert
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9.0 Hrs
Thus, 27.0m (3Nos of gantry) completes in 5.00 Days
NOTE: REQUIREMENT OF MACHINARY
1. Small TM -(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine - 3 Nos (1nos Spair) in proper working condition.
5. De-watering Pumps -2 Nos (1 Nos Spair) in proper working condition.

: Manpower
1. A gang of labours should prepared required rebars outside the tunnel.
2. There should be 2nos gangs for rebar placement. ( 1 gangs will work curb rebar placement & other gangs will work for crown
overhead. Aprox. total numbers of labours should be 50 to 60 nos. ( including cleaning gangs, concreting gangs)
3. Days shift and Night Shift
3.1 Foreman / Supervisor -2Nos for each shift.
3.2 Electrician -2Nos for each shift.
4. Surveyor -1Nos (Call duty)
5. Mechanic & helper -1 Nos for each shift.
6. All drivers should be on call duty.
7. Face-Incharge - Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as mentioned
above.
2. It is assumed that labours shall be paid regularly.
SCHEDULE OF 15.0M GANTRY FOR 50.0M STRECTH WITH REINFORCEMENT - MONTHLY PROGRESS AS PER THIS SCHEDULE= 206.37 m
ACTIVITIES DURATION FOR 45.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb-Reinforcement binding (15.0m)
10.0 Hrs 10.0 Hrs 10.0 Hrs
3 Overhead reinforcement binding (15.0m)
4 Gantry de-shuttering alignment fixing & bulk
heading (9.0m)
6.0 Hrs 6.0 Hrs 6.0 Hrs
5 Gantry de-shuttering alignment fixing & bulk
heading (6.0m)
6 Concrete Pouring - 9.0m (During Concrete pouring of overhead after it,
the
Pump curb will be poured)
alignment & Placement of 15.0 Hrs 15.0 Hrs 15.0 Hrs
7 pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
8 Pump cleaning 1.0 Hrs 1.00 Hrs 1.0 Hrs
9 Transport
Cleaning &ofReinforcement
materials (Rebars)
binding 3.0 Hrs 3.00 Hrs 3.0 Hrs
10 of Invert
11 Invert Concreting 16 Hrs
12 Deberis cleaning for every 3 gantry 12 Hrs
Thus, 45.0m (3Nos of gantry) completes in 6.54 Days
NOTE: REQUIREMENT OF MACHINARY
1. Small TM -(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine - 3 Nos (1nos Spair) in proper working condition.
5. De-watering Pumps -2 Nos (1 Nos Spair) in proper working condition.

: Manpower
1. A gang of labours should prepared required rebars outside the tunnel.
2. There should be 3nos gangs for rebar placement. ( 1 gangs will work curb rebar placement & other 2nos of gangs will work for
crown overhead. Aprox. total numbers of labours should be 60 to 70 nos. ( including cleaning gangs, concreting gangs)
3. Days shift and Night Shift
3.1 Foreman / Supervisor -2Nos for each shift.
3.2 Electrician -2Nos for each shift.
4. Surveyor -1Nos (Call duty)
5. Mechanic & helper -1 Nos for each shift.
6. All drivers should be on call duty.
7. Face-Incharge - Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as mentioned
above.
2. It is assumed that labours shall be paid regularly.
SCHEDULE OF 9.0M GANTRY FOR 30.0M STRECTH WITHOUT REINFORCEMENT - MONTHLY PROGRESS AS PER THIS SCHEDULE= 216.00 m
ACTIVITIES DURATION FOR 27.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb-Shuttering (9.0m)
Gantry de-shuttering alignment fixing & bulk 6.0 Hrs 6.0 Hrs 6.0 Hrs
4
heading (9.0m)

5 Concrete Pouring - 9.0m. (During Concrete pouring of overhead after it,


the
Pumpcurb will be poured)
alignment & Placement of 8.0 Hrs 8.0 Hrs 8.0 Hrs
6 pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning 1.0 Hrs 1.00 Hrs 1.0 Hrs
8 Invert Cleaning
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9 Hrs
Thus, 27.0m (3Nos of gantry) completes in 3.75 Days

NOTE: REQUIREMENT OF MACHINARY


1. Small TM -(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine - 3 Nos (1nos Spair) in proper working condition.
5. De-watering Pumps -2 Nos (1 Nos Spair) in proper working condition.
6.
: Manpower
1. There should be 4nos of gangs for cleaning, Gnatry Alignmnet, Concrete Pouring . Aprox. total numbers of labours should be 30
to 40 nos. ( including cleaning gangs, concreting gangs)
2. Days shift and Night Shift
2.1 Foreman / Supervisor -2Nos for each shift.
2.2 Electrician -2Nos for each shift.
3. Surveyor -1Nos (Call duty)
4. Mechanic & helper -1 Nos for each shift.
5. All drivers should be on call duty.
6. Face-Incharge - Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as
mentioned above.
2. It is assumed that labours shall be paid regularly.
SCHEDULE OF 15.0M GANTRY FOR 50.0M STRECTH WITHOUT REINFORCEMENT - MONTHLY PROGRESS AS PER THIS SCHEDULE= 291.89 m
ACTIVITIES DURATION FOR 45.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb-Shuttering (15.0m)
Gantry de-shuttering alignment fixing & bulk 6.0 Hrs 6.0 Hrs 6.0 Hrs
4
heading (9.0m)

5 Concrete Pouring - 9.0m. (During Concrete pouring of overhead after it,


the
Pumpcurb will be poured)
alignment & Placement of 15.0 Hrs 15.0 Hrs 15.0 Hrs
6 pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
7 Pump cleaning 1.00 Hrs 1.00 Hrs 1.0 Hrs
8 Invert Cleaning
9 Invert Concreting 12.0 Hrs
10 Deberis cleaning for every 3 gantry 9.0 Hrs
Thus, 45.0m (3Nos of gantry) completes in 4.63 Days

NOTE: REQUIREMENT OF MACHINARY


1. Small TM -(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine - 3 Nos (1nos Spair) in proper working condition.
5. De-watering Pumps -2 Nos (1 Nos Spair) in proper working condition.
6.
: Manpower
1. There should be 5nos of gangs for cleaning, Gnatry Alignmnet, Concrete Pouring . Aprox. total numbers of labours should be 40 to 50
nos. ( including cleaning gangs, concreting gangs)
2. Days shift and Night Shift
2.1 Foreman / Supervisor -2Nos for each shift.
2.2 Electrician -2Nos for each shift.
3. Surveyor -1Nos (Call duty)
4. Mechanic & helper -1 Nos for each shift.
5. All drivers should be on call duty.
6. Face-Incharge - Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as mentioned
above.
2. It is assumed that labours shall be paid regularly.
SCHEDULE OF 16.0M GANTRY FOR 50.0M STRECTH WITH REINFORCEMENT - MONTHLY PROGRESS AS PER THIS SCHEDULE= 216.00 m
ACTIVITIES DURATION FOR 48.0M OF CONCRETE LINING
S.NO DESCRIPTION
1 Cleaning, Mud Mat & Setting time plush pump shifing 24.00 Hrs
2 Curb-Reinforcement binding (16.0m)
10.0 Hrs 10.0 Hrs 10.0 Hrs
3 Overhead reinforcement binding (16.0m)
4 Gantry de-shuttering alignment fixing & bulk
heading (9.0m)
6.0 Hrs 6.0 Hrs 6.0 Hrs
5 Gantry de-shuttering alignment fixing & bulk
heading (7.0m)
6 Concrete Pouring - 9.0m (During Concrete pouring of overhead after it,
the
Pump curb will be poured)
alignment & Placement of 16.0 Hrs 16.0 Hrs 16.0 Hrs
7 pipes 2.0 Hrs 2.0 Hrs 2.0 Hrs
8 Pump cleaning 1.0 Hrs 1.00 Hrs 1.0 Hrs
9 Transport
Cleaning &ofReinforcement
materials (Rebars)
binding 3.0 Hrs 3.00 Hrs 3.0 Hrs
10 of Invert
11 Invert Concreting 16 Hrs
12 Deberis cleaning for every 3 gantry 12 Hrs
Thus, 48.0m (3Nos of gantry) completes in 6.67 Days
NOTE: REQUIREMENT OF MACHINARY
1. Small TM -(3Nos) with Maximum Capacity during transport of 3m³ and able to pour minimum quantity of 2m³
2. Hydraulic Gantry
3. Vibrators
4. Welding Machine - 3 Nos (1nos Spair) in proper working condition.
5. De-watering Pumps -2 Nos (1 Nos Spair) in proper working condition.

: Manpower
1. A gang of labours should prepared required rebars outside the tunnel.
2. There should be 3nos gangs for rebar placement. ( 1 gangs will work curb rebar placement & other 2nos of gangs will work for
crown overhead. Aprox. total numbers of labours should be 60 to 70 nos. ( including cleaning gangs, concreting gangs)
3. Days shift and Night Shift
3.1 Foreman / Supervisor -2Nos for each shift.
3.2 Electrician -2Nos for each shift.
4. Surveyor -1Nos (Call duty)
5. Mechanic & helper -1 Nos for each shift.
6. All drivers should be on call duty.
7. Face-Incharge - Nos.
:HURDLE/OBSTRUCTION
1. Above progress is based on consideration that there would be no machinary beakdown and no lack of manpower as mentioned
above.
2. It is assumed that labours shall be paid regularly.