An Independent Third Party Monitoring Report of KABELI CORRIDOR 132 KV TRANSMISSION LINE PROJECT

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 38

NEPAL ELECTRICITY AUTHORITY

(Environmental and social Safeguard Implementation Status)


An Independent Third Party Monitoring Report
Of
KABELI CORRIDOR 132 KV TRANSMISSION LINE PROJECT

Submitted to
Kabeli Corridor 132 KV Transmission Line Project
Godak, Ilam

Submitted By
Pathivara Professional Education Pvt. Ltd.
Damak, Jhapa
ABBREVIATIONS AND ACRONYMS
BS : Bikramsambat
CBO : Community Based Organization
CFUGS : Community Forest User Group
DDC : District Development Committee
DFO : District Forest Office
DOED : Department Of Electricity Development
IEE : Initial Environmental Examination
EPA : Environmental Protection Act
EPR : Environmental Protection at on Regulation
ESSD : Environmental And Social studies Department
HA : Hectare
HHS : House Holds
JV : Joint Venture
KCTLP : Kabeli Corridor Transmission Line Project
KC-ESMU: Kabeli Corridor Environment and Social Department Unit
KM : Kilometer
KV : Kilovolt
MW : Mega Watt
NEA : Nepal Electricity Authority
NGO : Non-Governmental Organization
NTFP : Non Tiber Forest Product
PAFs: Project Affected Families
RAP : Resettlement Action Plan
ROW : Right of Way
SIA : Social Impact Assessment
TL : Transmission Line
VDC : Village Development Committee
WB : World Bank
Acknowledgement

We would like to express our deepest acknowledgement and sincere appreciation


to the following persons and institutions for their valuable contribution, helpand
cooperation of all of which led to the successful completion of this study.

Firstly, we would like to express our sincere gratitude to Mr. Dipendra Raj
Dubedi, Project Manager of Kabeli Corridor 132 KV Transmission Line Project
for his coordination and guidance.

We would like to acknowledge Mr. PurnaChauhan, administrative officer of


Kabeli Corridor 132 KV Transmission Line Project. Similarly we are thankful to
all the staffs of Kabeli Corridor 132 KV Transmission Line Project.

Our heartfelt appreciation goes to Mr. BhojrajBhattarai for his kind cooperation
and support.We are thankful to the Project affected families, local people and
workers at sites for their cooperation during the monitoring and site visits by the
team of Pathivara Professional Education Pvt. Ltd.

Pathivara Professional Education Pvt. Ltd.


Damak, Jhapa
Declaration from the Consultancy

This is to declare that we, Pathivara Professional Education Pvt. Ltd. has
prepared this report entitled "Environmental and Social safeguard
Implementation Status of Kabeli Corridor 132 KV Transmission Line Project
(An Independent Third Party Monitoring Report)" with the help of senior
Environment specialist and social safeguard specialist. The data, facts and
figures presented here are truly collected by the experts during field visits.

............................. .........................
DamberKumariAdhikari , MadanBahadurThapa,

Senior Social Safeguard Specialist Senior Environment Specialist

.................................................................
Dilli Ram Bhattarai,
Managing Director
Pathivara Professional Education Pvt. Ltd.
Damak, Jhapa
Table of Contents
Abbreviation and Acronyms Pg.no

Acknowledgement

Declaration
1. Project Description.........................................................................................................................................1
1.1 Background...............................................................................................................................................1
1.2 Rationale of Study....................................................................................................................................1
1.3 Objectives.................................................................................................................................................2
1.4 Brief Description of Project.......................................................................................................................2
2. Data Requirement and Study Methodology...................................................................................................3
3. Major challenges and issued observed...........................................................................................................3
4. Environment and Social Safeguard Implementation......................................................................................4
4.1Waste management..................................................................................................................................4
4.2 Biological Environment.......................................................................................................................4
4.3 Socio- Economic and Cultural Environment..............................................................................................5
4.3.1 Land Loss and PAFs............................................................................................................................6
4.3.2 Local Employment.............................................................................................................................6
4.3.3 Local Economy...................................................................................................................................6
4.3.4 Occupation Safety..............................................................................................................................6
4.3.5 Law and order Situation.....................................................................................................................7
4.4 Compliance Monitoring............................................................................................................................7
4.5 Social Safeguard Implementation.............................................................................................................7
4.6 Conclusion and Recommendations..........................................................................................................9
4.7 Recommendations..................................................................................................................................9
Refrences….

Annexes
1. Project Description
1.1 Background
There are several hydropower projects having the different stages of developmental works in Kabeli
Corridor of Provience number one. The official website (www.doed.gov.np) of Department of
Electricity Development (DoED), recorded different hydropower projects which have capacity of
111.09 MW are under construction in Ilam, Panchthar and Taplejung districts. Similarly, four
developers have applied for generation licenses for 4 hydropower project (526 MW). Furthermore,
survey license had been issued for 8hydropower (335 MW). The major functions of the DoED are to
guarantee transparency of regulatory framework, accommodate, promote and facilitate private
sector's participation in power sector by providing "One Window" service and license to power
projects. Therefore, Kabeli Corridor 132 KV Transmission Line Project (KCTLP) under construction
is one of the main concern projects in the eastern region of Nepal for expansion and upgrading of
Integrated Nepal Power System.

During the power development projects like KCTLP there would be various environmental and
social impacts. Therefore, Nepal Electricity Authority (NEA) envisages in order making its power
projects more environmentally sound, sustainable and socially beneficial.
Since World Bank is financing the project, implementation of mitigation measures is also required to
fulfill the provisions of World Bank Safeguard policy.

Nepal electricity authority is implementing Kabeli Corridor 132 kV Transmission Line project with
the financial assistance of World Bank. The first section of line from Damaksubsatatin at Jhapa to
Godaksubsatation of Illam had been complete. The Initial Environmental Examination report ( IEE)
Social Impact Assessement (SIA) and Resettlement Action Plan (RAP) had been prepared for the
project as per the requirement of Government of Nepal and World bank. An MOU had been signed
between Environment and Social Studies Department of NEA and Kabeli Corridor 132 kV
Transmission Line Project to implement safeguards measures and monitoring works through its unit
office in coordination and support of the experts from the department.

1.2 Rationale of Study


Nepal is one of the rich countries of the world in term of its natural resources. Among the several
natural resources found in Nepal, water resource can be used to generate the hydropower and for
irrigation. Since, after the generation of electricity, the generated hydropower should be connected to
the national grid for its distribution in several areas through transmission line. So, construction of
transmission line along with hydropower is essential for the wide distribution of generated
electricity. According to DoED, there are several hydropower projects under construction stages in
Mechi Zone. During the construction of projects like KCTLP, there would be several environmental
and social impacts and to mitigate those impacts NEA plays a vital role to make its project more
environmentally sound, sustainable and socially beneficial. Since, World Bank is main financial
supporter of this project; KCTLP has to fulfill the World Bank Safeguard Policy. To mitigate and
implement the Environment Management Plan and for the regular environment and social
monitoring of the construction site Environment and Social Management Unit was established in
February 2012.
The scope of the service of the consultant is to carry out independent review and monitoring of the
implementation of safeguard measures as per the approved documents, environmental and social
monitoring works, compliance status of the tender clauses, stakeholder engagement status, conflicted
site(s) approaches made so far and works to be done to resolve the issues

1.3 Objectives
The broad objective of independent monitoring was to review work conducted by ESMU.
Specific objectives were:

 To review the work conducted by ESMU;


 To find out the task conducted as per the approved documents;
 To assure the constructions work complied the environmental and social tender clauses;
 To make sure concerns are adequately taken care;
 To suggest ESMU/ESSD and project for the procedures and areas where improvement is
required;
 To assess the actual impacts of the project and suggest additional mitigation/enhancement
measures if required;
 To assess the effectiveness of the mitigation and enhancement program conducted under the
project; and
 To visit and consult the people of major conflict area and suggest appropriate measures.

1.4 Brief Description of Project


The project lies in province number one of Nepal. It oblique through four districts namely Jhapa,
Ilam, Panchthar which lies in Mechi Zone and Terhathum in Koshi Zone. Kabeli Corridor
Transmission Line started from LakhanpurVDC of Jhapa District to AmarpurVDC of Panchther
District. There are 25 different VDCs of these four districts affected by the KCTLP. They are
Lakhanpur, Chulachuli, Evang, Mahamai, Danabari, Chisapani, Soyak, Godak, Siddhithumka,
Sangarumba, Mangalbare, Ektappa, Phakphok, Chamaita, Chilingdin, Pauwasartap, Nawamidanda,
Imbung, Chokmagu, Siwa, Phidim, Bharapa, Subhang, Amarpur and Chattedhunga.
The project components consist of 90.019 km long double circuit transmission line and a substations
of 132/33 kV capacity. The Right of Way (RoW) of the purposed project is pm from the center line
on each side. Thus, RoW for the transmission line is 18m. It will required approximately 5m× m
land (max) for tower pad foundation depending upon tower design types which is 1 to 3 Anna (1
Anna = 32 sq.m)
The Kabeli Corridor Transmission Line starts from plain terrain of Terai at Jhapa and extends north
east through PhaguKhola at the foot hill of Churia hill and then Mai Khola in the Mid hills. From
Soyak, it bifurcated into two branches, one extending towards north east which is 6 km long arm
terminating at Godak substation and another long arm proceed north west from Soyak to Kabeli
(Amarpur) substation.
The KCTLP has planned for rural electrification along 5 km corridor (2.5 km either side of center
line) of the proposed route alignment. Survey, mapping and engineering design of rural
electrification works was completed while tendering of 5 km corridor of first section was on
progress.
2. Data Requirement and Study Methodology
This independent monitoring report is prepared based on the secondary and primary level studies.
The primary level data was collected on the physical, biological, and socio-economic environmental
sectors using variousmethods such as field observation,focus group discussions with the local
communities. Structured and unstructured questionnaire survey of the project affected households
and focus group discussions with the project affected areas in the social, socio-economic and
cultural environment were done. The data were analyzed using various tools such as personnel
experience, and projects of similarnature in similar geographic locations.

3. Major challenges and issued observed


The implementation of environment and social management plan is becoming harder in recent time
due to the public obstacle. It is very difficult to implement and complete the objectives in time. Land
acquisition process and high compensation amount is the main hurdle for timely completion.
Similarly, lengthy official process takes long time . Furthermore, regular increase in expectation of
local peoples from project and those demands unable to fulfill by project also delay the work. Due to
the limited budget and resources it is difficult to implement unnecessary public demands. Small self-
centered groups, local political leaders and lack of coordination between government agencies also
take long time for implementation of proposed program.

During our field visit, it was found that in some of affected areas people were not satisfied with
compensation modality particularly land pricing. Compensation of damage done to crops during
cable stringing work is on process, however, people are not satisfied with the lengthy and tedious
process. Though the number of environmental and social augmentation programs such as
biodiversity awareness program, social awareness program, skill development training, people are
expecting more such programs to be conducted in affected area. Project had proposed to provide
electricity in project affected area which is found not to be implemented till now.

4. Environment and Social Safeguard Implementation


4.1Waste management
To minimize the envisaged impacts on the physical environment and to maximize the beneficial
impacts, the project has originated a various mitigation measures.

 The spoil materials generated was managed properly.


.
 Liquid and solid waste were collected in safe area and disposed safely. Spent oils, mobils,
and other chemicals generated had also been safely collected in drums and disposed as per
the advice of the engineers.

 Toilets in the camps and active construction sites were constructed as per the requirement to
prohibit haphazard defecation.

 Due to regular monitoring of construction by ESMU team, the management of domestic


wastes produced was managed properly.
4.2 Biological Environment

The field survey shows that out of 257 towers 166 towers are located in cultivated land, 48 towers
are in forest land and 43 towers are in barren land. Since the acquired lands for all four substations
were agricultural cultivated land, there is no direct impact on biological environment till the stage of
project construction.

To minimize the envisaged impacts on the biological environment and to maximize the beneficial
impacts, the project has originated a various mitigation measures during the construction and
operation phase. The mitigation measures implemented include:

 The loss of forest land use due to clearance of tall trees along ROW was compensated by the
compensatory afforestation programs.

 Cleared area was replanted and ground clearance activities were limited to trimmings of the
tall standing trees particularly in the steep slopes.

 restricting the felling to only lopping and topping of the high growing or potentially high
growing trees and poles,

 restriction of fuel wood use,


 control the workforce on the damage on the vegetation structure and punish those who
indulge on such activities,

 use of bird flight diverters across to increase the visibility of the conductors to avoid the bird
hits particularly across the waterways,
 erection of barricade around the tower foundations and substation sites and uses of thorny
protuberances around pylon to divert wild animals and to restrict climbing along the pylon.

4.3 Socio- Economic and Cultural Environment


To minimize the envisaged impacts on the socio-economic environment and to maximize the
beneficial
impacts, the project has originated a various mitigation measures during the construction and
operation phase.
 The loss of land and property, price of the standing crops, fodder tress, fruits trees was
compensated at the market price.
 The household was provided with salvation of the demolished material and transportation
cost was provided to transport salvaged material.
 Extra Discomfort allowances for 6 month rental and livelihood subsistence was provided to
those whose house was demolished.
 The loss of standing tress of the private, community and lease hold forest was compensated
as per forest guideline.
 NTFP enhancement training was given to the forest community user groups and NTFP
plantation had been encouraged in RoW of transmission line.

 The interested community forest user group members and leasehold forest members were
given job opportunities in the compensatory afforestation programs.
 The lost community resource due to project was compensated as per the forest guideline
2006.

 Telephone and electricity users were given prior information regarding the disruption of the
services and services will be re-established once the cable stringing is completed.

 The affected households were given priority in the project job. While providing Job gender
discrimination had been avoided. Priority has also given to female members and members of
the indigenous, tribal and vulnerable groups in job, enhancement and training program.

 The construction workforce was regularly instructed to respect female member of the
community, local people and their traditions and culture. They have been instructed to remain
within the camps and not to enter into the private premises without informing or without the
permission.

 The local law and order authorities were regularly informed about the construction planning
and sites of construction works and activities.

 In case of construction related work force impacts, the project had support the schools of the
project affected areas, had establish good shops and health service facility within the camps.

 Health and safety plans had prepared and operationalised for the entire period of construction
to safeguard the health and safety of the construction workforce.

 The construction workforce had instructed about the risk of the constriction works regularly
and had been provided with protective equipments. First aid kits had been provisioned in all
working sites.

 To minimize the impacts on the aesthetics material excavation works were limited to the
required amount and excavation material and cleared vegetation had been placed in closed
areas and in an environmentfriendly manner.
.
4.3.1 Land Loss and PAFs
In final route alignment all 257 towers were marked on the ground. Topographic map, GPS, survey
report was used for the identification of the tower site. In addition input from the local people
involved in survey work was also taken for the identification of the tower sites. However,
preliminary findings of the extensive field visit revealed that there are about 215 households affected
due to the lands required from tower pads and substation excluding the RoW.

4.3.2 Local Employment


Large number of employers had been involved on substation as well as tower foundation works.
Basically, local manpower was involved in unskilled work whereas foreign manpower as a skilled
and technical work but priority was given to local people (especially PAFs) according to their
knowledge. Engineers, Supervisor, Electrician, mason, quality control officer, surveyor, driver,
security guard and labor are the main area of employment for local people.

4.3.3 Local Economy


Business activities like hotel, grocery and vegetable shops have been temporarily increasing in
surrounding of the substation sites of Godak whereas other economic activities was also observed in
Phidim and Amarpur substation project sites. We found that the local economy and business has
been fluently increasing now days.

After involvement on construction activities of local people, their income generation activities
increased. It helped to promote local economy and positive impacts on livelihood of local people.
4.3.4 Occupation Safety
During regular monitoring of construction site, the contractor's staffs working at site were adequately
provided personal protective equipment (PPEs) such as shoes, masks, gloves, helmets, safety belts in
the construction site. The workers are not wearing that safety equipment due to their uneasiness.
During our field visit, we make sure to wear the PPEs to all the workers for their safety. However, no
case of accident and serious injury was reported in the project construction site.
4.3.5 Law and order Situation
The labors involved in project work lives in temporary camps located within substation area without
disturbing the local periphery. Some local labors up-down daily from their homes to the substation
and tower pad construction sites. No conflict was noted between the project workers and local people
regarding the use of local resources.

4.4 Compliance Monitoring


The IEE report has recommended various indicators and methods for different environment
conditions. Compliance monitoring confirms on a regular basis that all the agreed working condition
procedure and obligation regarding various environmental considerations are followed suitably. The
mitigation measure and monitoring work purposed in the IEE document had been incorporated in
contract documents.

4.5 Social Safeguard Implementation


According to MoU between KCTLP and ESSD had completed all of the 25 social awareness
program. The subject matter of awareness program covers: general introduction of project, tower
structures, right of way, land acquisition, compensation, construction planning and schedule, mode
of compensation and suggestion, electric hazards and safety, role of civil society for implementation
of project, economic opportunity due to project implementation, ecotourism etc. All together twenty
social awareness programs were conducted in project affected former VDCs covered with project
affected families, forest user groups and locals.

.
Table 1: Affected Land Parcels by Tower Pads and ROW and Compensation Status

S.N Name of the Affected Land Compensation Status


. section Parcels (No.) Tower Pads (NRs.) ROW Land (NRs)
Tower ROW Total Amount Total Amount
Pads Amount Paid Amount Paid
I Chulachuli to 38 (32) 202 (86) 9,87,201.00 8,14,538.33 92,10,779.4 74,22,159.9
Godak 1 5
II SoyakChamaita 92 (81) 479 48,09,241.0 46,10,155.0 On Process On Process
(Ilam Part) 0 0
III Panchathar Part 86 (26) 79 20,06,938.0 10,59,249.7 On Process On Process
(Chilindin to 0 7
AmarpurVDC)
IV Terhathum 12 (7) 45 16,92,42.08 98,323.18
District (Identifie
(Chhatedhung a d not
VDC) Final)
Sub – Total 228 805 (86) 79,72,622.0 65,82,266.2 92,10,779.4 74,22,159.9
(146) 8 8 1 5
V Structure Total 31 PAF identified (House, Goat Shed, Cattle Total Distributed
(Chulachuli to shed, Toilet, Kitchen) Amount Amount
Godak) (NRs. (NRs.
4204594.20) 38,51,252)
Note: Compensation amount received number of land parcel had been shown in brackets.

4.6. Problems Identified and their Solution Measures.

 Affected people are not satisfied with compensation modality and rate.
 Damage of crops and property during cable stringing was compensated only in some areas
and is on process in other.
 Number of environmental awareness and social augmentation programs launched were not
sufficient.
 Land under stringing cables of some areas was compensated and in some areas is under
process.
 The project had proposed electricity distribution in affected areas and implementation
program is under process.
 Public Relation Officier is not available in the project office due to wchich the matters
settling at the site is delaying.
 Project office has not sufficient staff to be mobilized at every working site.
 Local people of Jorsal of created obstacles for foundation work of tower as thy are not
satisfied with the compensation amount .

Solution measures of aforementioned problems are listed in the recommendation below.


4.7 Conclusion and Recommendations

Conclusion
 The physical environment was not affected by the construction activities as the construction
materials, tower parts, cements, iron rods etc. were stored inside the substation construction
site and security guards were available for 24 hours. Similarly, waste materials produced in
the labor camp site was properly disposed.
 Since maximum no. of tower lies at a cultivated land so there was no direct impact in the
biological environment but during stringing of wire there was some damage in the trees and
seasonal crops.
 According to the IEE report of project about 3500 trees will be cut down in the alignment of
the transmission line which causes impact in the bio diversity. To minimize the impact,
compensation plantation was conducted in about 60 hectare of land of Jhapa. Ilam, Panchther
and Tehrathum district. Furthermore, replacement plantation was carried out in those
plantation sites and will be continued for five years and finally will be handover to respective
District Forest Office.
 Social awareness programs were completed for PAF's in different affected areas and One
day biodiversity awareness programs were completed in 40 schools of project affected former
VDC's. Similarly, various training programs like NTFP training, Agriculture and Horticulture
training, Livestock training were successfully completed by KC-ESMU. Finally, skill
development training program for project affected peoples was also completed.

 Local people were employed in the construction work. But maximum local people were
involved in unskilled work while foreign manpower were used in skilled works. Likewise,
business activities like hotel, grocery and vegetable shops have been observed temporarily
increasing in surrounding of the substation sites which increases the income generation of the
local peoples.
 Regular monitoring of the construction site was done by the environmental and social
monitors.

Recommendations
Some recommendations based on the current environment and social monitoring works carried out
by KC_ESMU team which can help KCTLP to carry out further monitoring works easier and to
mitigate and minimize the social and environmental impact due to project.

 Regular monitoring in the construction site was needed for the improvement of health and
sanitation of labors and proper use of safety measures by the workers during construction
work.

 Awareness about use of NTFP's plants in Row would be beneficial for PAF's to get income
from NTFP's plants and to be safe from electrical hazards.

 Good earthlings in all the pylon structures, regular trimming of the trees has to be provisioned
to reduce the impact and effects of electromagnetic fields.

 Awareness programs have to be launched to further avoid and minimize the impacts on the
safety issues to the communities along the ROW of transmission corridor also.
 Most of the seedlings were planted on community forest, river basin and the degraded forest
areas. Open area with human and livestock disturbance is one of the major threats to the
protection of the plantation site. So, they have to be protected.

 Compensation modality and rate has to be justifiable.

 Damage of crops and property during cable stringing has to be compensated.

 Further environmental awareness and social augmentation programs are recommended.


Comparative Chart (Implementation of Environment and Social Management Plan)

S.N. Monitoring Implementation Status as per ESSD 3rd party monitoring status
and
Mitigation
Measures as
per MoU with
ESSD
1. Mitigation Achievement Current Status
Work
i. Biodiversity  All together 40 programs  Awareness raised after
Awareness were completed in different implementation of program.
program schools of Ilam, Panchther,  Positive support to project.
Tehrathum and Jhapa  Additional safety awareness
Total no. district. program needed.
program 40  Altogether 3777 affected  Understood the importace
(40 schools people (students, teachers of biodiversity
Covered) and locals) benefited.  Learnt the conservation
 Positive attitudes increased methods of biodiversity
 Good support was found
about project construction
and bio-diversity
conservation.
ii. Social  All of the program (20  Increased Knowledge about
Awareness program) were completed in electricity safety and use of
Program different places affected power in househols sector.
VDCs of Ilam, Panchther,  Local people got project
(Total no. of Tehrathum and jhapa. information on time.
program 20)  Altogether 625 affected  Involvemnt of local people
people benefited. increased in each and every
 Know about project needs, stages of project
electricity safety, local implementation.
people's role and found
involvement of local people
increases on project
construction.
iii. Placement of  40 hoarding boards,  Some of the Hoarding Board
Hoarding displayed in all the affected found in subststion and
Boards area. plantation sites.
.  Local people got the
 Public awareness increased knowledge about project,
about environment environment conservation,
conservation, electricity electricity safety and project
safety and project construction activities.
construction activities.  Positive impact and
awareness raised in locality
 Increased knowlade about
elelectricity saftey
 Positive impact on people
perception and attidutde
iv. Local school  School support program was  Stationery materials, white
support completed in board, reference books
program seventeenschools of Ilam, found in PurnaSmark,
(Library Panchther, Tehrathum and Godak,
Support) Jhapa. SukabodhMaviPhidim etc.
 School administration
responses was found
positive with project.
 Positive about project on
teachers, students
v. Plantation  Several discussion and
program meeting was held with  More than 70% planted
(Forest sector different community forest species are found in good
Mitigation user groups of Ilam, condition but 30% found in
and Panchther and Tehrathum dead condition.
Enhancement district.  Replacement plantation and
program  Till date all (97,00 sapling) plantation management
saplings have been planted continuously running.
which covered 60 hector in  Community Forest User
area at Jhapa, Ilam, Groups involved on
Panchthar and Terhathum. plantation management.
 Similarly, about 20,000  For the better management
saplings were planted as a of the differentplantation
replacement plantation for sites, following
dead species in all plantation staffs/Watchman were hired
sites. on contract basis.
 Actively participation of a) Purna Bahadur Lingdel
Community Forest User (Ratuwamai Plantation
Groups (CFUGs) was found Area, Jhapa)
on plantation activities. b) Khadga Bahadur Magar
(Suryadaya Community
Forest, Ilam)
c) Jaya Kumar Majhi
(Maule Kopchee
Community Forest,
Terhathum)
d) Sun Kumar Limbu
(Sukuna Community
Forst, Chulachuli, Ilam)

vi. NTFP  Completed two NTFP  Some of the member of


Training training at Birtamod (22nd Community Forest involved
to 28th Asar) and Phidim on NTFP production
(18th to 24th Ashoj) which personally.
covered five days theoretical  Most of the member
and two days practical harvesting Amleso as a
classes. The training was NTFPplants.
given to the affected CFUGs  People got knowledge
to provide know-how and about the importance of
skill for plantation, NTFP
management and harvesting  Involvement of CFUGs on
of non-timber forest NTFPs harvesting increased
products (NTFPs)
 The marketing and business
oriented activities through
NTFPs harvesting increases.
 Involvement of CFUGs on
NTFPs harvesting increases.
vii. 7 days  2 program was completed on  Some of the Farmers at
Agriculture December 2015 to January Mangalbere engaged on off
and 2016. Seasonal Vegetable farming.
Horticulture  Most of the PAFs (more  Only 50 % participants
Training than one hundred) applied their skill in
Program participated and benefited. vegetable farming.
 Increases knowledge about  Increased knowledge about
seasonal and off seasonal seasonal and off seasonal
vegetable farming and vegetable farming and
marketing system. marketing system.
 Some of the people involved  Some of the people involved
agriculture farming after agriculture farming after
training. training.
 Income from seasonal and
off seasonal vegetables
increased

viii. 3 days  3 days two program was  At Chhatedhunda,


Livestock completed December 2015 Terhathum few people
Farming to January 2016 at Ilam and involved pig farming by
Training and Phidim. making groups.
Assistance  Got the knowledge about  At Mangalbare, two people
Program livestock business plan, started small business of
marketing and farming poultry farming.
system.
 Some of the people started
small business of poultry
farming.
ix. Skill  As per needs of Afftected  Skill Training covers only
development people driving , House affected by Tower Pads but
Training wiring and Tailoring training RoW People also wanted
(Driving, conducted. skill Training.
tailoring,  House Wiring (40 PAFs-  The impact of skill training
House wiring, 390 Hours and CTEVT is found positive.
Welding and Standard), Driving (45PAFs-  60% of the people who got
Mobile One Month) and Tailoring driving training also
repairing for (15 PAFs -3 Months- involved on driving
100 affected CTEVT Standard) profession.
people) completed training on time  80% of participants engaged
on building electrician
activities.
 99% of Women
Participation of Tailoring
started their work.
Annex -2: Plantation Status at Different sites of KCTLP

S.N. Plantation Area Covered Number Planted Spices with Numbers 3rd Party
Area (ha) of Monitoring
Saplings Status
1. Sukuna Community 12.20 20,000 Khair-3,000, Simal-1,000, ….
Forest, Chulachuli- Tanki-1,000, Masala-2,000,
Ilam Bans - 3,000, Rittha - 1,000,
Chakrasi - 4,000, Koirala -
1,000.
2. Suryadaya 11.45 18,000 Khair - 500, Simal - 1,500, ……
Community Forset- Tanki - 1,000, Tik-500,
GodakIlam Harro-5,000, Barro-5,000,
Amala-2,000, Rittha-2,000,
Khamari-500.
3. Ratuwamai 6.6 9,600 Tik - 9,600
Plantation Project
Area-Jhapa (Section
I)
4. Barbhanjyang 3 4,800 Sisau-2,000, Masala-2,000,
Community Forest- Khair-500, Tejpatta-100,
Danawai, Ilam Simal-200
5. Maivalley 3.34 6,400 Tik-2,000, Harro-Barro-
Community Forest- 3,000, Rittha-1,000, Amala-
Soyak, Ilam 200, Khair-200
6. Sallery Community 5.15 9,000 Salla-6,000, Ritha-600,
Forest-Amarpur, Lapsi-1,000, Chiuri-500,
Panchthar Khair-600, Amala-300.
7. Maule Kopche 5.81 9,000 Khair-6,000, Ritha-600,
Community Forset- Lapsi-1,000, Chiuri-500,
Chhatedhunga, Khair-600, Amala-300.
Tehrathum
8. Ratuwamai 12.5 21,000 Tik-15,000, Khair-5,000
Plantation Project Masala-1,000
Area- Jhapa (Section
II)
Total 60 97800
Annex- 3: Replacement Plantation and Management in Different Plantation Sites

S.N. Plantation Area Covered Number Planted Spices with Remarks


Area (ha) of Numbers
Saplings
1. Sukuna Community 12.20 5,000 Khair – 1,500, Tik-1,000, Replacement
Forest, Chulachuli- Masala-2,000, Rittha-500 Plantation
Ilam Completed
2. Suryadaya 11.45 4,700 Simal - 500, Tik-1,500, Replacement
Community Forset- Harro-500, Barro-500, Plantation
GodakIlam Rittha-1,200, Khamari-500 Completed
3. Ratuwamai 6.6 2,500 Tik–2,500 Replacement
Plantation Project Plantation
Area-Jhapa (Section Completed
I)
4. Barbhanjyang 3 1,300 Masala-600, Tejpatta-200, Replacement
Community Forest- Simal-500 Plantation
Danawai, Ilam Completed
5. Maivalley 3.34 1,600 Tik-1,600 Replacement
Community Forest- Plantation
Soyak, Ilam Completed
6. Sallery Community 5.15 2,400 Salla-1,500, Ritha-500, Replacement
Forest-Amarpur, Amala-400. Plantation
Panchthar Completed
7. Maule Kopche 5.81 2,500 Khair-1,500, Ritha-500, Replacement
Community Forset- Masala-500. Plantation
Chhatedhunga, Completed
Tehrathum
Total 47.55 20,000
Annex- 4: Name of Community Forests where the tree had been cut down

S.N. Forest Name Location No. of cutting Name of Species


trees
1. Sukuna CF ChulachuliVDC– 5 101 Harro – 2, Jamun – 3, Saj
– 19, Sal – 29, Mango –
1, Siris – 2, Chilaune – 1,
Dabdabe – 3, Katari – 1,
Hallude – 14, Bot
Dhamero – 1, Karang – 3,
Satissal – 1, Firfire – 7,
Hade – 6, Gayu – 1,
Falame – 2, Kumvi – 3,
Kalikath – 1, Bhalayo – 1.
2. Tamakhe CF MahamaiVDC – 5 67 Saal – 30, Saj – 7, Karma
– 1, Kukath – 29
3. Suryodaya CF DanabariVDC– 9 28 Maina – 2, Saj – 9, Simal
– 1, Kutmiro – 1, Barro –
1, Chilaune – 1, Karma –
4, Lampate – 1, Siris – 1,
Sal – 7
4. Laxmi CF DanabariVDC – 8 1 Sal – 1
5. Khandechuli CF DanabariVDC – 9 7 Sal – 1 and Maina – 6
6. PragatiNamuna CF DanabariVDC – 8 16 Sal – 11, Jamun – 1, Saj –
3, Bot – Dhamer -1
7. Juntara CF ChisapaniVDC – 9 61 Seti Kath – 2, Hallute – 5,
Tuni – 1, Katus – 1,
Chhatiwan – 1, Chilaune
– 19, Dabdabe – 1,
Mauwa – 2, Saj – 3,
Latahar – 2, Lampate – 1,
Jamun – 1, Others-
Kukath – 22
8. Sitadevi CF SoyakVDC -6 23 Lampate -4, Kutmiro -4,
Siris- 2, Kadam -1, Simal
-1, Barro -2, Saj-4,
dabdabe-3, Kukath-2
9. Maivalley CF SoyakVDC– 9 405 Sal-168, salprolesize –
87, Chilaune – 101,
Lampate – 2, Botdhamero
– 6, Jaman – 2, saj – 1,
putalikath – 2, Kukath –
36
10. Suryodaya CF GodakVDC– 3 631 Saj – 13, Kutmiro – 1,
Halude – 1, Tuni – 1,
Maina-Kath – 1, Saal –
224, Sal pole size – 199,
Chilune – 1, Simal – 6,
Sindure – 9, Dabdabe – 1,
Others Kukath – 178
11. Aadharchuli SiddhithumkaVDC - 3 44 Chilaune – 8, Mauwa – 1,
Government Forest Uttis – 9, Kutath – 26
12. SatreRangapani ChisapaniVDC– 4 24 Chilaune – 3, and Sal –
21
Total 1408
Annex -5: Proposed Cutting tress in Different CF of Panchther and Tehrathum Districts

S.N. Forests Name Location Proposed No. of Name of Species


Cutting Trees
1. SupariBaghthala CF Terhathum 136 Sal – 128, Karam – 4,
bot bhageri – 4
2. BijeBangesal CF Terhathum 12 Sal – 12
3. Salle Sisne CF Terhathum 100 Sal – 94, Chilaune – 6
4. Maule Kopche CF Terhathum 187 Sal – 183, Karam – 1,
bot bhageri – 3
5. MahilaPatale CF Panchathar 134 Sal – 134
6. Dada CF Panchathar 75 Sal – 71, Salla – 4
7. Salleri CF- Bharapa Panchathar 325 Salla – 99, Sal – 10,
Lathara– 216
8. Amarpur-Salleri CF Panchathar 673 Sallo – 673
9. SubhangRastria Panchathar 26 Sal – 26
Forest
10 Deurali CF Panthar ?? ??
11 Phidim Panchthar ??
Total 2043?
Annex -6: Status of Handover of Wood log to Respective CFUG's

S.N. Forest Name Location No. of cutting Remark


trees
1. Sukuna CF ChulachuliVDC -5 101 Handover going on
2. Tamakhe CF MahamaiVDC -5 67 Handover Completed
3. Suryodaya CF DanabariVDC– 9 28 Handover Completed
4. Laxmi CF DanabariVDC– 8 1 Handover Completed
5. Khandechuli CF DanabariVDC– 9 7 Handover Completed
6. PragatiNamuna CF DanabariVDC– 8 16 Handover going on
7. Juntara CF ChisapaniVDC– 9 61 Handover not started
yet
8. Sitadevi CF SoyakVDC– 6 23 Handover Completed
9. Malvalley CF SoyakVDC– 9 405 Handover not started
yet
10. Suryodaya CF GodakVDC– 3 631 Handover completed
11. Aadharchuli SiddhithumkaVDC - 3 44 Handover Completed
Government Forest
12. SatreRangapani ChisapaniVDC– 4 24 Handover Completed
Total 1408
Annex -7: Detail list of Social Awareness Programs Organized by KC-ESMU Why this annex
here ?????

S.N Name of Place Name of Former District Date No. of


. (Location) VDCs Participants
1. Buddha Primary Mahamai-5, Ilam 2069/9/11 36
School Tamakhe
2. Bright Future English Danawari-9, Ilam 2069/9/12 33
Boarding School Sanduwa
3. Building of Godak Godak-3 Ilam 2069/9/17 22
Substation
4. Women Cooperative Siddithumka- Ilam 2069/9/17 22
Hall Panchhami Bazar
5. Balkanya Higher SoyakVDC-7 Ilam 2069/9/19 26
Secondary School
6. Suryodaya Primary ChulachuliVDC- Ilam 2069/9/22 25
School Peltimari
7. Juntara Community ChisapaniVDC- Ilam 2069/9/25 25
Forest Users Group's Borung
Office
8. SalleriVDC Building BharapaVDC Panchathar 2069/12/03 19
9. Siddheswori SubhangVDC Panchathar 2069/12/04 31
Secondary School
10. Naule Prime School ChatedhungaVDC Panchathar 2069/12/05 27
-Maghigon
11. Deurali Community PhidimVDC-Jorsal Panchathar 2069/12/04 17
Hall
12. Community Amar VDC Panchathar 2069/01/07 32
Hall,Bhimsensthan
13. Saraswoti Higher ChokmanguVDC- Panchathar 2069/01/07 32
Secondary School Dumribote
14. Talkharka Ward no 9 Sangarumba Ilam 2071/08/27 45
15. Tilpung Primary Chamaita Ilam 2071/09/01 45
School
16. Municipality Bulding Mangalbare Ilam 2071/08/29 45
17. Tilpung Primary Ekatappa and Ilam 2071/09/01 40
School Building Phakphok
18. Satyahangama Higher Imbung Panchathar 2071/09/05 33
Secondary School
Building
19. Bhagawoti Ma Vi. Nawamidanda and Panchathar 2071/09/12 25
Siwa Siwa
20. Pauwasartap Higher PauwasartapVDC Panchathar 2072/11/18 50
Secondary School
Total 630
Annex- 8: Detail List of One-day Bio-Diversity Awareness Programs Conducted by KC-ESMU
??????this Annex why???

S.N. Name of School Name of VDC District Date No. of


Participants
1. ShisuSewa Lower DanawariVDC-1 Ilam 2069/9/2 71
Secondary School-Chepti
2. LaxmiAdarsa Secondary MahamaiVDC-8 Ilam 2069/9/3 85
School- Bisnetar
3. YuwaBarsa Secondary Danawari -9 Ilam 2069/9/4 87
School
4. Bhagawoti Secondary MahamaiVDC-3, Ilam 2069/9/5 82
School Gotametar
5. Kankai Higher Secondary DanawariVDC-1, Ilam 2069/9/8 115
School Sitali
6. Sarswoti Secondary DanawariVDC-6, Ilam 2069/9/9 76
School Musekhola
7. SinghpurPashupati AmarpurVDC-7 Panchathar 2069/11/13 89
Secondary School
8. Amarpur Higher AmarpurVDC-4 Panchathar 2069/11/14 119
Secondary School
9. Jorpokhari Secondary BharapaVDC-2 Panchathar 2069/11/15 69
School
10. Siddeswori Higher BharapaVDC-6 Panchathar 2069/12/01 92
Secondary School
11. Siddheswari Secondary Subhang -2 Panchathar 2069/12/02 55
School
12. Narayan Lower Chhatedhung a Panchathar 2069/12/06 74
Secondary School- VDC-8
Aarchale
13. Kirateswor Secondary ChulachuliVDC-6 Ilam 2069/11/20 82
School
14. BalJyoti Secondary ChulachuliVDC-7 Ilam 2069/11/21 85
School
15. Bhanu Secondary School ChulachuliVDC-8 Ilam 2069/11/22 78
16. Mangalmaya Higher LakhanpurVDC-1 Jhapa 2070/01/12 82
Secondary School
17. Bani Higher Secondary LakhanpurVDC- 3 Jhapa 2070/01/13 75
School
18. Guheswory Lower LakhanpurVDC- 1 Jhapa 2070/01/15 123
Secondary School
19. PurnaSmarak Higher GodakVDC Ilam 2071/08/08 99
Secondary School
20. Nanda Higher Secondary GodakVDC Ilam 2071/08/09 110
School
21. BalKanya Secondary Soyak Ilam 2071/08/24 112
School
22. Janata Higher Secondary Chisapani Ilam 2071/08/23 96
School
23. Khandruk Higher Siddithumka Ilam 2071/08/25 101
Secondary School
24. Sangarumba Higher Sangarumba Ilam 2071/08/26 58
Secondary School
25. Bhanubhakta Higher Mangalbare Ilam 2071/08/28 70
Secondary School
26. Phalate Secondary School Chamaita Ilam 2071/09/02 105
27. Jalsingh Secondary Pauwasartap Panchathar 2071/09/04 59
School
28. Satyahangma Higher Imbung Panchathar 2071/09/07 117
Secondary School
29. Siddha Devi Higher Nawamidada Panchathar 2071/09/08 134
Secondary School
30. Bhagawati Secondary Siwa Panchathar 2071/09/09 107
School
31. Siddheswor Secondary Chilindin Panchathar 2071/09/02 112
School
32. Sartap Higher Secondary Pauwasartap Panchathar 2071/09/06 119
School
33. Sukhabodh Secondary Phidim Panchathar 2071/10/23 95
School
34. Gadhi Secondary School Phidim Panchathar 2071/10/25 88
35. Nilgiri Higher Secondary Subhang Panchathar 2071/10/26 129
School
36. Saraswoty Higher Chokmagu Panchathar 2071/10/27 115
Secondary School
37. Phidim Higher Secondary Phidim Panchathar 2072/11/18 120
School
38. Shree Janaki Secondary Ektappa Ilam 2073/08/29 103
School
39. Siddakali Secondary Bharapa Panchathar 2073/09/01 103
School
Bajendra Kali lower Bharapa Panchathar 2073/09/03 117
Secondary School
40.
Total 3808
Annex -9: Data Capturing Sheet Used in Field Visit
Location: Date:

Environment Indicators Methods Locatio Activities


category Parameters n
Slope Degree of Site
stability and slopes, observation
Physical landslide stability of
environment slopes and
change from
baseline

Waste Unpleasant
management and visual
impact

Land use Land use


change change,
cropping
pattern and
crop
diversification
Environment Indicators Methods Locatio Activities
category Parameters n

Biological Loss of trees Number of Observation


environment and shrubs tree removed and
discussion
with forest
user groups

Pressure on Forest cover Observation


the and
forest( fuel discussion
wood and with forest
timber) user groups

Non timber Forest cover Observation


forest and
product discussion
with forest
user groups
Environment Indicators Methods Locatio Activities
category Parameters n

Socioeconomi Acquisition of Land use Review of


c and cultural private land change, land
environment cropping acquisition
pattern and notice,
crop discussion
diversification with affected
people

Acquisition of Relocated Social


house and and displaced survey,
other people review of
structures property
acquisition,
level of
satisfaction of
relocated
people

compensatio Socioeconomi Compensatio


n c parameters n modality,
like economic amount, use
status, living of it, review
conditions etc of land
of affected acquisition
people
Environment Indicators Methods Locatio Activities
category Parameters n

Health and Types of


sanitation diseases
recorded and
of break of
diseases

Occupational No of Record of
health and casualty accident
safely
Environment Indicators Methods Locatio Activities
category Parameters n
Public health No need less
and safety people enter
into the site

employment No of local
people
employed by
project,
contractor

Local No industries
economy established,
business
centers
Environment Indicators Methods Locatio Activities
category Parameters n

Law and Incidence of Police records


order varies types of , and site
crimes and inspection
prostitution
and alcohol
relates crimes
36
Annex -10: Attendance sheet Used in Field Visit

37
Annex- 11: Relevant Photograph

38

You might also like