Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035

Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011


Contract Number: A5MU Page 1 of 9
Revision 1

SPECIFICATION - SILENCERS

This specification has been revised as indicated below and described in the revision record on the
following page. Please destroy all previous revisions.

Revision Date Originator's Reviewed/Checked By Pages


No. Name & Initials Name & Initials

A 9/9/10 L. STREEB T. WOOD ALL


0 10/19/10 L.STREEB T.WOOD ALL
1 3/8/11 L. STREEB T. WOOD ALL

APPROVALS SIGNATURES DATE

Lead Engineer
Engineering Manager:
Client Approval:

ISSUED FOR : Construction X Other ISSUED APPROVED


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 2 of 9
Revision 1

SPECIFICATION - SILENCERS

Record of Revisions
Revision Date Description
No.

A 9/9/10 CLIENT REVIEW - TOC

0 10/19/10 ISSUED FOR REVIEW/APPROVAL - SPECIFICATION

1 3/8/11 ISSUED APPROVED


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 3 of 9
Revision 1

SPECIFICATION - SILENCERS

TABLE OF CONTENTS
1.0 SCOPE…………………………………………………………………………….………...……..4

2.0 APPLICABLE CODES, STANDARDS AND REFERENCES….…………...………….……..4

2.1 ASA (ACOUSTICAL SOCIETY OF AMERICA)……………………………….…….…...........4

2.2 API (AMERICAN PETROLEUM INSTITUTE)………………...…………………..…….……..4

2.3 ASME (AMERICAN SOCIETY OF MECHANICAL ENGINEERS.……………….……..……4

2.4 OSHA (OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION)…….……….…....4

2.5 AWS (AMERICAN WELDING SOCIETY)………………………………..…………….………5

3.0 SYSTEM DESCRIPTION……………………………………………………………...…....…..5

4.0 TERMINOLOGY………………..………………………….……………………………………..5

5.0 DOCUMENTATION…..…………………………………….……………..……..………….…..6

6.0 PERFORMANCE GUARANTEE.………………………………………………………….......6

7.0 TECHNICAL DESIGN REQUIREMENTS…………………………….……………………….6

7.1 SILENCER………………..………………………….…………………....………..……….……6

7.2 WELDING……………………..…………..…………………………..………….……..............7

8.0 PAINTING AND PERSONNEL PROTECTION .……………………..………………….……7

9.0 INSPECTION AND TESTING……………….…………….……………….……….…….........8

9.1 INSPECTION…………………..……………………….…….………………………….…….…8

9.2 NON-DESTRUCTIVE EXAMINATION……………………………………..………….…..…..8

9.3 SOUND LEVEL TESTS……….………….……………………………..…………………….....8

10.0 PREPARATION FOR SHIPMENT……………………………………………………..……....8


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 4 of 9
Revision 1

SPECIFICATION - SILENCERS

1.0 SCOPE
This specification prescribes the general requirements for silencers. The requirements outlined
herein supplement the Silencers Datasheet on which the operating conditions and special
requirements are listed in detail for each silencer. If conflicts exist, the datasheet shall govern.

2.0 APPLICABLE CODES, STANDARDS AND REFERENCES

The publications listed below form part of this specification. Each publication shall be the latest
revision and addendum in effect on the date of contract award. Except as modified by the
requirements specified herein or the details of the drawings, Work included in this specification
shall conform to the applicable provisions of these publications.

2.1 ASA (Acoustical Society of America)

S1.1 Acoustical Terminology


S1.13 Measurement of Sound Pressure Levels in Air

S1.4 Specification for Sound Level Meters


2.2 API (American Petroleum Institute)

605 Large Diameter Carbon Steel Flanges

2.3 ASME (American Society of Mechanical Engineers)

B16.5 Pipe Flanges and Flange Fittings


B30.20 Below the Hook Lifting Devices
B31.3 Chemical Plant and Petroleum Refinery Piping
Boiler and Pressure Vessel Code:
Section II Material Specifications
Section V Nondestructive Examination
Section VIII, Div. 1 Pressure Vessels
Section IX Welding and Brazing Qualifications

2.4 OSHA (Occupational Safety and Health Administration)

29CFR1910 Occupational Safety and Health Standards


29CFR1926 Safety and Health Regulations for Construction
Noise Control, A Guide for Workers and Employers
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 5 of 9
Revision 1

SPECIFICATION - SILENCERS

2.5 AWS (American Welding Society)

A2.4 Standard Symbols for Welding, Brazing and Nondestructive Examination


A3.0 Terms and Definitions

3.0 SYSTEM DESCRIPTION

3.1 Sound pressure measurement procedures shall be made in accordance with ASA S1.13,
Measurement of Sound Pressure Levels in Air.

3.2 Required sound pressure levels and insertion loss (attenuation) values are specified on
the silencer datasheet.

3.3 Required and guaranteed sound pressure levels are measured at a distance of 3 meters
from the extreme outside point of the opening, perpendicular to the direction of flow, and
shall also be included for vent or suction silencers. For in-line silencers, sound pressure
levels shall be provided at a distance of 1 meter from pipe or duct, 3 meters downstream.

3.4 Silencers inherent self noise shall be taken into account in their design with special
attention given to casing radiation to ensure that the regenerated noise does not exceed
the allowable sound pressure level

4.0 TERMINOLOGY

4.1 dBA: Sound pressure level in decibels (reference 20 by 10:(-6:) newtons per square
meter) as read on a sound level meter set to the A weighted network, slow response
setting.

4.2 A-Weighted: A-Weighted means a specific weighting of the sound pressure level for the
purpose of determining the human response to sound. The specific weighting
characteristics and tolerances are those given in ASA S1.4.

4.3 PWL (Sound Power Level): Expressed in decibels (reference 10:(-12:) watts).

4.4 SPL (Sound Pressure Level): Expressed in decibels (reference 20 by 10:(-6:) newtons
per square meter).

4.5 Sound Attenuation: The reduction of sound by various means.


Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 6 of 9
Revision 1

SPECIFICATION - SILENCERS

5.0 DOCUMENTATION

Supplier shall submit the type and quantity of drawings and documentation for Purchaser’s
authorization or information as listed on the Supplier’s Drawing and Data Commitment Form.

6.0 PERFORMANCE GUARANTEE

Seller shall guarantee the noise level requirements in accordance with the Silencer Datasheet.

7.0 TECHNICAL DESIGN REQUIREMENTS

7.1 Silencer

A. Silencer design criteria are identified on the Silencer Datasheet. Upstream


pressure and temperature specified for atmosphere discharge silencers shall be
the conditions upstream of valve.

B. Silencer design shall be manufacturer's standard whenever design pressure is


less than 15 psi. Silencer shall be designed and constructed according to ASME
Code Section VIII, Division 1, whenever design pressure exceeds 15 psig.

C. Silencer shall discharge at or below sonic velocity unless otherwise specified on


the data sheet to avoid regenerated noise and damage to internals.

D. Silencer inlet and outlet connections shall follow ASME B16.5. Flanges larger
than 24 inches shall follow API 605.

E. Silencers shall be provided with 3/4 inch minimum size low point drain
connections. Drain connections, except for atmosphere silencers, shall be
flanged with pressure rating equal to the silencer design pressure rating.

F. Packing shall be required to maintain a consistent mechanical and chemical


stability.

G. Silencer casings shall be constructed of carbon steel, 1/4 inch plate minimum.
Internal construction shall also be carbon steel, except wherever the presence of
a corrosive environment requires the use of stainless steel or some special
internal coating.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 7 of 9
Revision 1

SPECIFICATION - SILENCERS

H. The minimum corrosion allowance shall be as specified on the Silencer


Datasheet.

I. Each silencer shall be provided with a minimum of 2 lifting lugs. Engineering


lifting components shall be designed to meet ASME B30.20 allowable design
stresses, using 1/3 of yield or AISC allowable stresses with load factor of 1.8 will
meet requirement, unless large factors are required by applicable codes or
standards. This factor includes impact. Lifting lug calculations shall be submitted
for approval.

J. A vertically mounted silencer shall be provided with 4 equally spaced mounting


supports.

K. Silencers shall meet the noise criteria specified in the Marafiq Sound Control
Specification.

7.2 Welding

A. Supplier shall submit to Purchaser the WPS and PQR, for welding, in accordance
with ASME Section IX for review and approval prior to the start of fabrication.

B. A weld map shall be submitted with the WPS and PQR for Purchaser’s review
and approval.

C. Welding, including repairs, shall comply with the requirements of ASME Section
IX and/or AWS.

D. Welding terms and definitions shall be in accordance with AWS 3.0.

8.0 PAINTING AND PERSONNEL PROTECTION

8.1 All carbon steel exposed surfaces shall be shop primed and finish painted in accordance
with Supplier’s standard painting system, unless otherwise specified on the data sheet

8.2 Flanged surfaces shall not be painted

8.3 If personnel protection is required on the datasheet, Supplier shall furnish all necessary
personnel protection material and labor for installation on the silencer in his shop.
Personnel protection shield shall consist of suitable metal guards or shields.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 8 of 9
Revision 1

SPECIFICATION - SILENCERS

9.0 INSPECTION AND TESTING

9.1 Inspection

A. Supplier shall furnish the Purchaser copies of Supplier’s inspection and quality
control plan for review and approval.

B. Materials and workmanship shall be subject to inspection by the Purchaser in the


shop.

C. The Purchaser’s inspector will check, as a minimum, equipment components,


tagging, critical dimensions, connection sizes and locations, and quality of
workmanship against certified drawings, data, and purchase order documents.

9.2 Non-Destructive Examination

A. Non-Destructive Examination procedures shall be submitted to Purchaser for


review and approval at least 4 weeks prior to commencing the work.

B. For all silencers, a hydrostatic test is required. It shall be conducted in


accordance with ASME Section VIII, Div.1 requirements. A hydrostatic test
report shall be provided to Purchaser.

C. Additional Non-Destructive Examinations required by ASME Code (such as X-


ray, mag particle, dye penetrant, etc.) shall also be conducted.

D. Lifting attachment welds shall be dye penetrant tested as a minimum.

9.3 Sound Level Tests

If sound level tests are required and run in an environment not covered by ASA S1.13,
procedures for calculating or correcting the data supplied in the Silencers Datasheet shall
be furnished to Purchaser for review. Supplier shall ensure compliance with Marafiq
Sound Control specification.

10.0 PREPARATION FOR SHIPMENT

10.1 Preparation for shipment shall be in accordance with the Supplier’s standards and as
noted herein. The Supplier shall be solely responsible for the adequacy of the preparation
for shipment.
Power and Water Utility Company for Jubail and Yanbu (MARAFIQ) Specification MQ-SP-M-4035
Project Name: MARAFIQ SPEC DEVELOPMENT Date: 08 Mar 2011
Contract Number: A5MU Page 9 of 9
Revision 1

SPECIFICATION - SILENCERS

10.2 Supplier shall furnish a packing list for each group of items shipped. Items shall be easily
identified on the packing list.

10.3 Flanged openings shall be provided with full size steel closures of 5 millimeters (3/16 of
an inch) minimum thickness with full face rubber gaskets and at least 4 full diameter
bolts. Large diameter flanges (10 inches and above) shall have 10 millimeters (3/8 of an
inch) thick full size steel covers with full face rubber gaskets and 1 full size bolt in every
other hole.

10.4 Open ends (without flanges) shall be adequately protected from moisture ingress and
corrosion during shipment and storage at site for a period of at least 6 months.

10.5 Adequate protection shall be provided against mechanical damage and atmospheric
corrosion in transit and for at least six months of outdoor storage at jobsite prior to
installation

End of Specification