CABLE TRENCH CONSTRUCTION

TYPE A

INPUT DATA

EARTH WORK

X-SEC OF EXCAVATED AREA 1.063

SEGMENT LENGTH 1

EARTH CUTTING VOLUME 1.8071

RATE(CUT +FILL) 10

COSTING 618.9318

SHUTTERING WORK

WOOD SURFACE.ARE NO OF SEC. T.SUR.ARE VOL(CFT) RATE RATE

0.6 6 36 3 450 35 1350

COST 1260

R.C.C WORK
CONCRETE CASTING
X-SEC OF DRAIN(M2) 0.325
LENGTH(M) 1
VOLUME(M3) 0.325
RATE 9500
COST 3087.5

REBAR WORK

NO OF REBAR ALONG LENGTH 23


LENGTH 1
DB10 UNIT WT 0.666
WT (TOTAL) 16.39026 DB10 mm

MID ver, segment


DB10

NO OF ROD 8
LENGTH 0.75
WT 4.27572 DB10 mm

SIDE VER, SEGMENT

NO OF ROD 16
LENGTH 0.75
DB12 0.888
WT OF DB12(KG) 11.40192 DB12 mm

BOTTOM SLAB ROD

NO OF ROD 8
LENGTH 1.64
DB12 0.888
WT OF ROD (KG) 12.4661 DB12 mm

TOTAL WEIGHT OF ROD 44.534 DB10 20.66598


RATE 75 DB12 23.86802
COST 3340.05

TOTAL COST PER METER 8306.482


319801.8

9500