ME049-Main Switch Board and Distribution Board

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

WCT TSR SDN BHD

INSPECTION CHECKLIST
Scope of Work : Installation of Main Switchboard

Project Title : MAIN CONTRACT WORK FOR CADANGAN MEMBINA 1 BLOK BANGUNAN PODIUM KOMPLEKS MEMBELI-
BELAH 8 TINGKAT DI FASA 2, DI ATAS LOT 795, 796, 797, 799, 800, 20007, 20008 & SEBAHAGIAN LOT-LOT
743, 746, 802, 803 MUKIM BANDAR KUALA LUMPUR, DAERAH KUALA LUMPUR, WILAYAH PERSEKUTUAN
FOR PNB MERDEKA VENTURES SDN BHD PACKAGE: PMV.RM.01 (Main Contract Works)

Location :

Date of Inspection :

Time :

Item Description of Work Contractor Consultant IAR/ NCR/ Remarks


Pass Fail Pass Fail SWO No.
1 Material to approved by consultant / client
a. Material approval document no.:
2 Cabinet size, finish, colour, damage etc
3 Name plate, labeling, damage signs and danger sign
4 Housing or enclosure and protection
5 Installation and fixing to structure
6 Check circuit
7 Busbar size, connection and support
8 Earth bar and earth connection
9 Bus PT ratios & connection
10 Bus voltmeters and connection
11 MCCB with the correct type and rating
12 Test of protection relay
13 As-built schematic diagram provided
14 Cleanliness and rubbish cleared away
15 Work as per approved method statement
a. Method statement document no.:
16 Others …

Comments : _____________________________________________________________________________________
_____________________________________________________________________________________

Prepared By : ___________________________ Name : Date : _________________


(Sub-contractor's Representative)

Checked By : ___________________________ Name : Date : _________________


(Maincontractor's Representative)

Witnessed By : ___________________________ Name : Date : _________________


(Consultant's Representative)