Professional Documents
Culture Documents
Engineering Project Management
Engineering Project Management
Engineering Project Management
Management
(OTM-455)
DE-39 Mechatronics
Syndicate – B
Project Report
Submitted By:
PC Usama Bin Qamar (39 MTS B)
Date: 11-6-2020
Submitted To:
Maam Afsahn
Case Study No 1
Burj Al Arab
Objectives:
To build a hotel which will be an iconic or a symbolic image for Dubai in the same
way Opera House is to Sydney-Australia or Eifel Tower to Paris-France
To build the hotel to resemble the sail of a Dhow, an Arabian vessel
To build the world`s most luxurious tourist hotel on an artificial Island
To build this hotel project to international quality standard and deliver within two
years
To break even and recoup the ROI within 3 years of commissioning
To create job opportunities for the local communities
In Scope:
Upon completion, the new property will include the following as described in the detailed
specifications and blueprint:
Landscaping
Foundation (with sand piling) poured concrete and concrete block.
Curved Driveway Bridge.
Main structure as per drawings and specifications.
Decks / Tennis Helipad / High Tech Conference Room.
Outdoor Garage.
Out Of Scope:
The construction of the artificial island on which the structure is located.
Project Time Management
Work at Burj Dubai is carried out in three shifts. Due to high day time temperatures up to 50°
Celsius – the concrete works are usually carried out during the slightly cooler night time
hours.
The total time taken for the construction of this building was 2,192 days with the average
height built per day was 37 centimeters or 1 feet and 2.88 inches
(www.theatlanticcities.com). If we carefully interpret the construction timeline as shown in
Table 1 we can understand that the work was speeding up when the project started. There was
a steady growth during 2005-06 till level 50 was reached. Since then it took a long time to
construct another 50 levels as the building was rising higher and the crew might be dealing
with challenges arising due to it. From January 07 to July 07 the construction again picked up
some speed as they were nearly building 10 floors every month. This was remarkable as the
construction was reaching the heights where any construction worker might not have gotten.
The construction was again slowed down in September 07 when level 150 was reached. After
that it took 7 months to complete the top most floor of the building. The average height built
per day might look small but considering the construction at 838 meters above ground is an
achievement. Let us now move on to the actual problems faced by the project management
while erecting the world’s highest structure.
The Table Below Shows All Type of Risks Involve in The Whole Project
Level
/L)
Incomplete design.
Inadequate site investigation.
Coordination and Co-
Uncertainty over the source and operation among the
1. Technical Risks availability of materials. H
different technical
Appropriateness of specifications departments
Inflation.
Availability and fluctuation in
Regular finance
foreign exchange.
monitoring.
Delay in Payment.
4. Financial Risks L
Repatriation of funds.
Periodical
Local taxes
estimation
Constraints on the availability
and employment of expatriate
staff.
Customs and import restrictions
and procedures. M
5. Political Risks
Difficulties in disposing of plant
and equipment.
Insistence on use of local firms
and agents
Table 3
Fish Bone Diagram:
Figure 2
The Fishbone Diagram is a tool for analyzing process dispersion. It is also referred to as the
"Ishikawa diagram" because Kaoru Ishikawa developed it, and the "fishbone diagram”
because the complete diagram resembles a fish skeleton. The diagram illustrates the main
causes and sub causes leading to an effect. It is a team brainstorming tool used to identify
potential root causes to problems. Because of its function it may be referred to as a cause-
and-effect diagram.
Figure 3
Project Stakeholder Management
Figure 4
The Above Figure Shows The Communication Plan for Burj-Al-Arab. The number of
crosses in the above table symbolizes the level of commitment it requires: X - Low, XX -
Med, XXX - High. The table above illustrates the communication methods to be
commenced with the stakeholders and the various departments of the Burj Al Arab
project. The table above will serve as a tool to keep record of all the communication plans
for the project, it also will help in planning future communication, and resolving project
conflicts.
Communication Deliverables:
Figure 5
Gantt Chart:
Figure 6