Id Modo da Nome da Tarefa Duração Início Término Predecessoras Junho 2020 Julho 2020 Agosto 2020

Tarefa 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
1 CRONOGRAMA POLANA PLAZA 40 dias Seg 8/6/20 Sex 31/7/20
2 Ceramic Floor Works 28 dias Seg 8/6/20 Qua 15/7/20
3 Terrace 21st 10 dias Qui 2/7/20 Qua 15/7/20 4
4 Terrace 1st 5 dias Ter 23/6/20 Seg 29/6/20 5
5 Terrace GF 5 dias Ter 16/6/20 Seg 22/6/20 6
6 Floor -1 Laundry 1 dia Seg 15/6/20 Seg 15/6/20 7,30
7 Hall of Elevators -1 to -5 5 dias Seg 8/6/20 Sex 12/6/20
8 Ceiling Works (Stucture, Boarding and 16 dias Seg 8/6/20 Seg 29/6/20
Plastering)
9 Ceiling Struture Laundry -1 3 dias Qui 11/6/20 Seg 15/6/20 10
10 Ceiling Struture Hall of Elevator -1 to -5 3 dias Seg 8/6/20 Qua 10/6/20
11 Ceiling Gysum Board Laundry -1 3 dias Ter 16/6/20 Qui 18/6/20 9
12 Ceiling Gypsum Board Hall of Elevator -1 to 3 dias Sex 19/6/20 Ter 23/6/20 11
-5
13 Ceiling Gysum Plaster 1st Floor 7 dias Seg 8/6/20 Ter 16/6/20
14 Ceiling Gysum Plaster GF 2 dias Qua 17/6/20 Qui 18/6/20 13
15 Ceiling Gysum Plaster Laundry -1 3 dias Sex 19/6/20 Ter 23/6/20 14
16 Ceiling Plaster Hall of Elevator -1 to -5 4 dias Qua 24/6/20 Seg 29/6/20 15
17 Painting Works 35 dias Ter 9/6/20 Seg 27/7/20
18 All the missing Apartments (2ng Hand Walls 30 dias Ter 9/6/20 Seg 20/7/20
and Ceilings)
19 Hotel 1st Floor Rooms 7 dias Qua 17/6/20 Qui 25/6/20 13
20 Hotel 1st Floor Corridors 5 dias Qua 17/6/20 Ter 23/6/20
21 Hotel GF 3 dias Sex 26/6/20 Ter 30/6/20 19,34
22 Floor -1 5 dias Qua 24/6/20 Ter 30/6/20 15
23 Hall of elevator -1 to -5 5 dias Ter 30/6/20 Seg 6/7/20 16
24 Signaling of the Basement 15 dias Ter 7/7/20 Seg 27/7/20 23
25 Carpet Instaltions 7 dias Qua 24/6/20 Sex 3/7/20 52,72
26 Skiritng Instaltions 7 dias Qui 2/7/20 Sex 10/7/20 25
27 Hydraulic Works 10 dias Qua 10/6/20 Ter 23/6/20
28 Hotel TermoAc. Instalation Floor 1 to 3 7 dias Qua 10/6/20 Qui 18/6/20
29 Floor -5 Rainwater Pump Instalation 3 dias Sex 19/6/20 Ter 23/6/20 28
30 Floor -1 Piping Laundry 1 dia Qui 11/6/20 Qui 11/6/20
31 Floor -1 Piping Basement 1 dia Sex 12/6/20 Sex 12/6/20 30
32 PVC Piping Floor -2 to -5 3 dias Seg 15/6/20 Qua 17/6/20 31
33 GF Sanitary Equipments 2 dias Qui 18/6/20 Sex 19/6/20 32
34 Sprinklers Instalations 3 dias Seg 15/6/20 Qua 17/6/20
35 Floor -1 Laundry Sanitary Eqp. Instalations 1 dia Seg 22/6/20 Seg 22/6/20 33
36 Stair Works 26 dias Sex 12/6/20 Sex 17/7/20
37 Hotel Stair Painting 15 dias Seg 15/6/20Sex 3/7/20
38 Hotel Stair Handrail 9 dias Seg 15/6/20 Qui 25/6/20
39 Residence Stair Painting 20 dias Sex 12/6/20 Qui 9/7/20

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Ter 9/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo

Página 1
Id Modo da Nome da Tarefa Duração Início Término Predecessoras Junho 2020 Julho 2020 Agosto 2020
Tarefa 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
40 Residence Stair Handrail 16 dias Sex 26/6/20 Sex 17/7/20 38
41 Electrical Works 39 dias Seg 8/6/20 Qui 30/7/20
42 All the Cabling and Wiring 9 dias Seg 8/6/20 Qui 18/6/20
43 Lights and Instalations 11 dias Seg 8/6/20 Seg 22/6/20
44 Floor 21st to 4th 7 dias Seg 8/6/20 Ter 16/6/20
45 Floor 3 2 1 7 dias Seg 8/6/20 Ter 16/6/20
46 Ground Floor 2 dias Qua 17/6/20 Qui 18/6/20 45
47 Basements -1 to -5 2 dias Sex 19/6/20 Seg 22/6/20 46
48 Board Instalations 39 dias Seg 8/6/20 Qui 30/7/20
49 Floor 21st to 4th 30 dias Sex 19/6/20 Qui 30/7/20
50 Floor 3 2 1 10 dias Seg 8/6/20 Sex 19/6/20
51 Main boards Instalation/Connections 7 dias Seg 8/6/20 Ter 16/6/20
52 Hotel rooms Boards 5 dias Seg 15/6/20 Sex 19/6/20
53 Ground Floor 5 dias Qua 17/6/20 Ter 23/6/20 51
54 Floor -1 to -5 5 dias Qua 24/6/20 Ter 30/6/20 53
55 Tranformer and MV SwitchGear Instalations 7 dias Qua 24/6/20 Qui 2/7/20 53

56 HVAC Works 15 dias Seg 6/7/20 Sex 24/7/20


57 Grids Instalations 15 dias Seg 6/7/20 Sex 24/7/20
58 Floor 21st to 4th 2 dias Seg 6/7/20 Ter 7/7/20
59 Floor 3 2 1 9 dias Qua 8/7/20 Seg 20/7/20
60 Corridors and Common areas 2 dias Qua 8/7/20 Qui 9/7/20 58
61 Hotel rooms Grids 7 dias Sex 10/7/20 Seg 20/7/20 60
62 Ground Floor 2 dias Ter 21/7/20 Qua 22/7/20 61
63 Floor -1 to -5 2 dias Qui 23/7/20 Sex 24/7/20 62
64 Exterior Units of the Hotel 2 dias Qui 23/7/20 Sex 24/7/20 62
65 Ventilators Intalation 12 dias Ter 7/7/20 Qua 22/7/20
66 Floor 1 3 dias Ter 7/7/20 Qui 9/7/20 4
67 Ground Floor 2 dias Sex 10/7/20 Seg 13/7/20 66,5
68 Basements -1 to -5 7 dias Ter 14/7/20 Qua 22/7/20 67
69 Fire Detection Project (Extin) 34 dias Ter 9/6/20 Sex 24/7/20
70 Firedetectors Intalation 31 dias Ter 9/6/20 Ter 21/7/20
71 Floor 21st to 4th 2 dias Sex 17/7/20 Ter 21/7/20 73
72 Floor 3 2 1 10 dias Qua 10/6/20 Qua 24/6/20
73 Ground Floor 2 dias Qua 15/7/20 Sex 17/7/20 75
74 Control Panels 1 dia Sex 17/7/20 Seg 20/7/20 73
75 Basements -1 to -5 15 dias Qua 24/6/20 Qua 15/7/20 72
76 CO detector Instalation (Extin) 5 dias Sex 17/7/20 Sex 24/7/20 73,75
77 Other Speciality Works
78 Screen of the Apartments (21st to 4th)
79 Access Controls 19 dias Seg 22/6/20 Qui 16/7/20

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Ter 9/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo

Página 2
Id Modo da Nome da Tarefa Duração Início Término Predecessoras Junho 2020 Julho 2020 Agosto 2020
Tarefa 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1
80 Floors 3 2 1 (Locks) 7 dias Seg 22/6/20 Ter 30/6/20 52
81 Basements (Barriers) 3 dias Qua 1/7/20 Sex 3/7/20 80
82 Control Panels 2 dias Seg 6/7/20 Ter 7/7/20 81
83 CCTV (Floor 3 to Basement -5) 7 dias Qua 8/7/20 Qui 16/7/20 82

Tarefa Resumo do projeto Tarefa Manual Somente início Data limite

Projeto: Cronograma Polana Pla Divisão Tarefa Inativa Somente duração Somente término Andamento
Data: Ter 9/6/20 Marco Marco Inativo Acúmulo de Resumo Manual Tarefas externas Progresso manual

Resumo Resumo Inativo Resumo Manual Marco externo