N°.

Nombre de tarea
1 HOUSE CONSTRUCTION
Start
2 Quantity Crews Performance
3 Prelimary Activities
4 Fireman's Permit
5 Building Permit Aproved
6 Temporary power
7 Temporal de Agua/Water supplies
8 Perimeter Fence
9 Store
10 Cleaning and Leveling Ground
11 Survey
Structures
12 Foundation
13 Excavation 6.41 M3 0+1 2.567 M3/day
14 Set Foundation Steel 0.33662 Ton 1+1 732.06 Ton/day
15 Mix and Pour Foundation concrete 1.6 M3 1+0.5 15 M3/day
16 Blocking Foundation and Fill Block core 11.968 M2 1+1 6.31 M2/day
17 Soil compaction 57.56 M2 0+1 222.8 M2/day
18 Floor
19 Mix and Pouring Floor Concrete 5.756 M3 1+0.5 15 M3/day
30 Roof 96.28 M2 1+1 22.08 M2/day
20 Masonry
21 Blocking Walls 96.82 M2 1+0.5 14.42 M2/day
22 Framing
23 Set steel frames
24 Formwork frames
25 Mix and Pouring Frames Concrete 0.84 m3 1+0.5 15 m3/day
26 Blocks Plastering 243.83 M2 1+0.5 18.5 M2/day
27 Notches Plastering 56.32 ml 1+0.33 19.66 ml/day
28 Electricity /day
29 Plumbing
31 Exteriors and others
32 Parking Slot
33 Slab and Garbage Cage Formwork 3.375 M2 1+0.5 16.54 M2/day
Mix and Pour Basement Slab and Garbage
35 Container 3.33 M3 1+0.5 M3/day
Exterior column
36 Column Formwork 3.48 M2 1+1 15.03 M2/day
37 Set Column Steel 0.00575 Ton 1+1 732.06 Ton/day
38 Mix and Pour Column Concrete 0.29 M3 1+0.5 15 M3/day
39 Finishes
40 Ceramic Tiles 57.56 M2 1+0.33 11.04 M2/day
41 Cealing 46.74 M2 1+1 12.09 M2/day
42 Doors Instalation 5 UND 1 3.15 UND/day
43 Windows Instalation 7 UND 1+0.33 12.62
44 Pintura 487.66 M2 2 48 M2/day
45 End
46
Costo
Calculated Duration materiales Costo MO TOTAL COST

0
0
0
0
0
0
0
0

0
2.5 2.5 110.893 411.41303 522.30603
0.01 1.5 218.803 208.13 426.933
0.11 0.5 93 30.048 123.048
1.9 2 277.87 139.36 417.23
0.26 0.5 115.577 14.84 130.417
0
0.39 0.5 743.75 287.16 1030.91
4.37 4.5 0
0
6.72 7 285.5 491.1 776.6
0

0.06 0.5 0
13.18 13.5 256.8 1145.98 1402.78
2.87 3 0
0
0
0
0
0.21 0.5 0

0.24 0.5 0
0.01 0.5 0
0
0
5.22 5.5 1338.38 446.46 1784.84
3.87 4 223.88 416.26 640.14
1.59 2 410 74.56 484.56
0.56 1 404 49.7944 453.7944
5.08 2 300 500 800
0
Predecesor

the start of the project


the start of the project
the start of the project
the start of the project
the start of the project
the start of the project
the start of the project
after the cleaning is acomplish, the Survey can start

survey
Excavation
Set Foundation steel
Pouring foundation Concrete

Soil Compaction
Predecesors
HOUSE CONSTRUCTION
Start
Prelimary Activities
Fireman's Permit
Building Permit Aproved
Temporary power
Temporal de Agua
Perimeter Fence
Store
Cleaning and Leveling Ground
Survey
Foundation
Excavation
Pour Foundation concrete
Set Foundation Steel
Blocking Foundation and Fill Block core
Floor
Pouring Floor Concrete
Masonry
Blocking Walls
Framing
Formwork frames
Pouring Frames Concrete
Mochetas
Repello
Techo
Estacionamiento
Nombre de tarea
Concrete Slab
Slab and Tinaquera Formwork
Set Slab Steel
Pour Basement Slab
Acabados
Ceramic Tiles
Cealing
Doors Instalation
Windows Instalation
Pintura
Cuadrilla
Albañil
Ayudante 1
Ayudante 2
reforzador
Mozaiquero
Electricista
Plomero
Electricista
Pintor