ODR Docking CB - SPLM, 26-Apr-2019
ODR Docking CB - SPLM, 26-Apr-2019
WORKING PROGRESS
PREPARED BEFORE/AFTER DOCKING
No Activity Start Date Finish Date Progress PIC
1 Mobilization CB. SPLM to Shipyard 22-Apr-19 23-Apr-19 100% SPL
2 Shifting TB. Pelangi, Trans, BMP 02, and CB. SPL Pioneer to clear area Jetty 23-Apr-19 23-Apr-19 100% SPL
3 Unloading Crane Liebheer 23-Apr-19 23-Apr-19 100% SPL
4 Prepared Air Bag for Docking 23-Apr-19 23-Apr-19 100% EMB
5 Docking CB.SPL Mahakam 23-Apr-19 24-Apr-19 100% EMB
6 Undocking CB.SPL Mahakam 27-Apr-19 27-Apr-19 0% EMB
7 Loading Crane Liebherr 27-Apr-19 27-Apr-19 0% SPL
8 Reporting (Docking Report, Antifouling Report) 28-Apr-19 28-Apr-19 0% EMB
REPLATING
1 Replating Bottom and Hull (Based on UT result) 24-Apr-19 26-Apr-19 50% EMB
2 Replating Main Deck (Based on condition) 24-Apr-19 26-Apr-19 100% Decline
MAINTENANCE
1 Blow-Out existing line exhaust AE no.1 and AE no. 2 25-Apr-19 26-Apr-19 100% SPL
2 Shellac / coating alternator AE no. 3 24-Apr-19 26-Apr-19 80% SPL
3 Compression test AE no.1 and AE no. 2 25-Apr-19 25-Apr-19 35% SPL
4 Replace fan galley room 26-Apr-19 26-Apr-19 100% SPL
S-CURVE
S-CRUVE
Dry Docking CB SPL Mahakam
100.0%
90.0%
80.0%
70.0%
60.0%
50.0% Plan
Actual
40.0%
30.0%
20.0%
10.0%
0.0%
22-Apr-19 23-Apr-19 24-Apr-19 25-Apr-19 26-Apr-19 27-Apr-19 28-Apr-19
22-Apr-19 23-Apr-19 24-Apr-19 25-Apr-19 26-Apr-19 27-Apr-19 28-Apr-19
Plan 8.0% 16.0% 31.0% 55.5% 81.0% 94.0% 100.0%
Actual 4.0% 16.0% 27.4% 39.6% 63.9%
TODAY ACTIVITIES
TODAY ACTIVITIES:
TIME (LOCAL : GMT+08:00-17.50)
No Activities
1 Sanblasting bottom, hull and top side hull
2 Painting primer (first layer) bottom
3 Painting siller (second layer)
4 Cleaning strainer sea chest and valves
5 Repair air vent FOT and FWT
6 Repair fairlead and pulley forward
7 Repair vent FOT and FWT , fabricate cover vent
8 Install alternator and alightment to engine
9 Blow-out exhaust line engine no.1
10 Install zinc anode
11 Repair railing on the top deck
12 Install exhaust fan galley room
TOMORROW PLAN:
No Activities
1 Continue sandblasting bottom plate
2 Painting primer (first layer) bottom plate
3 Painting siller (second layer) underwater area
4 Painting top coating (second layer) on hull top side
5 Install checker plate for floor engine room
6 Modify anchor rest for winch no. 3 and no.4
7 Cleaning exhaust line engine
8 Survey class BKI to SPLM
9 Ultrasonic test for Special Survey 1
10 Calibration injector genset no. 1 and no.2
11 Compression test genset no.1 and no. 2
12 Magger test alternator and motor pump
Readiness Material
Status (Delivery Order) Remark
1 Painting for Accomodation Done Owner Supply
2 Checker Plate 7mm & Plate Grating Done Owner Supply
3 Zinc Anode Done Owner Supply
4 Plate profile L 5 x 5 cm Done Owner Supply
5 Plate Grating Done Owner Supply
6 Pipe 1.5" Done Owner Supply
DOCUMENTATION REPORT
Primer coating (first layer) portside Primer coating (first layer) starboardside Cleaning valves seachest
Install zinc anode S-8 Install and alighment alternator to engine Repair and install cover vent tank