Proposal Title : Supply and Installation of Conventional


Lightning Protection System for substation,
generator and workshop building.

Project Name : Vintage Garments Limited

Project Address : East Norshighopur, Buripara,


Ashulia, Dhaka

Proposal Submission : 05/11/2019


Date
Ref: EMK-19-1192/R Date: 05th November, 2019

To,
The Managing Director,
Vintage Garments Limited
East Norshighopur, Buripara, Ashulia, Dhaka

Subject: Proposal for Supply & Installation of Conventional Lightning Protection System
(LPS) for substation, generator and workshop building.

Dear Sir,
Thank you for your kind interest in Emkay Enterprises Ltd. It is our pleasure to submit the
Quotation for Supply and Installation of Conventional LPS System, as per guide of NFPA 780
and ACCORD requirements.

Trust that you will find our offer in line with your requirements. For any further clarification
please let us know.

Sincerely Yours,

For Emkay Enterprises Ltd

Engr. Md. Anisur Rahman


Asst. Manager
Cell : 01766666947

Enclosures:

1. Technical & Financial Proposal


2. Terms & Conditions
Technical & Financial Offer for Supply & Installation of Conventional LPS system
SL
Item Description Qty Unit Price Total Price
No
Air Terminal: Supply of air terminal (Made of solid Copper)
with double base plate, nut-bolt, cable lugs and any others
1 installation accessories. Completed as per design and 58 nos
1,300.00 75,400.00
standard (NFPA- 780,Class I) Air Terminal Height 24" Long
& 9.5 mm dia.
Roof & Cross Run Conductor, Down Conductor (Made of
copper): Supply of Roof & Cross Run Conductor which will
be installed as surface wiring on parapet wall and metal roof.
Down Conductor, which will be installed as down conductor
2 400 mtr
from roof to earth resistivity test point box, using clamp, nut- 400.00 160,000.00
bolt and all necessary installation accessories. Completed as
per design and Class I: 10x3 mm cu strip for Roof and Down
Conductor.
3 Bonding Conductor : Copper 5mm dia solid for bonding 50 mtr
320.00 16,000.00
Earth Test Box with Copper bus Bar (30mmX10mm)
4 12 nos
including nut-bolts, royal bolts, royal plug, washer etc. 2,500.00 30,000.00

Earth Electrode: Supply of Earthing Electrode made of solid


copper size of 12.7 mm diameter, 30' long including 1.5" dia
5 5 nos
G.I. Pipe (10 feet for Each Earthing system at Top side only) 12,000.00 60,000.00
Note: Earth resistance should below 10 ohms.

Supply of Shadel, Socket, Joint Clamp, Joint Socket, MS


6 Sheet, Nut-bolts, Screw, Washer and Others required sundry 1 Lot
100,000.00 100,000.00
materials.
Sub Total= 441,400.00

VAT+AIT (7.5%)= 33,105.00

Total(A)= 474,500.00
Installation, Testing & Commissioning work with as built
7 1 Job 200,000.00 200,000.00
drawing and Test report
Sub Total= 200,000.00

VAT(15%)= 30,000.00

Total(B)= 230,000.00

Grand Total Amount(A+B) = 704,505.00


Summary:

Amount in
SL Scope of Work
BDT
Technical & Financial Offer for Supply & Installation of
A. Conventional LPS system for substation, generator and workshop 704,505.00
building.
Total in BDT 704,505.00
In Words: Seven Lac Four Thousand Five Hundred Five Taka Only

2. Terms & Conditions:

i. Payment Terms:
A. 70% of the total order value will be paid with the work order.
B. Mode of Payment will be PO/DD/account payee cheque in favor of Emkay Enterprises Ltd.
C. 20% Payment should be done at the time of delivery of products at site.
D. Rest 10% after ACCORD Approval.

ii. Offer Validity:

A. Price quoted will remain valid for one (1) month from the offering date.
B. All the prices are including Govt. VAT.

iii. Deliverables:

A. 5-7 days required to start the work from the date of raising invoice. However if delivery is
major then we can may be able to improve on the above.
B. Project will be completed with 15-20 days from the day of starting project.
C. Testing report of Earth Resistance Measurement will be provided after completion of the
installation.
D. Approval from ACCORD.

Note:
i. The above proposed amount is provided only for the turnkey project for one facility
considering all terms & conditions of installations of safety.
ii. Water Supply will be supported by Client.
iii. Power supply will provide by Client.
iv. Civil pit made by client
v. Extra required materials bill paid as per unit price.