EXTENSION / CONSTRUCTION OF MOTHER AND CHILD HEALTH CARE CENTER IN DHQ KILLA SAIFULLAH, BORDERIRNG DISTRICT OF BALOCHISTAN.

ID Task Name Duration Start Finish 2020 Predecessors 2021 2022


May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
1 DHQ KILLA SAIFULLAH, 418 days Mon 6/1/20 Wed 1/5/22
BORDERIRNG DISTRICT OF
BALOCHISTAN
2 Approval Stage 21 days Mon 6/1/20 Mon 6/29/20
3 Bidding Stage 30 days Tue 6/30/20 Mon 8/10/202
4 Bid Evaluation Stage 30 days Tue 8/11/20 Mon 9/21/203
5 Mobilization Stage 30 days Tue 9/22/20 Mon 11/2/204
6 CONSTRUCTION OF LABOUR 277 days Tue 11/3/20 Wed
ROOM 11/24/21
7 Excavation 7 days Tue 11/3/20 Wed 11/11/205
8 Foundation 45 days Thu 11/12/20 Wed 1/13/217
9 Walls 60 days Thu 1/14/21 Wed 4/7/21 8
10 Slage Season 45 days Thu 4/8/21 Wed 6/9/21 9
11 Slab 30 days Thu 6/10/21 Wed 7/21/2110
12 Finishing Works 90 days Thu 7/22/21 Wed 11/24/2111
13 REPAIR RENOVATION OF 277 days Tue 11/3/20 Wed
DHQ KILLA SAIFULLAH 11/24/21
14 Excavation 7 days Tue 11/3/20 Wed 11/11/205
15 Foundation 45 days Thu 11/12/20 Wed 1/13/2114
16 Walls 60 days Thu 1/14/21 Wed 4/7/21 15
17 Slage Season 45 days Thu 4/8/21 Wed 6/9/21 16
18 Slab 30 days Thu 6/10/21 Wed 7/21/2117
19 Finishing Works 90 days Thu 7/22/21 Wed 11/24/2118
20 CONSTRUCTION OF 277 days Tue 11/3/20 Wed
DIALYSES CENTER AT DHQ 11/24/21
KILLA SAFULLAH
21 Excavation 7 days Tue 11/3/20 Wed 11/11/205
22 Foundation 45 days Thu 11/12/20 Wed 1/13/2121
23 Walls 60 days Thu 1/14/21 Wed 4/7/21 22
24 Slage Season 45 days Thu 4/8/21 Wed 6/9/21 23
25 Slab 30 days Thu 6/10/21 Wed 7/21/2124
26 Finishing Works 90 days Thu 7/22/21 Wed 11/24/2125
27 CONSTRUCTION OF 277 days Tue 11/3/20 Wed
INCINERATOR 11/24/21
28 Excavation 7 days Tue 11/3/20 Wed 11/11/205
29 Foundation 45 days Thu 11/12/20 Wed 1/13/2128
30 Walls 60 days Thu 1/14/21 Wed 4/7/21 29
31 Slage Season 45 days Thu 4/8/21 Wed 6/9/21 30
32 Slab 30 days Thu 6/10/21 Wed 7/21/2131
33 Finishing Works 90 days Thu 7/22/21 Wed 11/24/2132
Task Project Summary Manual Task Start-only Deadline

Project: DHQ killa Saifullah Split Inactive Task Duration-only Finish-only Progress
Date: Sat 5/30/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
EXTENSION / CONSTRUCTION OF MOTHER AND CHILD HEALTH CARE CENTER IN DHQ KILLA SAIFULLAH, BORDERIRNG DISTRICT OF BALOCHISTAN.
ID Task Name Duration Start Finish 2020 Predecessors 2021 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
34 CONSTRUCTION OF 120 days Thu 7/22/21 Wed 1/5/22
OVERHEAD WATER TANK
35 Bottom Slab 30 days Thu 7/22/21 Wed 9/1/21 32
36 Walls 30 days Thu 9/2/21 Wed 10/13/2135
37 Slab 30 days Thu 10/14/21 Wed 11/24/2136
38 Finishing Works 30 days Thu 11/25/21 Wed 1/5/22 37

Task Project Summary Manual Task Start-only Deadline

Project: DHQ killa Saifullah Split Inactive Task Duration-only Finish-only Progress
Date: Sat 5/30/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone