Project: DHQ killa Saifullah Split Inactive Task Duration-only Finish-only Progress
Date: Sat 5/30/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Page 1
EXTENSION / CONSTRUCTION OF MOTHER AND CHILD HEALTH CARE CENTER IN DHQ KILLA SAIFULLAH, BORDERIRNG DISTRICT OF BALOCHISTAN.
ID Task Name Duration Start Finish 2020 Predecessors 2021 2022
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
34 CONSTRUCTION OF 120 days Thu 7/22/21 Wed 1/5/22
OVERHEAD WATER TANK
35 Bottom Slab 30 days Thu 7/22/21 Wed 9/1/21 32
36 Walls 30 days Thu 9/2/21 Wed 10/13/2135
37 Slab 30 days Thu 10/14/21 Wed 11/24/2136
38 Finishing Works 30 days Thu 11/25/21 Wed 1/5/22 37