1. SV = (100,000 – 200,000) = -$100,000. The project is behind schedule since it is negative.

2. CV = (100000 – 300000) = -$200000. This project is over the control budget.


3. SPI = (100000/200000) = 0.5. We are behind schedule.
4. CPI = (100000/300000) = 0.33. We are control budget.
5. Project % Complete = (100000 / 400000) * 100 = 25%
6. EAC = $1200000
7. TCPI = 3 or TCPI = 0.33
8. TCPI = 0.11
9. Performance
10. Calculation