Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Figure shows the activity and time frame used in completing the specific activities.

Conceptualizing and gathering information was done during the third week, fourth week of

November and first week of December. Analyzing and Designing of the project took place on the

second week up to fourth week of December. Canvassing of supplies and materials and

purchasing was done during the last week of December until the first week of January.

Construction of project was done during the second week of January until the first week of

February. Testing, calibrating and revision was done during the second and third week of

February. Evaluation of the prototype was done during the last week of February. The project

finished from the first two weeks of March.

You might also like