Estimate For Bamboo Structure For Tapovan at The Lily Pool
Estimate For Bamboo Structure For Tapovan at The Lily Pool
Sarobar, Kolkata
plastering the back ferroceme installing the wind 1 day, 2 installing the 3 days,
wall on 2 sides with nt 1 day, 2 ties people front gable 2
lime plaster in 3 people wall people
coats, including lime lime 3 installing the back 2 days,
punning on top, on a days, 2 wall 2
ferrocement people people
substrate
making the IPS 1 day, 4 jointing the roof 2 days,
flooring people rafters with 4
waterproof filler people
material
keeping the IPS 1 day, 1 laying the top ridge 2 days, applying the 2 days,
flooring under water people steel sheet and side 2 P.U. coating 2
for 15 days coverings people people
maintaining the 4 days, 1
water level every people
alternate day for 15
days and cleaning
the IPS flooring
Total: 23 working days,
12 days of masonry/plaster works, 29 man-days of masonry/plaster works
21 days of bamboo works, 84 man-days of bamboo works
For ECCD-India, Pulaha Dasgupta and Laurent Fournier, 20th August 2010