3500 ENCORE RACK CONFIGURATION

Client / End-user: Pakistan Oil Fields Limited


BN Project No.: 5BH-500000214 Document No. : CFG-BNX-500000214
Project: Upgrade of Meyal LPG 3300 Vibration Monitoring
Revision : A
system

PROJECT

Upgrade of Meyal LPG 3300 Vibration Monitoring


System

3500 ENCORE RACK CONFIGURATION

POL P.O. No.: PSO-0447/MEYAL

5BH-500000214

Rev Date Description Prepared by Verified by Approved by


A 11-03-2013 Issued for Approval A.Hameed R.Gruta J.Al-Shawa

File Name: CFG-BNX-500000214 Page: 1 of 3


3500 ENCORE RACK CONFIGURATION

Client / End-user: Pakistan Oil Fields Limited


BN Project No.: 5BH-500000214 Document No. : CFG-BNX-500000214
Project: Upgrade of Meyal LPG 3300 Vibration Monitoring
Revision : A
system

DOCUMENT REVISION HISTORY

Rev Date Revision Details / Remarks


A 11-03-2013 Issued for Approval

File Name: CFG-BNX-500000214 Page: 2 of 3


3500 ENCORE RACK CONFIGURATION

Client / End-user: Pakistan Oil Fields Limited


BN Project No.: 5BH-500000214 Document No. : CFG-BNX-500000214
Project: Upgrade of Meyal LPG 3300 Vibration Monitoring
Revision : A
system

Attachments

- 3500 Encore Rack Configuration

File Name: CFG-BNX-500000214 Page: 3 of 3


GE Energy OC - Bently Nevada
Bahrain Rack 1 K-103A/B

Barriers
Physical Address Corner Frequency Trip Set Points Latching Bently Nevada Rack
Monitor Type Channel Type Transducer Type Units Xdcr Orient. or Thrust Multipl Additional Informations
Indicating Hi Pass Lo Pass

Channel
No. Machine Name Direction or Associated Keyphasor y Pre-Alarm / Alert Trip Alarm / Danger None, MTL external, Reading Reading Reading Reading Relay Comments
Range Filter Filter

Slot
Tag Name Keyphasor Polarity OK Alert Danger Galvanic Isolator,
e.g. mils p-p, g 30 - 30000 Delay Delay Internal 100% > Alert > Danger
e.g. 3500/40 e.g. X-Y, Seismic e.g. 3300XL-8mm, 330400
pk, um
3 - 3000 Hz
Hz
e.g. 2X Lo Hi Lo Lo Hi Hi Not OK Action Rack ID, Rack Address, Scale Factor, Relay Logic
Time Time (Full Scale) Setpoint Setpoint
0U 1 15E
1 Rack 1 2 23E P[__] F[__] Rack Address: 1, IP Address: ..., IP Address: ...

2 1 Radial Vibration 7200-5mm Proximitor 0 - 100 µm pp None 30 3s 40 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 200 mV/mil
3 42E
3 2 Radial Vibration 7200-5mm Proximitor 0 - 100 µm pp None 30 3s 40 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 200 mV/mil

4 1 Radial Vibration 7200-5mm Proximitor 0 - 100 µm pp None 30 3s 40 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 200 mV/mil
4 42E
5 2 Radial Vibration 7200-5mm Proximitor 0 - 100 µm pp None 30 3s 40 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 200 mV/mil

6 1 Thrust Position 7200-5mm Proximitor 0.5 / 0.5 mm 0.4 3s 0.5 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] SF: 200 mV/mil; GAP: -9.75
5 42E
7 2

8 1 Thrust Position 7200-5mm Proximitor 0.5 / 0.5 mm 0.4 3s 0.5 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] SF: 200 mV/mil; GAP: -9.75
6 42E
9 2
7 Blank

10 1 Velocity 2 9200 2-wire Seismoprobe 0 - 20 mm/s pk 0° No ne NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 500 mV/in/s
8 42E
11 2 Velocity 2 9200 2-wire Seismoprobe 0 - 100 µm pp 0° Non e 2X 33 3s 45 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 500 mV/in/s

12 1 Velocity 2 9200 2-wire Seismoprobe 0 - 20 mm/s pk 0° No ne NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 500 mV/in/s
9 42E
13 2 Velocity 2 9200 2-wire Seismoprobe 0 - 100 µm pp 0° Non e 2X 33 3s 45 1000 ms NonL NonL L External P[__] F[__] P[__] F[__] P[__] F[__] P[__] F[__] SF: 500 mV/in/s

10 Blank
11 Blank

12 Blank

GE Energy OC - Bently Nevada CUSTOMER: END USER: NOTE:


Project:
(Bahrain)
Customer to provide missing information
Document #:

Revision number: Page number:

Date:

GE Energy OC - Bently Nevada


Created by: Ali Mohamed - 105038550
Bahrain