The project status report provides an update on the relocation and improvement of the MCOM garbage area. It states that as of February 20, 2020, 50.86% of the project has been completed, including site preparation, laying of CHB blocks, and plastering works. Remaining tasks include continuing plastering, constructing the roof and door. The engineering department is awaiting additional requested materials. The budget for the project is PHP 15,100 and it is targeted to be completed by February 29, 2020.
The project status report provides an update on the relocation and improvement of the MCOM garbage area. It states that as of February 20, 2020, 50.86% of the project has been completed, including site preparation, laying of CHB blocks, and plastering works. Remaining tasks include continuing plastering, constructing the roof and door. The engineering department is awaiting additional requested materials. The budget for the project is PHP 15,100 and it is targeted to be completed by February 29, 2020.
The project status report provides an update on the relocation and improvement of the MCOM garbage area. It states that as of February 20, 2020, 50.86% of the project has been completed, including site preparation, laying of CHB blocks, and plastering works. Remaining tasks include continuing plastering, constructing the roof and door. The engineering department is awaiting additional requested materials. The budget for the project is PHP 15,100 and it is targeted to be completed by February 29, 2020.
SUBJECT : ED Report No. : ER-KM20-003 OF MCOM GARBAGE AREA
MCOM BLDG. B, COMMERCIAL
LOCATION : Date : February 20, 2020 AREA, SBGP I
PROJECT DETAILS:
TO BE DONE BY: In-House MCOM Maintenance Personnel
DATE STARTED: February 10, 2020 TARGET COMPLETION: February 29, 2020 PROGRESS ACHIEVED: 50.86 % as February 20, 2020 APPROVED BUDGET: Php 15,100.00
WORKS COMPLETED:
• Site preparation and layouting of garbage area
• Laying of CHB • Plastering works • Layouting of Door
REMAINING TASKS:
• Continuation of plastering works
• Construction of roof • Construction of door and lock mechanism.
Note: ED is awaiting for delivery of requested additional materials.
Prepared by: Checked and Reviewed by:
Kenneth G. Molina Engr. Allan B. Mendoza
Jr. Electro-Mechanical Engineer Division Chief, PM&M
Noted by:
Engr. Eduardo B. Reyes, Jr.
Manager, ED Related Photos: SBDMC, INC. ENGINEERING DEPARTMENT
As of: Thursday, February 20, 2020
Project Start: Monday, February 10, 2020 Target Date of Saturday, February 22, 2020 Completion:
STATEMENT OF WORK ACCOMPLISHMENT
RELOCATION AND IMPROVEMENT OF MCOM GARBAGE AREA ACCOMPLISHMENT PERCENTAGE PERCENTAGE PERCENTAGE BOQ To Date Actual Planned of Slippage NO. DESCRIPTION Wt. % QTY UNIT UNIT COST TOTAL QTY % AMOUNT Wt. % Wt. % Wt. % A. Civil works Layouting of CHB 4" 36.42% 1.00 lot 5,500.00 5,500.00 1.00 100.00 5,500.00 36.42% 36.42% 0.00% Plastering works 25.56% 1.00 lot 3,860.00 3,860.00 0.50 50.00 1,930.00 12.78% 25.56% -12.78% Construction of Roof 21.46% 1.00 lot 3,240.00 3,240.00 0.00 0.00 0.00 0.00% 16.09% -16.09% Construction of Door and lock 6.62% 1.00 lot 1,000.00 1,000.00 0.25 25.00 250.00 1.66% 4.97% -3.31% Welding Works 9.93% 1.00 lot 1,500.00 1,500.00 0.25 25.00 375.00 2.48% 7.45% -4.97% SUB-TOTAL 100.00% 15,100.00 7,680.00 50.86% 90.50% -37.15% TOTAL 15,100.00 50.86% 90.50% -37.15% GRAND TOTAL COST (PhP) 15,100.00
Note: 1. (-) means delayed, (+) means advanced
2. ED waiting for availability of requested additional materials.
PREPARED BY: CHECKED AND REVIEWED BY: NOTED BY:
KENNETH G. MOLINA ENGR. ALLAN B. MENDOZA ENGR. EDUARDO REYES, JR.