Professional Documents
Culture Documents
Tunnelling Methods - 2010-HO
Tunnelling Methods - 2010-HO
Tunnelling Methods - 2010-HO
Six lectures:
• Methods – soft ground and rock
• Aspects of tunnel lining design
• Assessing stability and face pressures
• Settlement prediction
• Building damage assessment
• Site investigation & Instrumentation for
tunnels
GENERAL
1
MRT Lines generally under roads. Current lines connect
the satellite towns with the CBD/Orchard road
FUNCTION
• Trunk sewers – connect population
centres with treatment works or deep
collector sewers
• MRT tunnels – connect population
centres
• Deep sewers – feed to treatment plants
• Road Tunnels – connect population
centres
• Storage caverns – location important,
but cost also major issue
2
FUNCTION & SIZE
• Trunk sewers - typically 3m diameter,
6m to 12m depth
• Subway tunnels – typically 6m
diameter,15m to 30m depth
• Deep sewers – 4m to 7.5m diameter –
30 to 50m depth
• Road Tunnels – typically 10 to 15m
diameter
• Storage caverns – can be huge & deep
ALIGNMENT CONSTRAINTS
• Trunk sewers – gentle vertical gradient
(gravity flow) – tight curves (50m radius)
• MRT tunnels – up to 3% vertical
gradient, curve radius >200m
• Deep sewers – gentle vertical gradient
(gravity flow)
• Road Tunnels – up to 8% vertical
gradient
• Storage Caverns – depends on usage
3
OTHER CONSTRAINTS
• Avoid other underground infrastructure,
building foundations, basements
• Availability of land for shafts & work
sites
• Trying to avoid going under buildings –
due to risk of damage
4
IMPACT OF ALIGNMENT ON
TUNNELLING METHODS
• The alignment of the tunnel is affected by a
number of factors that result from the end use
of the tunnel and existing land use and
infrastructure. For many urban tunnels, these
factors control the vertical and horizontal
alignment, and therefore the ground
encountered during tunnelling. There is often
limited scope to alter the alignment to tunnel
is better ground.
• Storage caverns are a major exception, as
economy of construction is often the
governing factor.
TUNNELLING METHODS
5
CONTENT
• Ground behaviour
• Excavation methods
• Methods for Ground Support
• Singapore experience
GROUND BEHAVIOUR
6
TUNNELMAN’S CLASSIFICATION –
SOFT GROUND
Squeezing Plastic squeeze into tunnel. Soft to
medium clays, Stability Number 5 to 9
Flowing Soil and water flows into the tunnel.
Silts and sands below the water table
Running Dry granular materials run back to angle
of repose. Sands above the water table
Ravelling Chunks of material progressively drop
out. Fractured materials, lightly
cemented sands.
Swelling Ground absorbs water, slowly swelling
into tunnel. Swelling clays, desiccated
soils.
Firm Ground has sufficient ‘stand-up time’ to
allow heading to be advanced, lining
installed
7
MARINE CLAY - BASE HEAVE FAILURE,
13m DEEP EXCAVATION, JGP BASE SLAB
8
OLD ALLUVIUM - FLOWING
EVEN WITH DEWATERING
9
FIRM BEHAVIOUR - HARD CLAY OF THE FORT
CANNING BOULDER BED
10
RAVELLING IN FAULT ZONE IN THE
JURONG FORMATION
11
STABLE ROCK OF THE JURONG
FORMATION
12
STABLE ROCK OF THE BUKIT TIMAH
GRANITE
13
WEATHERED GRANITE
14
EXCAVATION METHODS
15
BEAUMONT TUNNELLING
MACHINE, CHANNEL TUNNEL,
1880’S, SOFT ROCK
16
HARD ROCK TUNNEL BORING MACHINE
Ventilation
Belt conveyor
for spoil
17
HAND MINING
18
SCL – BIGGER TUNNELS, BIGGER
EXCAVATORS
19
DIGGER SHIELD, CITY HALL TO BUGIS, 1986
Extendable hoods
Face Grids
Extendable deck
Digger arm
20
EPB SHIELD, CLARKE QUAY, 1999
21
SUPPORTING THE GROUND
• ‘Good rock’ – may need little or no
support
• Stable ground – needs long term
support
• Ravelling ground – needs support
quickly after excavation
• Squeezing/flowing/running ground –
needs continuous support during
excavation
BOLTS AND
ANCHORS
Rock, stiff soil
22
Sprayed concrete
-Stable or
stabilised soil
Stable or Slow ravelling rock
1 Cutterhead
2 Cutterhead Support
3 Ring Erektor
4 Anchor Drilling Devices
5 Wire Mesh Erector (Net Support)
5
2
1 4
3
23
SUPPORTING THE GROUND
DURING TUNNELLING
Soft and mixed conditions
24
Sprayed concrete lining – suitable for stable (or
stabilised) ground
BRUNEL TUNNEL
First shield driven tunnel
25
BRUNEL SHIELD, RIVER
THAMES, 1830’S
Face Grids
Extendable deck
Digger arm
Shield skin provides temporary support, except at
face. Used with compressed air in soft clay, sand
below the water table
26
Ravelling ground – can be supported in a digger
shield, but only with skilled miners and slow
progress
27
Face Pressure Control on EPB, Slurry and
Mixshield
Bentonite Bentonite
Soil suspension suspension
Air bubble
Hydraulic Hydraulic
transport cycle transport cycle
Screw conveyor
1. Tunnel face
1 2. Cutting wheel
8
3. Excavation
chamber
4. Pressure
4
7 bulkhead
2
6
5. Thrust cylinders
3
6. Screw conveyor
5
7. Segment erector
8. Segmental Lining
28
EPB Shield - Face Pressure Control
Increase / Lowering of Shield Advance Rate
Increase / Lowering of
Screw Discharge Rate
Water Earth
Pressure
SCREW CONVEYOR
Plenum Chamber
– face pressure
Discharge – at atmospheric
pressure
29
EBP-Shield Taipai (Ø 6.26 m) , belt conveyor outlet
HERRENKNECHT
30
LIMITS ON EPB SHIELD
• Minimum size (1200mm) to
accommodate screw
• Coarse granular soil - difficult to turn
into suitable plastic spoil. Also mixed
face of rock and permeable soil
Körnungslinie
Hydrometer Sieve
Clay Silt Sand Gravel
Fine- Medium- Coarse- Fine- Medium- Coarse- Fine- Medium- Coarse-
Percent coarser by weight d in %
100 0
Percent finer by weight d in %
90 10
80 20
70 30
60 EPB Foam
40
50 50
40 60
30 70
20 80
Slurry 90
10
0 100
0,001 0,002 0,006 0,02 0,06 0,2 0,6 2,0 6,0 20,0 60,0
Sieve size d in mm
31
without foam treatment with foam treatment
HERRENKNECHT
Bentonite
Water
Polymers
Foam
32
Poor EPB material. Mixture of rock chips and
granular soil. Difficult to condition.
HERRENKNECHT
33
Air lock
SLURRY SHIELDS
• Slurry is used to provide both support to
the face and to transport the excavated
ground
• Slurry may be formed by mixing water
with bentonite, polymer or the ground (if
enough clay)
• Bentonite (or polymer) properties
selected depending on the ground and
the shield size
34
SECTION THROUGH AVN D-SERIES
1 Cutting wheel 6 Air pressure cushion 11 Slurry discharge line 16 Hydraulic oil tank
2 Excavation chamber 7 Motor gearbox assembly 12 Pressure bulkhead 17 Airlock bulkhead
3 Crusher chamber 8 Bentonite 13 Steering cylinder 18 Airlock
4 Submerged wall 9 Bentonite level indicator 14 Bypass assembly 19 Air pressure regulation equipment
5 Main bearing 10 Face access hatch 15 Drive motor 20 Electric cabinet
HERRENKNECHT
Mixshield – Layout
4
1. Submerged
Wall
2. Excavation
Chamber
3. Regulation
5 Chamber
1
3 4. Air Cushion
5. Pressure
2
Bulkhead
Page 70
35
Face Pressure Control by Air Bubble – Used for
many European designed slurry shields
Slurry behaviour
∆P
slurry soil slurry soil
36
TBM Technique – Filter Cake at Tunnel Face
slurry soil
Filter cake
formed
Page 73
4% loose bedding
6% compact bedding
37
Stone Crusher
Can be incorporated into slurry shields, but not into EPB machines
38
FLOW DIAGRAM OF SLURRY TREATMENT
39
CONVERTIBLE EPB / SLURRY MACHINE
Slurry Mode
HERRENKNECHT
EPB Mode
HERRENKNECHT
40
PERMANENT LININGS FOR
SOFT GROUND
41
CAST INSITU CONCRETE
CONCRETE SEGMENTS
42
TAIL VOID GROUTING
• Typical diameter of shield for MRT
construction:6.46 to 6.55m
• Typical outside dimension of ring: 6.3m
• Average gap: 80 to 125mm all around
ring
• Needs to be filled to minimise
settlement and ensure even ground
pressure on ring. Properties of grout
important to function of ring – will deal
with in next lecture
43
SHIELD LAUNCH
Difference in diameter
between shield & lining
Conventional grouting
– through lining. Only
suitable in stable
ground
44
radial gap to be grouted
Simultaneous
grouting of the tail
void
Shove rams
typically 20 to 30
100t to 200t rams
Grout pipes
Wire brush
tail seals
45
Grout
Concrete segment
CONCRETE SEGMENT,
GROUT, GROUND
46
USE OF RIBS AND LAGGING IN
SINGAPORE
• Exploratory adits under Bukit Timah canal
• Exploratory adits, tunnelling Clarke Quay to
Dhoby Ghaut
• Some crosspassages
47
USE OF SCL IN SINGAPORE
FORT CANNING TUNNEL
Short tunnel (about 240m)
Stable ground (some
treatment)
Large size (15m diameter)
Non-circular cross-section
CROSSPASSAGES
Short tunnel (6m to 40m)
Stable ground (some
treated by grouting or dewatering)
Non-circular cross-section
48
USE OF EPBS IN SINGAPORE
• Ulu Pandan sewer outfall - 3.754m machine, let 1983
• Lavender to Bugis, two 5.93m machines, let 1986
• North East Line, 14 No approx. 6.5m machines, let
1997
• Changi Line, two 6.13m machines, let 1998
• DTSS, eight machines of varying diameter, 2000-
2005
• Cable tunnel
• Circle line (part)
• DownTown Line 1
49
USE OF SLURRY SHIELDS
IN SINGAPORE
• Extensively used for pipe jacking, typical
diameter up to 3m
• Used for several sections of the Circle line
ADVANTAGES OF SLURRY
SHIELDS IN SINGAPORE
• Better ground control in mixed faces of
rock and granular soil
50
DISADVANTAGES OF SLURRY
SHIELDS
• Cost of slurry treatment plant
• Slower maximum rates of tunnelling than EPB
shields
• Issues with disposal of slurry
• Noise from treatment plant in urban
environment (mitigation measures possible)
• Some difficulties handling completely
weathered mudstone due to high clay content
51